Question

In: Civil Engineering

n earthwork contract requires to cut and move excavated rocks. The site is a typical limestone...

n earthwork contract requires to cut and move excavated rocks. The site is a typical limestone rock formation in a cut section, which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic tests indicate a seismic wave velocity of 5,000 fps for the rock layer material. The contractor proposes to rip the rock with a 370-hp crawler tractor. Answer the following questions.

As a Construction Manager for this site development project, prepare detailed cost estimate for the project, and bid documents.

      Assume 10% time value cost of money, bonds, insurance, and storage over total direct cost, contingency at 2% of total direct cost, indirect overhead cost at 5% of total direct cost (additional on top of the equipment and operator costs), and 10% fee (on subtotal total of direct and indirect cost).

Solutions

Expert Solution

Detailed solution is as follows,

Productivity

For the given seismic wave velocity,ie., 5,000 fps and using 370 hp tractor ,referring the tractor production chart,

Productivity =560 bcy/hr

Volume of rock = 15000 x 85 x 3

                       =3825000 cft

Total durationto cut the rock = 3825000/560

                                        =6830 hours

Estimation

The normal cost for the tractor per hour = $ 96 per hour(including operator charges)

Total direct cost = 96 x 6830 =655680

Other costs are as follows

Cost for fee =10% of Direct and Indirect cost

                 =10% of 767145

                =76714.56

Total Estimation =(Total Direct +Indirect cost) + Cost for fee

                           =767145.6 +76714.56

                           =$832860

  

                                                    


Related Solutions

An earthwork contract requires to cut and move excavated rocks. The site is a typical limestone...
An earthwork contract requires to cut and move excavated rocks. The site is a typical limestone rock formation in a cut section, which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic tests indicate a seismic wave velocity of 5,000 fps for the rock layer material. The contractor proposes to rip the rock with a 370-hp crawler tractor. Answer the following questions. What is the total duration of the rock cut project assuming 10 hours per day...
A. An earthwork contract requires to cut and move excavated rocks. The site is a typical...
A. An earthwork contract requires to cut and move excavated rocks. The site is a typical limestone rock formation in a cut section, which is 15,000 ft long, 85 ft wide, and 3 ft deep. Seismographic tests indicate a seismic wave velocity of 5,000 fps for the rock layer material. The contractor proposes to rip the rock with a 370-hp crawler tractor. Answer the following questions. (a) Calculate the production in bcy per hour, for full-time ripping, with efficiency based...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT