Question

In: Finance

Norman Inc. wishes to accept a new project which has a NPV of US$98,000. A sum...

Norman Inc. wishes to accept a new project which has a NPV of US$98,000. A sum of US$10,000,000 will be needed to invest in it. The net earnings for the current year are US$1,000,000 and the accumulated retained earnings to date are US$7,000,000. The current amount of long term debt carried on Norman Inc.’s balance sheet is US$5,333,333.33. Norman Inc. wishes to finance the new investments in line with its existing capital structure.
i. Will Norman Inc. be in a position to pay any dividends this year if it follows the residual dividend approach? If yes, what will be the total amount of dividend paid?
ii. What will be the debt‐to‐equity ratio of the newly financed project?

iii. What would be the implications of Norman Inc.’s dividend payout decision?

Solutions

Expert Solution

Total retained earnings = 7000000+1000000 = $       80,00,000
Long term debt $       53,33,333
Total $   1,33,33,333
Weight of long term debt = 5333333/13333333 = 40.00%
Weight of equity = 8000000/13333333 = 60.00%
i) The required equity for the new investment = 10000000*60% = $       60,00,000
As the total retained earnings is 8000000, the equity
portion can be met out of it.
Residual amount that can be paid as dividend = 8000000-6000000 = $       20,00,000
Answer:
Yes.
Total amount of dividend that can be paid = $       20,00,000
ii) Debt equity ratio for the newly financed project = 0.40/0.60 = 0.67
iii) The residual dividend policy would mean that, the
dividends would fluctuate from year to year
depending on the retained earnings available for
distribution after providing for the equity portion of
capital expenditure. Fluctuating dividends will drive
away investors who required constant or growing
dividends.

Related Solutions

Calculate the NPV for Project A and accept or reject the project with the cash flows...
Calculate the NPV for Project A and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 7% Project A Time 0 1 2 3 4 5 Cash Flow -990 350 480 500 630 120 2) Calculate the NPV for project L and recommend whether the company should accept or reject the project. Cost of Capital is 6% Project L Time 0 1 2 3 4 5 Cash Flow -         8,600          ...
What is the payback period, NPV, IRR of A. Using this information, should we accept Project...
What is the payback period, NPV, IRR of A. Using this information, should we accept Project A. Why or why not. Given the following information answer the question above. The discount rate is 10 percent.      PROJECT A       t           Cash Flow       0          (150,000)        1          40,000           2          40,000              3          40,000          4           40,000           5            40,000               ROUND TO NEAREST DOLLAR OR TEN %
If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?
Considering the following projects.ProjectYear01234ACash flows-$100$35$35$35$35BCash flows-$100$60$50$40$30Project A has WACC = 6.00% while project B has WACC = 8.50%.If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?Would your decision (Your answer from part A) change if these two projects were independent?
(Calculating project cash flows and​ NPV)  ​Weir's Trucking, Inc. is considering the purchase of a new...
(Calculating project cash flows and​ NPV)  ​Weir's Trucking, Inc. is considering the purchase of a new production machine for $115,000. The purchase of this new machine will result in an increase in earnings before interest and taxes of $21,000 per year. To operate this machine​ properly, workers would have to go through a brief training session that would cost $4,250 after tax. In​ addition, it would cost ​$5,500 after tax to install this machine correctly. ​ Also, because this machine...
(Calculating project cash flows and NPV)?? Weir's Trucking, Inc. is considering the purchase of a new...
(Calculating project cash flows and NPV)?? Weir's Trucking, Inc. is considering the purchase of a new production machine for $115,000. The purchase of this new machine will result in an increase in earnings before interest and taxes of $27,000 per year. To operate this machine properly, workers would have to go through a brief training session that would cost $5500 after tax. In addition, it would cost 5500 after tax to install this machine correctly. Also, because this machine is...
Calculate the IRR, the NPV, and the MIRR for each project, and indicate the correct accept/reject decision for each.
11.  Problem 10-08 (NPVs, IRRs, and MIRRs for Independent Projects)NPVs, IRRs, and MIRRs for Independent ProjectsEdelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $18,000, and that for the pulley system is $22,000. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:YearTruckPulley1$5,100$7,50025,1007,50035,1007,50045,1007,50055,1007,500Calculate the IRR, the NPV, and the MIRR for each project,...
NPV always gives you correct decision for accepting the project. If NPV always gives us the...
NPV always gives you correct decision for accepting the project. If NPV always gives us the correct decision why should we pay attention to profitability ratios or IRR? Provide an example where one of these other ratios might change your decision on a project.
Calculating Project NPV Down Under Boomerang, Inc., is considering a new three-year expansion project that requires...
Calculating Project NPV Down Under Boomerang, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $3,950,000. The fixed asset will be depreciated straight-line to zero over its three -year tax life, after which time it will be worthless. The project is estimated to generate $3,175,000 in annual sales, with costs of $1,455,000. The tax rate is 35 percent and the required return is 10 percent. What is the Project's NPV?
5. Brandt Enterprises is considering a new project that has an estimated NPV of $800. The...
5. Brandt Enterprises is considering a new project that has an estimated NPV of $800. The assistant to CFO conducted a sensitivity analysis with regard to sales price and salvage value. The results are documented in the table below: Sales price change by -30% -15% 0 15% 30% NPV results 579.2 724 800 876 1051.2 Salvage value change by -30% -15% 0 15% 30% NPV results 624 780 800 820 984 The assistant needs to explain what sensitivity is and...
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Inital Outlay (105,000.000) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% Your company is considering three independent projects. Given the following cash flow information,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT