In: Operations Management
Think of a managed project or a project for which you were a member of the team. For that particular project:
Identify three key stakeholders who were involved in or affected
by the project.
Describe the selected project. Include the names of the sponsor and
project manager their functions.
Identify three key stakeholders who were involved in or affected by
the project and why you included them
What was the attitude of each key stakeholders interest in the
project and how did you perceive their attitudes that relate to the
success or failure of the project
Describe each stakeholder's function or relationship it had for the
project. Include each stakeholder's level of interest or concern in
the success or failure of the project.
Describe the level of power of each of three stakeholders
influencing the project outcome.
Describe another aspect that you can monitor about stakeholders
that would help you better manage and plan your project.Identify
what the potential benefit of a project manager can be obtained
from the collection and analysis of the above information in order
to effectively manage and plan your future projects.
Answer 1
The three key stakeholders who were involved in the project
are-
1. Suppliers
2. Employees
3. Investors
Answer 2
The selected project was to complete outdoor advertising of the
company which had a a retail outlet dealing in customers and
selling consumer durable goods. The name of the sponsor was 1 India
family Mart.
Answer 2B.
The function of the project manager in this project was as
follows-
1. Timely completion of the project
2. Ensure that all the activities has been divided among the team
members.
3. Daily feedback from the team members regarding the stages of
work completion
4. Solving the problems faced by them during the execution of
project.
5. Coordinating with senior team members and communicating with
them the details of the project.
Answer 3
The three key stakeholders who were involved in the project and why
I included them was-
1. Investor- investor was included in the project because the
project required large amount of money to be invested, so I needed
an investor who had invest money and wait for some days until the
payment is done by the company.
2. Employees- employees was included in the project because they
are the people who are responsible for completing the project and
if they are not involved the project will never be completed.
3. Suppliers- suppliers are important in the project because it is
the suppliers who are responsible for supplying the material in
order to execute the project. They have to ensure timely supply of
material related to the project otherwise the project will not be
completed in the given time duration.
Please up vote
this answer.
Due to limited time availability I have answered 4 parts of the
question you can post the remaining parts again in order to get the
answer.