In: Accounting
McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2020 and completed in 2021. Cost and other data are presented below:
2020 2021
Costs incurred during the year $1,500,000 $1,300,000
Estimated costs to complete 1,200,000 0
Billings during the year 1,200,000 1,300,000
Cash collections during the year 1,000,000 1,500,000
Part 1: Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2020 and 2021.
Part 2: Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries to record costs, billings, collections, and profit (loss) recognition. Round your answers to the nearest whole dollar.
Part 3: Assume that McCombs recognizes revenue upon project completion. Required: Compute the amount of gross profit recognized by McCombs during 2020 and 2021.
McCombs Contractor | 2020 | 2021 | |||||||||
Ans to 1 | Calculation of Gross Profit | Ans to 2 | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | ||||
Particulars | 2020 | 2021 | Note | Costs Incurred | CIP (Work-in-progress) | 15,00,000 | 13,00,000 | ||||
Contract Price | 25,00,000 | 25,00,000 | A | Cash | 15,00,000 | 13,00,000 | |||||
Cost Incurred during the year | 15,00,000 | 13,00,000 | B | ||||||||
Estimated cost to complete | 12,00,000 | - | C | Billing | Accounts Receivable | 12,00,000 | 13,00,000 | ||||
Cost Incurred to date | 15,00,000 | 28,00,000 | D | Billing on CIP | 12,00,000 | 13,00,000 | |||||
(Sum total of the cost incurred during the year) | |||||||||||
Estimated total cost | 27,00,000 | 28,00,000 | E=C+D | Receiving Payments | Cash | 10,00,000 | 15,00,000 | ||||
Percentage complete | 55.56% | 100.00% | F=D/E | Accounts Receivable | 10,00,000 | 15,00,000 | |||||
(Cost Incurred to date/Estimated total cost) | |||||||||||
Revenue to be recognized | 13,88,889 | 11,11,111 | G | Period end adjustments for Revenue | Construction Expense | 15,00,000 | |||||
(Contract Price*Percentage complete)- revenue previously recognized | (Gross Profit/Loss entry) | CIP (Work-in-progress) | 1,11,111 | ||||||||
Year 2020: 55.56% completed. Revenue recognized = 55.56% x $ 2,500,000 = $ 1,388,889. | Construction Revenue | 13,88,889 | |||||||||
Year 2021: 100% completed. Revenue recognized = 100% x $ 2,500,000 – $ 1,388,889 (previously recognized) = $ 1,111,111 | |||||||||||
Period end adjustments for Revenue | Construction Expense | 13,00,000 | |||||||||
Gross Profit/(Loss) | (1,11,111) | (1,88,889) | H=G-B | (Gross Profit/Loss entry) | CIP (Work-in-progress) | 1,88,889 | |||||
Billings during the year | 12,00,000 | 13,00,000.00 | Construction Revenue | 11,11,111 | |||||||
Collection during the year | 10,00,000 | 15,00,000.00 | |||||||||
Ans to 3 | Calculation of Gross Profit | ||||||||||
Particulars | 2020 | 2021 | Note | ||||||||
Contract Price | 25,00,000 | 25,00,000 | A | ||||||||
Cost Incurred during the year | 15,00,000 | 13,00,000 | B | ||||||||
Estimated cost to complete | 12,00,000 | - | C | ||||||||
Cost Incurred to date | 15,00,000 | 28,00,000 | D |
Related SolutionsMcCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun in 2017 and
completed in 2018. Cost and other data are presented below:
2017
2018
Costs incurred during the
year
$1,500
$1,300
Estimated costs to
complete
1,200
0
Billings during the
year
1,200
1,300
Cash collections during the
year
1,000
1,500
1. Compute the amount of revenue and gross profit recognized
during 2017 and 2018.
2. Assume that McCombs recognizes revenue on this...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun in 2017 and
completed in 2018. Cost and other data are presented below:
2017
2018
Costs incurred during the
year
$1,500
$1,300
Estimated costs to
complete
1,200
0
Billings during the
year
1,200
1,300
Cash collections during the
year
1,000
1,500
1.Compute the amount of revenue and gross profit recognized
during 2017 and 2018.
