Question

In: Civil Engineering

An earthwork contract requires to cut and move excavated rocks. The site is a typical limestone...

An earthwork contract requires to cut and move excavated rocks. The site is a typical limestone rock formation in a cut section, which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic tests indicate a seismic wave velocity of 5,000 fps for the rock layer material. The contractor proposes to rip the rock with a 370-hp crawler tractor. Answer the following questions.
What is the total duration of the rock cut project assuming 10 hours per day work?

Solutions

Expert Solution

Detailed solution is as follows,

Tractor Productivity

For the given seismic wave velocity,ie., 5,000 fps and using 370 hp tractor ,referring the tractor production chart,

Productivity =560 bcy/hr

Quantity of rock

Given Length =15000 ft

Width = 85 ft

depth =3 ft

Volume of rock = 15000 x 85 x 3

                       =3825000 cft

Total duration required to cut

Per day productivity =productivity per hour x no of hours worked in a day

                             =560 x 10

                             =5600 cft

No of days required to complete the work = total volume/productivity per day

                                                            =3825000/5600       

                                                            =683 days


Related Solutions

n earthwork contract requires to cut and move excavated rocks. The site is a typical limestone...
n earthwork contract requires to cut and move excavated rocks. The site is a typical limestone rock formation in a cut section, which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic tests indicate a seismic wave velocity of 5,000 fps for the rock layer material. The contractor proposes to rip the rock with a 370-hp crawler tractor. Answer the following questions. As a Construction Manager for this site development project, prepare detailed cost estimate for the...
A. An earthwork contract requires to cut and move excavated rocks. The site is a typical...
A. An earthwork contract requires to cut and move excavated rocks. The site is a typical limestone rock formation in a cut section, which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic tests indicate a seismic wave velocity of 5,000 fps for the rock layer material. The contractor proposes to rip the rock with a 370-hp crawler tractor. Answer the following questions. (a) Calculate the production in bcy per hour, for full-time ripping, with efficiency based...
Two assemblages of lithic scrapters were excavated from different levels in a cave site Level 1:...
Two assemblages of lithic scrapters were excavated from different levels in a cave site Level 1: Sample mean: 14.83 Variance: 7.05 Sample Size: 63 Level 2: Sample Mean: 14.17 Variance: 5.49 Sample Size: 47 From superficial examination, they seem to differ. However, your job is to test whether the difference between the samples from the two levels represent a significant difference between the two occupations. Lets use a 0.05 significance level for this analysis Step 1: Frame this is a...
The site of a proposed north-south road will cut through the western side of a hill....
The site of a proposed north-south road will cut through the western side of a hill. The proposed cutting is 13 m high with a batter angle of 70 degrees. The site has been drilled by a single diamond drill hole. In the drill hole, 10 m of dolerite overlies 5 m of sandstone. RQD for the dolerite is 80% and RQD for the sandstone is 50%. There was 20 cm of core loss at 5 m and 40 cm...
a) You have recently graduated and been employed as an assistant site engineer on an open-cut...
a) You have recently graduated and been employed as an assistant site engineer on an open-cut mine. Your supervisor asks you to assist with modernising some mine operations. In particular, you are asked to investigate how modern surveying and spatial science technologies might be used to improve management of the mine. Describe four applications of modern surveying technologies that might improve mine management. For each of these: describe the application, identify and describe the surveying and spatial sciences technology that...
A shipment contract requires all but which of the following in order to be designated a shipment contract?
1. A shipment contract requires all but which of the following in order to be designated a shipment contract? Multiple Choice Title will pass to the buyer at the time and place of shipment. The seller must ship the goods to the buyer. Title remains with the seller until the goods are delivered to their destination. The seller must use a common carrier to ship the goods to the buyer. 2. All but which of the following items is treated...
The Great Giant Corp. has a management contract with its newlyhired president. The contract requires...
The Great Giant Corp. has a management contract with its newly hired president. The contract requires a lump sum payment of $25 million be paid to the president upon the completion of her first ten years of service. The company wants to set aside an equal amount of funds each year to cover this anticipated cash outflow. The company can earn 6.5% on these funds. How much must the company set aside each year Please walk me through the steps...
AMC has just signed a contract. The contract requires an initial investment of $5 million, and...
AMC has just signed a contract. The contract requires an initial investment of $5 million, and creates positive cash flows of $2 million one year from today, $1.5 million two years from today, and $2.5 million three years from today. What is the value of this contract AMC can earn 9 percent on its money?
You would like to sequence the genome of this organism. The restriction enzyme cut site for BglII is AGATCT.
  A) You would like to sequence the genome of this organism. The restriction enzyme cut site for BglII is AGATCT. You will use it to clone fragments of the genome in order to sequence it. How many times would you expect this enzyme to cut within the chromosome of Andrebacillus wieczorius ? (2) B) You decide to use a modified bacteriophage vector that can accommodate fragments digested with BglII. You use a partial digest on the chromosomal DNA. What...
A project will cut firm’s operating costs by $50,000. The project requires an initial investment of...
A project will cut firm’s operating costs by $50,000. The project requires an initial investment of $30,000 and be depreciated using straight-line depreciation to a zero book value over the 4-year life of the project. The company has a marginal tax rate of 35 percent. What is the operating cash flow of the project using the tax shield approach? a. $42,800 b. $35,125 c. $40,450 d. $38,930
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT