Question

In: Accounting

During 2020, Blue Spruce Corporation started a construction job with a contract price of $6.16 million....

During 2020, Blue Spruce Corporation started a construction job with a contract price of $6.16 million. Blue Spruce ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Blue Spruce sends billings as revenues are earned. Billings are non-refundable. The following information is available:

2020 2021 2022
Costs incurred to date $ 880,000 $3,080,000 $6,060,000
Estimated costs to complete 4,620,000 3,080,000 -0-

Calculate the amount of gross profit that should be recognized each year under the percentage-of-completion method.

2020

2021

2022

Solutions

Expert Solution

Year Gross Profit
2020 $                105,600
2021 $              (105,600)
2022 $                100,000

Working:

Year Actual Cost Incurred[a] Accumulated cost incurred till date[b] Total estimated Cost [c] % of Completed [d=b/c] Contract Price[e] Revenue Recognized[f=e*f] Current Period Revenue [g] Gross Profit [g-a]
2020 $                880,000 $                880,000 $             5,500,000 16.00% $        6,160,000 $            985,600 $            985,600 $          105,600
2021 $             2,200,000 $             3,080,000 $             6,160,000 50.00% $        6,160,000 $        3,080,000 $        2,094,400 $       (105,600)
2022 $             2,980,000 $             6,060,000 $             6,060,000 100.00% $        6,160,000 $        6,160,000 $        3,080,000 $          100,000

Related Solutions

During 2020, Pina Colada Corporation started a construction job with a contract price of $5.32 million....
During 2020, Pina Colada Corporation started a construction job with a contract price of $5.32 million. Pina Colada ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Pina Colada sends billings as revenues are earned. Billings are non-refundable. The following information is available: 2020 2021 2022 Costs incurred to date $ 760,000 $2,660,000 $5,220,000 Estimated costs to complete 3,990,000 2,660,000 -0- (a) Calculate the...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $344,000 $709,500 $920,200 Estimated costs to complete 516,000 236,500 0 Billings to date (non-refundable) 258,000 774,000 1,376,000 Collections to date 232,200 696,600 1,225,500 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Grouper Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Prepare all necessary journal entries for 2021. (Credit account...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT