In: Finance
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:
0 | 1 | 2 | 3 | 4 |
Project S | -$1,000 | $873.06 | $250 | $10 | $10 |
Project L | -$1,000 | $0 | $250 | $420 | $822.83 |
The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
_______ %
1. use NPV function in EXCEL to find the NPV of two projects.
=NPV(rate,Year1 to Year5 cashflows)-Year0 cashflow
NPV,Project S=NPV(16%,Year1 to Year5 cashflows)-16000=$3645.76
NPV,Project L=NPV(16%,Year1 to Year5 cashflows)-40500=-$881.05
WACC | 16.00% | |
Project S | Project L | |
Year0 | -16000 | -40500 |
Year1 | 6000 | 12100 |
Year2 | 6000 | 12100 |
Year3 | 6000 | 12100 |
Year4 | 6000 | 12100 |
Year5 | 6000 | 12100 |
NPV | 3645.76 | -881.05 |
Option d is correct
NPV of Project S>NPV of project L
2. Use IRR function in EXCEL to find the IRR
=IRR(Year0 to Year4 cashflows)
Project S,IRR=IRR(Year0 to Year4 cashflows)=11.3%
Project L,IRR=IRR(Year0 to Year4 cashflows)=12.7%
Project S | Project L | |
Year0 | -1000 | -1000 |
Year1 | 873.06 | 0 |
Year2 | 250 | 250 |
Year3 | 10 | 420 |
Year4 | 10 | 822.83 |
IRR | 11.3% | 12.7% |
Project L has better IRR because of higher than Project S.