2.Assume that McCombs recognizes revenue on this contract over...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...On January 1, 2018, Grumpy Contractors agreed to construct a
building at a contract price of $5,000,000. Grumpy estimates that
the project will be finished in 2020. Information related to the
costs and billings for this contract are as follows:
2018
2019
2020
Total costs incurred to date
$1,500,000
$3,300,000
$4,400,000
Estimated costs to complete
2,500,000
1,000,000
-0-
Customer billings to date
1,200,000
2,700,000
4,400,000
Collections to date
1,000,000
2,500,000
4,400,000
Instructions:
Assuming the building was finished in 2020, calculate...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a
building at a contract price of $3,000,000. Marcos estimated total
construction costs would be $2,000,000 and the project would be
finished in 2012. Information relating to the costs and billings
for this contract is as follows:
? 2010?? 2011?? 2012?
Total costs incurred to date?$
750,000?$1,320,000?$2,300,000
Estimated costs to complete?1,250,000? 880,000?-0-
Customer billings to date?1,100,000? 2,000,000?3,000,000
Collections to date?1,000,000? 1,750,000?2,950,000
Instructions
1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...On February 1, 2010, Marcos Contractors agreed to construct a
building at a contract price of $3,000,000. Marcos estimated total
construction costs would be $2,000,000 and the project would be
finished in 2012. Information relating to the costs and billings
for this contract is as follows:
? 2010?? 2011?? 2012?
Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000
Estimated costs to complete?1,250,000? 880,000?-0-
Customer billings to date?1,100,000? 2,000,000?3,000,000
Collections to date?1,000,000? 1,750,000?2,950,000
Instructions
1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...On February 1, 2010, Marsh Contractors agreed to construct a
building at a contract price of $5,800,000. Marsh estimated total
construction costs would be $4,000,000 and the project would be
finished in 2012. Information relating to the costs and billings
for this contract is as follows: 2014 2015 2016 Total costs
incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs
to complete 2,500,000 1,760,000 -0- Customer billings to date
2,200,000 4,000,000 5,600,000 Collections to date 2,000,000
3,500,000 5,500,000
Instructions Fill in...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work...Chicago contractors got $5,400,000 contract to construct a
school building for the City of Chicago. Work on this contract
began in 2013 and the financial data pertaining to this contract is
available here. Cost incurred till Dec.31, 2013 $1,080,000 Billings
made to City $1,000,000 Amount collected from City $ 750,000 The
estimated future cost to complete this contract is $3,240,000.
(a) Prepare Chicago contractors 2013 journal entries using
COMPLETED CONTRACT method. (b) Show how the contract accounts will
appear in...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is...Question: In ABC firm of building, contractors began
construction on 1st April, 2019. The contract is incomplete and the
contractor is confused about how to transfer profit or loss in the
P/L account. Being a student of cost accounting, you are required
to state the rules regarding the transfer of profits to profit and
loss account in case of incomplete contracts( 0%,20%,50%,75%,90 %)
to the contractor.
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...Rookie Construction Limited (RCL) entered into a contract to
construct a building for $975,000. The contract provided for
progress payments. RCL’s accounting year ends December 31. Work
began under the contract on August 1, 2019, and was completed on
October 31, 2021. RCL uses the percentage-of-completion method to
account for this long-term contract. Construction activities are
summarized below:
2019
2020
2021
Construction costs incurred to date
180,000
630,000
825,000
Estimated remaining costs to complete
630,000
190,000
0
Progress Billings during...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...Problem 1: Long-Term Contract
At the beginning of 2018, the Harding Construction Company
received a contract to build an office for $5 million.
Harding will construct the building according to the
specifications provided by the buyer, and the project is estimated
to take three years to complete.
According to the contract, Harding will be the buyer in
installments over the construction period according to a
prearranged schedule.
Information related to the contract is as follows:
2018
2019
2020...
ADVERTISEMENT
ADVERTISEMENT
Latest Questions
ADVERTISEMENT
|