Question

In: Accounting

Interest during Construction Dexter Construction Corporation is building a student condominium complex; it started construction on...

Interest during Construction

Dexter Construction Corporation is building a student condominium complex; it started construction on January 1, Year 1. Dexter borrowed $1 million specifically for the project by issuing a 10%, 5-year, $1 million note, which is payable on December 31 of Year 3. Dexter also had a 12%, 5-year, $3 million note payable and a 10%, 10-year, $1.8 million note payable outstanding all year.

In Year 1, Dexter incurred costs as follows:

Interest during Construction

Dexter Construction Corporation is building a student condominium complex; it started construction on January 1, Year 1. Dexter borrowed $1 million specifically for the project by issuing a 10%, 5-year, $1 million note, which is payable on December 31 of Year 3. Dexter also had a 12%, 5-year, $3 million note payable and a 10%, 10-year, $1.8 million note payable outstanding all year.

In Year 1, Dexter incurred costs as follows:

January 1 $280,000
March 1 540,000
June 30 1,000,000
November 1 420,000

Calculate Dexter's capitalized interest on the student condominium complex for Year 1.

Calculate Dexter's capitalized interest on the student condominium complex for Year 1.

Required:

Prepare the journal entry to record Hemingway’s acquisition of the equipment.

Solutions

Expert Solution

Solution:

Year 1: Weighted-Average accumulated expenditure and interest capitalized
Date Expenditure Weigh Avearge
01-Jan $2,80,000 12/12 $2,80,000
01-Mar $5,40,000 10/12 $4,50,000
30-Jun $10,00,000 6/12 $5,00,000
01-Nov $4,20,000 2/12 $70,000
Accumulated Expenditure $22,40,000 $13,00,000
Weighted average interest rate of all other debt
Debt Amount Interest rate Interest amount
12% Note $30,00,000 12% $3,60,000
10% Note $18,00,000 10% $1,80,000
Totals $48,00,000 $5,40,000
Weighted average rate (total interets/ total debt) 11.25%
Year 1: Interest Capitalized
Average Interest Rate Capitalized Interest
Avearge Accumulated Expenditure $13,00,000
Specific $10,00,000 10.00% $1,00,000
Other debt $3,00,000 11.25% $33,750
Total Interest Capitalized $1,33,750

Related Solutions

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2019 2020 Costs incurred during the year $ 290,000 $ 150,000 Estimated additional cost to complete 145,000 — Billings during the year 260,000 265,000 Cash collections during the year 240,000 285,000 Required: Record the preceding transactions in MSK’s books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
Interest during construction Jones company is constructing a production complex that qualifies for interest capitalization. The...
Interest during construction Jones company is constructing a production complex that qualifies for interest capitalization. The following information is available: • capitalization period: January 1, 2016 to June 30, 2017 • expenditures on project 2016: January 1-$468,000 May 1-$489,000 October 1-$648,000 2017 March 1-$1,452,000 June 30-$588,000 • amounts borrowed and outstanding: $1.4 million borrowed at 10%, specifically for the project $7 million borrowed on July 1, 2105, at 12% $19 million borrowed on January 1, 2011, at 6% Required: Note:...
Interest During Construction Alta Company is constructing a production complex that qualifies for interest capitalization. The...
Interest During Construction Alta Company is constructing a production complex that qualifies for interest capitalization. The following information is available: Capitalization period: January 1, 2019, to June 30, 2020 Expenditures on project: 2019: January 1 $ 516,000 May 1 477,000 October 1 648,000 2020: March 1 1,404,000 June 30 684,000 Amounts borrowed and outstanding:    $1.7 million borrowed at 10%, specifically for the project    $8 million borrowed on July 1, 2018, at 12%    $13 million borrowed on January 1, 2017, at...
interest During Construction Zimmer Company is constructing a production complex that qualifies for interest capitalization. The...
interest During Construction Zimmer Company is constructing a production complex that qualifies for interest capitalization. The following information is available: Capitalization period: January 1, 2016, to June 30, 2017 Expenditures on project: 2016: January 1 $ 612,000 May 1 573,000 October 1 492,000 2017: March 1 1,404,000 June 30 612,000 Amounts borrowed and outstanding:    $1.5 million borrowed at 10%, specifically for the project    $7 million borrowed on July 1, 2015, at 12%    $17 million borrowed on January 1, 2011, at...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in early 2010 and was completed in 2011. The following additional information is available:                                                                                                    2010                       2011        Costs incurred............................................................. $ 2,430,000            $ 2,700,000        Estimated costs to complete............................................. 2,600,000                         —        Collections during the year.............................................. 2,400,000               3,600,000          Billings for the year …………………………………………..     2,800,000                3,200,000 Used the percentage-of-completion method. Instructions Under the contract-based approach, a)     How much revenue should be reported...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available: 2019 2020 Cost Incurred $1,458,000 $1,620,000 Estimated costs to complete 1,560,000 - Billed 1,700,000 1,900,000 Collections during the year 1,440,000 2,160,000 Miller uses the percentage-of-completion method. Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019 and 2020? b) Prepare all journal entries for 2019...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available:                                                                                           2019               2020        Costs incurred...................................................... $1,458,000          $1,620,000        Estimated costs to complete.................................. 1,560,000                         —        Billed ……………………………………………….    1,700,000           1,900,000        Collections during the year.................................... 1,440,000            2,160,000 Miller uses the percentage-of-completion method. Instructions Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019...
At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures...
At the beginning of 2018, Heinz Corp. started construction on a new office building. Construction expenditures during 2018 were as follows: January 1                     $400,000 May 1                          150,000 July 1                         300,000   December 31               100,000    Heinz has the following debts outstanding during 2018; the bonds payable is directly related to the construction projects; none of the others are related to the construction project. Liability Annual Percent Loan Amount Notes Payable 4% $200,000 Bonds Payable 6% $400,000 Mortgage Payable 5% $300,000
During 2020, Pina Colada Corporation started a construction job with a contract price of $5.32 million....
During 2020, Pina Colada Corporation started a construction job with a contract price of $5.32 million. Pina Colada ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Pina Colada sends billings as revenues are earned. Billings are non-refundable. The following information is available: 2020 2021 2022 Costs incurred to date $ 760,000 $2,660,000 $5,220,000 Estimated costs to complete 3,990,000 2,660,000 -0- (a) Calculate the...
During 2020, Blue Spruce Corporation started a construction job with a contract price of $6.16 million....
During 2020, Blue Spruce Corporation started a construction job with a contract price of $6.16 million. Blue Spruce ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Blue Spruce sends billings as revenues are earned. Billings are non-refundable. The following information is available: 2020 2021 2022 Costs incurred to date $ 880,000 $3,080,000 $6,060,000 Estimated costs to complete 4,620,000 3,080,000 -0- Calculate the amount...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT