Question

In: Accounting

McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun...

McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2020 and completed in 2021. Cost and other data are presented below:

2020 2021

Costs incurred during the year $1,500,000 $1,300,000

Estimated costs to complete 1,200,000 0

Billings during the year 1,200,000 1,300,000

Cash collections during the year 1,000,000 1,500,000

Part 1: Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2020 and 2021.

Part 2: Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries to record costs, billings, collections, and profit (loss) recognition. Round your answers to the nearest whole dollar.

Part 3: Assume that McCombs recognizes revenue upon project completion. Required: Compute the amount of gross profit recognized by McCombs during 2020 and 2021.

Solutions

Expert Solution

McCombs Contractor 2020 2021
Ans to 1 Calculation of Gross Profit Ans to 2 Journal Entries Debit $ Credit $ Debit $ Credit $
Particulars 2020 2021 Note Costs Incurred CIP (Work-in-progress) 15,00,000 13,00,000
Contract Price           25,00,000           25,00,000 A Cash 15,00,000 13,00,000
Cost Incurred during the year           15,00,000           13,00,000 B
Estimated cost to complete           12,00,000                     -   C Billing Accounts Receivable 12,00,000 13,00,000
Cost Incurred to date           15,00,000           28,00,000 D Billing on CIP 12,00,000 13,00,000
(Sum total of the cost incurred during the year)
Estimated total cost           27,00,000           28,00,000 E=C+D Receiving Payments Cash 10,00,000 15,00,000
Percentage complete 55.56% 100.00% F=D/E Accounts Receivable 10,00,000 15,00,000
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized           13,88,889           11,11,111 G Period end adjustments for Revenue Construction Expense 15,00,000
(Contract Price*Percentage complete)- revenue previously recognized (Gross Profit/Loss entry) CIP (Work-in-progress)     1,11,111
Year 2020: 55.56% completed. Revenue recognized = 55.56% x $ 2,500,000 = $ 1,388,889. Construction Revenue 13,88,889
Year 2021: 100% completed. Revenue recognized = 100% x $ 2,500,000 – $ 1,388,889 (previously recognized) = $ 1,111,111
Period end adjustments for Revenue Construction Expense 13,00,000
Gross Profit/(Loss)         (1,11,111)         (1,88,889) H=G-B (Gross Profit/Loss entry) CIP (Work-in-progress)     1,88,889
Billings during the year           12,00,000      13,00,000.00 Construction Revenue 11,11,111
Collection during the year           10,00,000      15,00,000.00
Ans to 3 Calculation of Gross Profit
Particulars 2020 2021 Note
Contract Price           25,00,000           25,00,000 A
Cost Incurred during the year           15,00,000           13,00,000 B
Estimated cost to complete           12,00,000                     -   C
Cost Incurred to date           15,00,000           28,00,000 D

Related Solutions

McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                         2017                2018 Costs incurred during the year                           $1,500               $1,300 Estimated costs to complete                                1,200                        0 Billings during the year                                      1,200                  1,300 Cash collections during the year                          1,000                  1,500 1. Compute the amount of revenue and gross profit recognized during 2017 and 2018. 2. Assume that McCombs recognizes revenue on this...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                         2017                2018 Costs incurred during the year                           $1,500               $1,300 Estimated costs to complete                                1,200                        0 Billings during the year                                      1,200                  1,300 Cash collections during the year                          1,000                  1,500 1.Compute the amount of revenue and gross profit recognized during 2017 and 2018. 2.Assume that McCombs recognizes revenue on this contract over...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000 Instructions Fill in...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work...
Chicago contractors got $5,400,000 contract to construct a school building for the City of Chicago. Work on this contract began in 2013 and the financial data pertaining to this contract is available here. Cost incurred till Dec.31, 2013 $1,080,000 Billings made to City $1,000,000 Amount collected from City $ 750,000 The estimated future cost to complete this contract is $3,240,000. (a) Prepare Chicago contractors 2013 journal entries using COMPLETED CONTRACT method. (b) Show how the contract accounts will appear in...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is...
Question: In ABC firm of building, contractors began construction on 1st April, 2019. The contract is incomplete and the contractor is confused about how to transfer profit or loss in the P/L account. Being a student of cost accounting, you are required to state the rules regarding the transfer of profits to profit and loss account in case of incomplete contracts( 0%,20%,50%,75%,90 %) to the contractor.
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT