Question

In: Accounting

On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in...

On 01 May 2015, the management of Netcare concluded a contract with Build-IT Building Contractors, in terms of which the construction company undertook to build one Medical Suite Block, consisting of 50 suites of 3 rooms, a waiting room, Doctors consulting room, reception area and kitchenette. The contract stipulated that the building would be completed by 15 December 2015.

The contracting parties also agreed to the following:

a) If the hostels are not completed by 15 December 2015, Build-IT Building Contractors would be liable for an amount of R10 000 per day delayed after 15 December 2015.  

b) Ten percent of the contract price would be held back until Mr. Smith, Netcare’s architect, issues a final certificate.  

Evaluate which form of breach of contract, if any, has been committed in each of the following independent situations. Provide reasons in support of your evaluation.                                                                             

2.2.1    Build-IT Building Contractors only completes the work on 7 January 2015. The delay is caused by serious floods resulting from an unforeseeable cyclone in September 2015.                                                                                              (5)

2.2.2    Build-IT Building Contractors only completes the work on 10 January 2015. The delay is caused by a week-long strike by the construction company’s employees.                                                                                                                                           (5)

2.2.3    On 6 January 2015, Mr. Smith issues a final certificate, but owing to a cash flow problem, Netcare does not pay the outstanding balance on the contract price.   (5)

Solutions

Expert Solution

This question belongs to the concept of Breach of Contract in case of construction Contracts.

  • Types of breach of Contract:
    • 1. Major (“Material”) Contract Breaches:involves the failure to perform an essential and significant term or multiple terms of a contract which result in a negative effect on the value of the contract. render the contract terminated with immediate effect and sue for damages resulting from the breach.
    • 2. Minor (“Non-Material”) Contract Breaches:  which pertains to an inconsequential or ancillary term that does not affect the whole outcome of the contract. The party can claim for damages.
  • 3 Common Causes for Breach of Contract in Construction
    • 1. Defective Performance
    • 2. Schedule Issues
    • 3. Failure to Perform
  • Potential Remedies Under Breach of Contract
    • 1. Damages for Breach of Contract
    • 2. Rescission
    • 3. Reformation
    • 4. Specific Performance

As per question, case wise discussion is given below:

2.2.1: Build-IT Building Contractors only completes the work on 7 January 2015. The delay is caused by serious floods resulting from an unforeseeable cyclone in September 2015: in this case delay is not due to contractor fault but due to natural calmity. Hence this is not the actual breach & management of Netcare should not sue Build-IT Building Contractors, for damages.

2.2.2    Build-IT Building Contractors only completes the work on 10 January 2015. The delay is caused by a week-long strike by the construction company’s employees: in this case delay is due to contractor fault i.e strike by employees, it concludes Minor (“Non-Material”) Contract Breaches as the performance/completeion period got delayed. Hence management of Netcare should can sue Build-IT Building Contractors, for damages @ R 10000 per day , total of R 2,60,000 for 26 days.

2.2.3    On 6 January 2015, Mr. Smith issues a final certificate, but owing to a cash flow problem, Netcare does not pay the outstanding balance on the contract price : in this case since Ten percent of the contract price should be paid as soon as architect issue final certificate delay by Netcare on account cash flow problem is a breach of contract & Build-IT Building Contractors can sue for the damages or intrest from 6 January 2015 till actual date of payment.

Thankyou!!


Related Solutions

On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000 Instructions Fill in...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is incomplete and the contractor is confused about how to transfer profit or loss in the P/L account. Being a student of cost accounting, you are required to state the rules regarding the transfer of profits to profit and loss account in case of incomplete contracts( 0%,20%,50%,75%,90 %) to the contractor.
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work on this contract began in 2013 and the financial data pertaining to this contract is available here. Cost incurred till Dec.31, 2013 $1,080,000 Billings made to City $1,000,000 Amount collected from City $ 750,000 The estimated future cost to complete this contract is $3,240,000. (a) Prepare Chicago contractors 2013 journal entries using COMPLETED CONTRACT method. (b) Show how the contract accounts will appear in...
Waterway Corp. enters into a contract with a customer to build an apartment building for $1,069,900....
Waterway Corp. enters into a contract with a customer to build an apartment building for $1,069,900. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $153,300 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $51,100 each week that completion is delayed. Waterway commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Cheyenne Corp. enters into a contract with a customer to build an apartment building for $995,600....
Cheyenne Corp. enters into a contract with a customer to build an apartment building for $995,600. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $145,500 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $48,500 each week that completion is delayed. Cheyenne commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Indigo Corp. enters into a contract with a customer to build an apartment building for $1,061,800....
Indigo Corp. enters into a contract with a customer to build an apartment building for $1,061,800. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $139,200 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $46,400 each week that completion is delayed. Indigo commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Problem 3 An entity entered into a construction contract to build a condo building at a...
Problem 3 An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s): 20x0 20x1 20x2 20x3 Costs incurred during the year $ 6500 19500 25000 5800 Estimated costs to complete 38500 26000 6500 - Billings 18000 18000 - 18000 For each of the parts below, prepare the ‘mini’ income statement for the project for each...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT