Question

In: Operations Management

Think of a managed project or a project for which you were a member of the...

Think of a managed project or a project for which you were a member of the team. For that particular project:

Identify three key stakeholders who were involved in or affected by the project.
Describe the selected project. Include the names of the sponsor and project manager their functions.
Identify three key stakeholders who were involved in or affected by the project and why you included them
What was the attitude of each key stakeholders interest in the project and how did you perceive their attitudes that relate to the success or failure of the project
Describe each stakeholder's function or relationship it had for the project. Include each stakeholder's level of interest or concern in the success or failure of the project.
Describe the level of power of each of three stakeholders influencing the project outcome.
Describe another aspect that you can monitor about stakeholders that would help you better manage and plan your project.Identify what the potential benefit of a project manager can be obtained from the collection and analysis of the above information in order to effectively manage and plan your future projects.

Solutions

Expert Solution

Answer 1
The three key stakeholders who were involved in the project are-
1. Suppliers
2. Employees
3. Investors
Answer 2
The selected project was to complete outdoor advertising of the company which had a a retail outlet dealing in customers and selling consumer durable goods. The name of the sponsor was 1 India family Mart.
Answer 2B.
The function of the project manager in this project was as follows-
1. Timely completion of the project
2. Ensure that all the activities has been divided among the team members.
3. Daily feedback from the team members regarding the stages of work completion
4. Solving the problems faced by them during the execution of project.
5. Coordinating with senior team members and communicating with them the details of the project.
Answer 3
The three key stakeholders who were involved in the project and why I included them was-
1. Investor- investor was included in the project because the project required large amount of money to be invested, so I needed an investor who had invest money and wait for some days until the payment is done by the company.
2. Employees- employees was included in the project because they are the people who are responsible for completing the project and if they are not involved the project will never be completed.
3. Suppliers- suppliers are important in the project because it is the suppliers who are responsible for supplying the material in order to execute the project. They have to ensure timely supply of material related to the project otherwise the project will not be completed in the given time duration.


Please up vote this answer.
Due to limited time availability I have answered 4 parts of the question you can post the remaining parts again in order to get the answer.


Related Solutions

For the aluminum structural member shown, provide an explanation for which processes you think were used
For the aluminum structural member shown, provide an explanation for which processes you think were used in its manufacture and why. See Figure P2.28.   Figure P2.28.
Think about a group or team you were in that had a dominating member. a)     Describe the...
Think about a group or team you were in that had a dominating member. a)     Describe the scenario, and the effect the dominating member had on the group or team. (If this has not happened to you, discuss using examples, a hypothetical situation, and for parts b) and c), describe specific measures that could be taken.) b)     Explain how the team dealt with this. c) In hindsight, discuss other ways you might have dealt with the situation.
How do member-managed and manager-managed LLC management structures differ?
How do member-managed and manager-managed LLC management structures differ?
Identify an example of a project(s) on which you have worked. Discuss how it was managed....
Identify an example of a project(s) on which you have worked. Discuss how it was managed. Could you have used any of the methods discussed in this unit? *Note: please type it and has to be at least three paragrpahs.** Thank You! It can be an project that you have worked on before
You are a member in a project team and the project manager asked you to purchase...
You are a member in a project team and the project manager asked you to purchase 4 laptops with certain specifications (Lenovo ThinkPad T series, Core i7, 2 Tera Storage, 32 GB Ram, 15.6" size, NVIDIA® graphics). How do you set your procurement management to do that?
you are a member in a project team and the project manager asked you to purchase...
you are a member in a project team and the project manager asked you to purchase 4 laptops with certain specifications (lenovo thinkpad T series,core i7,2 tera storage ,32 GB Ram ,15.6 size , NVIDIA graphics ) how do you set your procurement management to do that?
You are a junior manager with expertise in project management and a member of a project...
You are a junior manager with expertise in project management and a member of a project team of a company that just won the bid to develop a new internet banking management system for a major bank in South Africa. The project will entail the following activities along with their respective precedence, duration and cost. Activity Code Activity Immediate Predecessor Normal Time(Weeks) Crashing Time(weeks) Normal Cost Crashing cost 1 A – 12 8 $100000 $104000 2 B A 17 15...
1) If you were a member of the Second Chicago School, which standard model of oligopoly...
1) If you were a member of the Second Chicago School, which standard model of oligopoly would you think best models market performance? A. Cournot B. Hotelling C. Bertrand D. Mazur 2) In a game, if every firm is best-responding to every other firm in a game, then A. Every firm is maximizing profit conditional on what every other firm has chosen to do. B. The firms strategies represent a Nash equilibrium. C. No firm has any unilateral incentive to...
Question: 1) Which project do you think is more risky? How do you think you should...
Question: 1) Which project do you think is more risky? How do you think you should incorporate differences in risk into your analysis? Question: 2) Based on the calculated payback period, net present value (NPV), and internal rate of return (IRR) for each project, which project looks better for New Balance sharehold-ers? Why? Question: 3) Should Rodriguez be more or less critical of cash flow forecasts for Persistence than of cash flow forecasts for Sneaker 2013? Why? Question: 4) What...
If you were a member of the Federal Reserve board of​ governors, and you saw that...
If you were a member of the Federal Reserve board of​ governors, and you saw that the economy was sliding into a​ recession, which of the following actions would you MOST likely​ recommend? A. Sell U.S. government bonds in open market operations. B. Raise the discount rate. C. Implement fiscal policy. D. Raise the reserve requirement. E. Buy U.S. government bonds in the open market.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT