An earthwork contract requires to cut and move excavated rocks.
The site is a typical limestone rock formation in a cut section,
which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic
tests indicate a seismic wave velocity of 5,000 fps for the rock
layer material. The contractor proposes to rip the rock with a
370-hp crawler tractor. Answer the following questions.
What is the total duration of the rock cut project assuming 10
hours per day work?
Detailed solution is as follows,
Tractor Productivity
For the given seismic wave velocity,ie., 5,000 fps and using 370 hp tractor ,referring the tractor production chart,
Productivity =560 bcy/hr
Quantity of rock
Given Length =15000 ft
Width = 85 ft
depth =3 ft
Volume of rock = 15000 x 85 x 3
=3825000 cft
Total duration required to cut
Per day productivity =productivity per hour x no of hours worked in a day
=560 x 10
=5600 cft
No of days required to complete the work = total volume/productivity per day
=3825000/5600
=683 days