Question

In: Finance

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,500, and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend?

Select the correct answer.

a. Project S, since the NPVS > NPVL.
b. Both Projects S and L, since both projects have IRR's > 0.
c. Neither Project S nor L, since each project's NPV < 0.
d. Project L, since the NPVL > NPVS.
e. Both Projects S and L, since both projects have NPV's > 0.

Solutions

Expert Solution

NPV of Project S

NPV :
NPV = PV of Cash Inflows - PV of Cash Outflows
If NPV > 0 , Project can be accepted
NPV = 0 , Indifference point. Project can be accepted/ Rejected.
NPV < 0 , Project will be rejected.

Year CF PVF@13% Dic CF
0 $-11,000.00 1 $-11,000.00
1 $    6,500.00 0.8850 $    5,752.21
2 $    6,500.00 0.7831 $    5,090.45
3 $    6,500.00 0.6931 $    4,504.83
4 $    6,500.00 0.6133 $    3,986.57
5 $    6,500.00 0.5428 $    3,527.94
NPV $ 11,862.00

NPV of Project L

Year CF PVF@13% Dic CF
0 $-46,500.00 1 $-46,500.00
1 $ 14,500.00 0.8850 $ 12,831.86
2 $ 14,500.00 0.7831 $ 11,355.63
3 $ 14,500.00 0.6931 $ 10,049.23
4 $ 14,500.00 0.6133 $    8,893.12
5 $ 14,500.00 0.5428 $    7,870.02
NPV $    4,499.85

PVF = 1/ (1+r)^n

r = Interest rate

n = Tme Gap

OPtion 1 has to be selcted, as the projects are mutually exclusive, the project with higher NPV has to be selected

Pls do rate, if the answer is correct and comment, if any further assistance is required.


Related Solutions

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,000, and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,500, and its expected cash flows would be $11,950 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer: a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $29,000, and its expected cash flows would be $14,900 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $34,500, and its expected cash flows would be $14,200 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $47,500, and its expected cash flows would be $13,800 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,000, and its expected cash flows would be $13,450 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $25,500, and its expected cash flows would be $12,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash...
a. Project L requires an initial outlay at t = 0 of $64,022, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. b.Project L requires an initial outlay at t = 0 of $75,000, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 10%. What is the project's MIRR? Do not round intermediate calculations. Round...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $85,241, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 10%. What is the project's IRR? Round your answer to two decimal places.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT