In: Finance
Calculate the NPV for Project A and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 7%
Project A
Time 0 1 2 3 4 5
Cash Flow -990 350 480 500 630 120
2) Calculate the NPV for project L and recommend whether the company should accept or reject the project. Cost of Capital is 6%
Project L
Time 0 1 2 3 4 5
Cash Flow - 8,600
5,000
5,800
5,800
5,000
- 10,000
3) Calculate the Pay Back for project K and decide if the firm should accept or reject the project. Cost of Capital is 11% and the maximum allowable payback is 4 years
Project K
Time 0 1 2 3 4 5
Cash Flow - 11,000
3,230
4,120
1,530
3,500
990
4) Calculate the Discounted Pay Back for project S and decide if the firm should accept or reject the project. Cost of Capital is 10% and the maximum allowable discounted payback is 3 years
Project S
Time 0 1 2 3 4 5
Cash Flow - 11,000
3,350
4,120
2,280
3,500
1,000
5) Calculate the IRR for project T and decide if the firm should accept or reject the project. Appropriate Cost of Capital is 8%
Project T
Time 0 1 2 3 4 5
Cash Flow - 11,000
3,350
4,120
1,530
3,500
1,000
6) Calculate the MIRR for project I and decide if the firm should accept or reject the project. Appropriate Cost of Capital is 12%. Reinvestment rate is 5%
Project I
Time 0 1 2 3 4
Cash Flow - 11,000
5,330
4,120
1,530
2,030
7) Calculate the PI for project D and decide if the firm should accept or reject the project. Appropriate Cost of Capital is 8%
Project D
Time 0 1 2 3 4 5
Cash Flow - 1,000
330
485
620
289
100
0 | 1 | 2 | 3 | 4 | 5 | NPV | ||
A | -990 | 350 | 480 | 500 | 630 | 120 | $730.68 | Accept |
L | -8,600 | 5,000 | 5,800 | 5,800 | 5,000 | -10,000 | $2,636.64 | Accept |
NPV can be calculated using NPV function in excel or calculator or manually using the given discount rates.
If NPV > 0, project should be accepted.
Payback | ||||||||
K | -11,000 | 3,230 | 4,120 | 1,530 | 3,500 | 990 | 3.61 | Accept |
Payback period is the no. of years it takes to recover the investment. As it is less than 4 years, accept this project.
0 | 1 | 2 | 3 | 4 | 5 | D.Payback | ||
S | -11,000 | 3,350 | 4,120 | 2,280 | 3,500 | 1,000 | ||
DCF S | -11,000 | 3,045 | 3,405 | 1,713 | 2,391 | 621 | 4.72 | Reject |
Discounted payback is payback using discounted cash flows (DCF). As it is above 4 years, reject the project.
IRR | ||||||||
T | -11,000 | 3,350 | 4,120 | 1,530 | 3,500 | 1,000 | 8.40% | Accept |
IRR can be calculated using IRR function in excel or calculator. As IRR > 8%, accept the project.
MIRR | |||||||
I | -11,000 | 5,330 | 4,120 | 1,530 | 2,030 | 6.87% | Reject |
MIRR can be calculated using MIRR function in excel or manually using formula
PI | ||||||||
D | -1,000 | 330 | 485 | 620 | 289 | 100 | 2.49 | Accept |
PI = 1 + NPV / CF0
As PI > 1, Accept the project