Question

In: Finance

A firm has a proposed 5-year project. If accepted today (t=0), the project is expected to...

A firm has a proposed 5-year project. If accepted today (t=0), the project is expected to generate positive net cash flows for each of the following five years(t=1 through t=5). A new machine will be put in service, and to implement this project, an old machine will be sold. Note the following items. The new machine costs $1,000,000. Shipping and installation will cost an additional $500,000. Thus the Installed Cost is $1,500,000.This new machine will be sold five years from today when this project is completed. We believe that it can be sold for $100,000 in five years. If this project is accepted, then an old, fully depreciated, machine will be replaced. The old machine can be sold for $50,000 today. The Installed Cost of this new asset will be depreciated using the IRS 5-year MACRS schedule: year 1, 20%; year 2, 32%; year 3, 19.2%; year 4, 11.52%; year5, 11.52%; and year 6, 5.76%. Note that these yearly amounts sum to 100%. The project will increase revenues and operating expenses (before depreciation and amortization) by $800,000 and $300,000 per year, respectively, for each of the following five years (t=1 to t=5).

An initial increase in Net Working Capital of $50,000 is required today and this amount will be recovered in 5 years when the project is terminated. No other changes in NWC will be required during the project’s life. The cost of capital of the project is r=11%. The corporate income tax rate is 40%.

You are required to determine the following:

a) Compute the relevant cash flows

b) Compute the NPV, IRR , Payback period and profitability index to decide whether a firm

should start this project or not.

b) Compute the NPV, IRR , Payback period and profitability index to decide whether a firm

should start this project or not.

Solutions

Expert Solution

Cash outflow in year 0 = cost of new machine - sale of old machine + investment in NWC

Operating cash flow (OCF) each year = income after tax + depreciation

profit on sale of machine at end of year 5 = sale price - book value

book value = original cost - accumulated depreciation

after-tax salvage value = salvage value - tax on profit on sale of machine   

NPV and IRR are calculated using NPV and IRR functions in Excel

Payback period is the time taken for the cumulative cash flows to equal zero

Payback period = 3 + (cash flow required in year 4 for cumulative cash flows to equal zero / year 4 cash flow) = 3 + ($172,800 / $369,120) = 3.47 years

NPV is $129,282

IRR is 14.35%


Related Solutions

A company is evaluating a project that would require a $5 million investment today (t = 0).
Using Excel (if applicable),A company is evaluating a project that would require a $5 million investment today (t = 0). The after-tax cash flows would depend on whether a new property tax is imposed. There is a 75% chance that the tax will pass and 25% chance that it won't. If the tax passes, the project will produce after-tax cash flows of $1,200,000 at the end of each of the next 5 years. If the tax doesn't pass, the after-tax...
firm is considering a project with the following expected cash flows: Year Cash Flow 0 -P350...
firm is considering a project with the following expected cash flows: Year Cash Flow 0 -P350 million 1 100 million 2 185 million 3 112.5 million 4 350 million The project’s WACC is 10 percent. What is the project’s discounted payback? a. 3.15 years b. 4.09 years c. 1.62 years d. 3.09 years The lolo Corporation has been presented with an investment opportunity that will yield end-of-year cash flows of $30,000 per year in Years 1 through 4, $35,000 per...
Today is T=0. A company paid a dividend of $2.40 yesterday. Dividends are expected to grow...
Today is T=0. A company paid a dividend of $2.40 yesterday. Dividends are expected to grow at a rate of 10% for three years, 8% for one year and then at a rate of 6%, forever. The required return is 13% and is never expected to change. Estimate the equilibrium price of a share of stock at T=0.
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0...
*Two part question A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000 2 1,000 3 1,000 4 2,000 5 2,000 Assuming an interest rate of 10%, the project's simple payback period is most nearly _________. A. 2 years B. 4 years C. 6 years D. 5 years E. 7 years Using the information from the problem above and linear interpolation, the project's discounted payback period is most nearly ___________. A. 3.62 years B....
In the Chicago mayor's race, candidate A proposes a project that will cost $200,000 today (t=0),...
In the Chicago mayor's race, candidate A proposes a project that will cost $200,000 today (t=0), $100,000 next year (t=1) and $15,000 to destroy it after ten years of operation (t=12) when the project is discontinued. Once finished in three years (t=3), it will generate a flow of revenue of $40,000 per year until it is discontinued in (t=12) - ie in t=12 the project generates that flow of revenue too. 1. Set the discount rate as r and write...
Firm C is considering a project with an up-front cost at t = 0 of $1500....
Firm C is considering a project with an up-front cost at t = 0 of $1500. (All dollars in this problem are in thousands.) The project’s subsequent cash flows are critically dependent on whether a competitor’s product is approved by the Food and Drug Administration (FDA). If the FDA rejects the competitive product, C’s product will have high sales and cash flows, but if the competitive product is approved, that will negatively impact company C. There is a 75% chance...
A firm is considering a project that requires a time t=0 cash outlay of $100,000 for...
A firm is considering a project that requires a time t=0 cash outlay of $100,000 for a piece of equipment. The firm will depreciate this equipment to zero via straight line depreciation over an eight year economic life. The project will require the purchase of an additional $8,000 of inventory at time t=0. The inventory purchase will result in an account payable of $3,500 at time t=0. The firm's tax rate is 40%. What is the net cash flow at...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $29,000, and its expected cash flows would be $14,900 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,500, and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT