Question

In: Operations Management

Dumfries Industries is generating a materials requirement plan for the next six weeks. Here is its...

Dumfries Industries is generating a materials requirement plan for the next six weeks. Here is its most current information:

Master Production Schedule

Week

1

2

3

4

5

6

Item A

10

0

20

20

10

10

Other information

Item

Item’s Parent

Lead time

Lot size

Current inventory

A

None

1 week

LFL

20

B

A

1 week

20

20

C

B

1 week

50

20

How many levels does a product structure for Dumfries item A have?

Using MRP methodology, how much of Parts A, B, and C should be ordered, and when should they be ordered?

Which item will experience the highest average inventory, following this plan?

Consider the following three jobs: Job Alpha requires two weeks of work and is due in four weeks. Job Beta requires three weeks of work and is due in five weeks. Job Carlos requires one week of work and is due in three weeks. If these jobs are completed in alphabetical order, how late will Job Beta be?

Suppose you have three jobs waiting to be completed, and you must determine the sequence in which these jobs should be worked on. You calculated the critical ratio for each of the jobs and the results were that Job A has a critical ratio of 1.27, Job B has a critical ratio of -0.89, and Job C has a critical ratio of 0.15. Which of these jobs is already late? Why?

Solutions

Expert Solution

(1) MRP Problem of Dumfries Industries.

MPS for End-Item A:

Week number

0

1

2

3

4

5

6

Quantity

0

10

0

20

20

10

10

Item A

OH =20

LT=1

SS=0

Q=LFL

Gross reqmts.

0

10

0

20

20

10

10

Scheduled receipts

0

0

0

0

0

0

0

Projected on hand

20

20

10

10

0

0

0

Net reqmts.

0

0

0

10

20

10

10

Planned-order receipts

0

0

0

10

20

10

10

Planned-order releases

0

0

10

20

10

10

0

Item B

OH =20

LT=1

SS=0

Q=20

Gross reqmts.

0

0

10

20

10

10

0

Scheduled receipts

0

0

0

0

0

0

0

Projected on hand

20

20

20

10

10

0

10

Net reqmts.

0

0

0

10

0

10

0

Planned-order receipts

0

0

0

20

0

20

0

Planned-order releases

0

0

20

0

20

0

0

Item C

OH =20

LT=1

SS=0

Q=50

Gross reqmts.

0

0

20

0

20

0

0

Scheduled receipts

0

0

0

0

0

0

0

Projected on hand

20

20

20

0

0

30

30

Net reqmts.

0

0

0

0

20

0

0

Planned-order receipts

0

0

0

0

50

0

0

Planned-order releases

0

0

0

50

0

0

0

Formula:

Net requirements = Gross requirements – On hand inventory – Scheduled receipts.

Product Structure for Dumfries Item A has three levels with Item A being at Level 0.

The number of units of Parts A, B and C that should be ordered at particular points of time is given in the preceding MRP Schedule.

Item C will experience the highest average inventory as per the given plan.

(2) Scheduling Problem: Jobs Alpha, Beta, Carlos.

Job Sequence

Processing Time

(in weeks)

Due Date

(in weeks)

Flow Time

(in weeks)

Days Tardy = Flow Time - Due Date

(in weeks) (0 if negative)

Alpha

2

4

0 + 2 = 2

0

Beta

3

5

2 + 3 = 5

0

Carlos

1

3

5 + 1 = 6

3

     There will be no delay for Job Beta as its tardiness is zero.

(3) Critical Ratio Problem.

Job B and Job C are already late as their Critical Ratios are less than 1, with Job B being most late (having lowest value of Critical Ratio).

The Product Tree Structure is given below:


Related Solutions

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 92 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 35 40 17 25 75 85 20 60 200 87 Use the least total cost and the least unit cost lot-sizing methods to determine...
The Chewy Candy Company would like to determine an aggregate production plan for the next six...
The Chewy Candy Company would like to determine an aggregate production plan for the next six months. The company makes many different types of candy but feels it can plan its total production in pounds provided that the mix of candy sold does not change too drastically. At the present time, the Chewy Company has 70 workers and 9000 pounds of candy in inventory. Each worker can produce 100 pounds of candy a month and is paid $19 an hour...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 170 units per month (Cost per Unit = $40 ). Overtime is limited to a maximum of 20 units per month (Cost per Unit =$60). Units purchased from the subcontractor (Cost per Unit = $72 ) cannot exceed 30 per month and the total purchases from the subcontractor over the 6 month period...
Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that...
Aggregate Planning Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit = $20 ). Overtime is limited to a maximum of 30 units per month (Cost per Unit =$30). Units purchased from the subcontractor (Cost per Unit = $26 ) cannot exceed 40 per month and the total purchases from the subcontractor over the 6...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 150 units per month. Overtime capacity is 20 units per month. Overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory...
A company is planning its production schedule over the next six months (it is currently the...
A company is planning its production schedule over the next six months (it is currently the end of month 2). The demand (in units) for its product over that timescale is as shown below: Month 3 4 5 6 7 8 Demand 5000 6000 6500 7000 8000 9500 The company currently has in stock: 1000 units which were produced in month 2; 2000 units which were produced in month 1; 500 units which were produced in month 0. The company...
Jim’s Donuts is developing its production and raw materials budget for the next 3 days. The...
Jim’s Donuts is developing its production and raw materials budget for the next 3 days. The company’s management projects sales of 600 batches of donuts on Monday; 500 batches on Tuesday; 700 on Wednesday and 900 on Thursday. Jim plans to have 10% of the donuts sold the next day already made the previous day (in ending Finished Goods Inventory). Jim also has 20% of the raw materials of sugar and flour on hand at the beginning of the day...
The PROCOM Corporation is planning its financing for the next six months. PROCOM makes one item,...
The PROCOM Corporation is planning its financing for the next six months. PROCOM makes one item, which it sells through the retail shop in the front of the factory. The planning process was started with profit-and loss computations. Profit is revenue less expenses and revenue is quantity times the unit price. Expenses are made up fixed costs and variable costs. Fixed costs include: rent, salaries, and utilities. Variable costs depend directly on the quantity. These costs are materials and labor....
Clayton Industries is planning its operations for next year. Ronnie Clayton, the CEO, wants you to...
Clayton Industries is planning its operations for next year. Ronnie Clayton, the CEO, wants you to forecast the firm's additional funds needed (AFN). Data for use in your forecast are shown below. Based on the AFN equation, what is the AFN for the coming year? Dollars are in millions. Last year's sales = S0 $350 Last yr's accounts payable $40 Sales growth rate = g 30% Last yr's notes payable $50 Last year's total assets = A0* $360 Last yr's...
The Jumbo Jamboree Corp. plans to close its business over the next five years. They plan,...
The Jumbo Jamboree Corp. plans to close its business over the next five years. They plan, however, to maintain their annual dividends to their loyal shareholders. They plan to play the coming year’s dividend of $2.50, and reduce the dividend to $2.00 for the second year, $1.50 for the third year, $1.00 for the fourth year, and $.50 for the fifth year. The expected market selling price of the stock at the end of the fifth year is expected to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT