Question

In: Accounting

Interest During Construction Alta Company is constructing a production complex that qualifies for interest capitalization. The...

Interest During Construction

Alta Company is constructing a production complex that qualifies for interest capitalization. The following information is available:

  • Capitalization period: January 1, 2019, to June 30, 2020
  • Expenditures on project:
    2019:
    January 1 $ 516,000
    May 1 477,000
    October 1 648,000
    2020:
    March 1 1,404,000
    June 30 684,000
  • Amounts borrowed and outstanding:
       $1.7 million borrowed at 10%, specifically for the project
       $8 million borrowed on July 1, 2018, at 12%
       $13 million borrowed on January 1, 2017, at 6%

Required:

Note: Round all final numeric answers to two decimal places.

  1. Compute the amount of interest costs capitalized each year.
    Capitalized interest, 2019 $ fill in the blank 1
    Capitalized interest, 2020 $ fill in the blank 2
  2. If it is assumed that the production complex has an estimated life of 20 years and a residual value of $0, compute the straight-line depreciation in 2020.

    $ fill in the blank 3

  3. Since GAAP requires accrual accounting, if a company capitalizes interest during the construction period it will report   income than if it had not capitalized interest. In future periods, the same company will report   income than if it had not capitalized interest.

Solutions

Expert Solution

Specific funds = 1.7 mn

General funds = 8+13 = 21 mn

Weighted average rate of General funds

Amount Rate Interest

8 mn 12% 960000

13 mn 6% 780000

Total 1740000

Weighted average rate = 1.74 mn /21 mn

= 8.2857%

Interest to capitalize in 2019

since the cost incurred in 2019 is less than 1.7 mn , we will use rate of specific borrowing only i.e. 10%

2019

Jan 1 $ 516000 for 12 months @ 10% = 51600

May 1 $ 477000 for 8 months@ 10% = 31,800

Oct 1 $ 648000 for 3 months@ 10% = 16200

  Total 1641000    99600

Interest to capitalize in 2020

Jan 1 specific borrowings 1641000 for 6 months @ 10% = 82050

March 1 out of specific borrowings 1700000- 164100 = 59000 for 4 months@ 10% = 1966.67

out of general funds 1404000-59000= 1345000 for 4 months @ 8.2857%= 37147.55

June 30 684000 out of general funds for 0 months @ 8.2857 % 0

Total 121164.22

Cost of asset

Amount spent (516000+477000+648000+1404000+684000) 3729000

Interest capitalizes in 2019 99,600

Interest capitalized in 2020 1,21,164.22

Cost of complex 39,49,764.22

Yearly Depreciation = (cost of asset - residual value) / expected useful life

= ( 3949764.22 . - 0 ) / 20

= 197488.21

Depreciation in 2020 , will stary from date of completion of asset on 30 th June

Depreciation for 6 months = $ 98,744 .11

Depreciation if interest was not capitalized

Depreciation = 3729000 /20 * 6/12 = $ 93,225

increase in depreciation due to capitalization of Interest = 98744.11 -93225 = 5519.11

Income in 2020 (if interest not capitalized) = (-)121164. 22 +5519.11 = (-) 115645.11


Related Solutions

Alta Company is constructing a production complex that qualifies for interest capitalization. The following information is...
Alta Company is constructing a production complex that qualifies for interest capitalization. The following information is available: Capitalization period: January 1, 2019, to June 30, 2020 Expenditures on project: 2019: January 1 $ 516,000 May 1 549,000 October 1 492,000 2020: March 1 1,512,000 June 30 600,000 Amounts borrowed and outstanding:    $1.4 million borrowed at 12%, specifically for the project    $5 million borrowed on July 1, 2018, at 14%    $18 million borrowed on January 1, 2017, at 8% Required: Note:...
Interest during construction Jones company is constructing a production complex that qualifies for interest capitalization. The...
Interest during construction Jones company is constructing a production complex that qualifies for interest capitalization. The following information is available: • capitalization period: January 1, 2016 to June 30, 2017 • expenditures on project 2016: January 1-$468,000 May 1-$489,000 October 1-$648,000 2017 March 1-$1,452,000 June 30-$588,000 • amounts borrowed and outstanding: $1.4 million borrowed at 10%, specifically for the project $7 million borrowed on July 1, 2105, at 12% $19 million borrowed on January 1, 2011, at 6% Required: Note:...
interest During Construction Zimmer Company is constructing a production complex that qualifies for interest capitalization. The...
interest During Construction Zimmer Company is constructing a production complex that qualifies for interest capitalization. The following information is available: Capitalization period: January 1, 2016, to June 30, 2017 Expenditures on project: 2016: January 1 $ 612,000 May 1 573,000 October 1 492,000 2017: March 1 1,404,000 June 30 612,000 Amounts borrowed and outstanding:    $1.5 million borrowed at 10%, specifically for the project    $7 million borrowed on July 1, 2015, at 12%    $17 million borrowed on January 1, 2011, at...
     1. Cooper, Inc., is constructing a building that qualifies for interest capitalization. The following information...
     1. Cooper, Inc., is constructing a building that qualifies for interest capitalization. The following information is available: Capitalization period: January 1, 2013-December 31, 2014 Expenditures on project (incurred evenly): 2013 $30,000 2014 $50,000 Amounts borrowed and outstanding (all debt incurred January 1, 2013) $10,000 at 10% (specifically for the construction project) $18,000 at 11% (general debt) $30,000 at 13% (general debt) Required: a. Compute the amount of interest that should be capitalized in 2013 and 2014. (Round interest rates...
During 2018, the COYOTE Company spent $4,000,000 for various construction projects which are qualified for capitalization of interest.
During 2018, the COYOTE Company spent $4,000,000 for various construction projects which are qualified for capitalization of interest. The total expenditures of $4,000,000 were made as follows: $1,000,000 on 1/1/2018, $2,000,000 on 4/1/2018, and $1,000,000 on 10/1/2018. The company had the following debts outstanding as of December 31, 2018:1. 6%, 5-year note to finance construction of various assets, dated January 1, 2017, with interest payable annually on each January 1. $1,500,0002. 8%, 15-year bonds issued at par on December 31,...
Interest during Construction Dexter Construction Corporation is building a student condominium complex; it started construction on...
Interest during Construction Dexter Construction Corporation is building a student condominium complex; it started construction on January 1, Year 1. Dexter borrowed $1 million specifically for the project by issuing a 10%, 5-year, $1 million note, which is payable on December 31 of Year 3. Dexter also had a 12%, 5-year, $3 million note payable and a 10%, 10-year, $1.8 million note payable outstanding all year. In Year 1, Dexter incurred costs as follows: Interest during Construction Dexter Construction Corporation...
Computing and Recording Interest Capitalization Weld Corporation is constructing a plant for its own use. Weld...
Computing and Recording Interest Capitalization Weld Corporation is constructing a plant for its own use. Weld capitalizes interest on an annual basis. The following expenditures are made during the current year: January 1, $30,000; July 1, $290,000; September 1, $800,000; and December 31, $2,110,000. The following debts were outstanding throughout the current year. Debt Amount Construction note, 12% $100,000 Short-term note payable, 15% 400,000 Accounts payable (noninterest-bearing) 400,000 Answer the following questions, rounding your answers to the nearest whole dollar....
IAS 23 requires the capitalization of borrowing costs directly attributable to the acquisition, construction, or production...
IAS 23 requires the capitalization of borrowing costs directly attributable to the acquisition, construction, or production of a qualifying asset. Previously, IAS 23 allowed companies to expense or capitalize borrowing costs. Required: Justify whether there is a change in accounting policy.
EBC is a construction company. They are in the process of constructing a building whose plumbing...
EBC is a construction company. They are in the process of constructing a building whose plumbing would be installed in 12 days at a cost of $ 64 or in 10 days at a cost of $ 80 by working overtime. Plumbing is on the critical path and each day’s saving in completion time of the whole project is worth $ 10. a) You have been asked to advise the project team on whether to take the 10 day or...
Computing and Recording Interest Capitalization The following information is from Bowin Inc. for a long-term construction...
Computing and Recording Interest Capitalization The following information is from Bowin Inc. for a long-term construction project that is expected to be completed in January 2021. The construction project is for a building intended for the company’s own use. The capital expenditure on January 1, 2020, is for the purchase of land for the building site. No new construction loans were opened for the project in 2020. All debt was outstanding for the full year. Capital Expenditures for 2020 Date...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT