Question

In: Civil Engineering

a- • Must a contractor be delayed beyond the contractual project duration in order to successfully...

a- • Must a contractor be delayed beyond the contractual project duration in order to successfully file a claim for 15 delay damages? • Explain your answer

b- • A contract contains the following clause: • “The owner specifically reserves the right to modify the progress schedule as required by the conditions of the work.” Can a contractor that has been delayed by the owner’s revisions to the order of the work in the schedule successfully file a claim for a time extension? • Explain your answer

c- • What is the role of “as-built” schedules in litigation involving delays?

d- • To minimize the chance of losses, suggest a methodology to follow when a delay, that has the potential 18 of resulting in litigation, occurs on a construction project.

e- • Explain two of the added costs that might be incurred by the contractor as a result of a change issued by the owner.

Solutions

Expert Solution

a) Most contracts state that a contractor is not responsible for delays from causes beyond the contractor’s control. In fact, some state contractor’s regulations require such an explicit “force majeure” clause in contracts. This type of force majeure clause entitles a contractor to a time extension only. The contractor is protected from liquidated damage or other claims for delays beyond the contractor’s control, but the contractor’s affirmative claim for compensation for the delay will be controlled by other contract provisions. Hence contractor must not be delayed beyond the contractual project duration in order to successfully file a claim for 15 delay damages.

b) Most construction contracts state that there will be no payment for changes in the work unless ordered in a signed writing. These clauses are generally enforceable and can obviously impact a contractor’s right or ability to collect for changes, delays and other claims. If the contract has a written change order clause, the contractor may not get paid unless there is a written change order. It does not matter how much work was done, how much it cost or who ordered the work. Written change order clauses are actually required by many state licensing statutes or regulations. If it is impossible to get a signed change order or work must begin immediately, the contractor has a “claim.” The claims provisions in the contract become important, particularly written notice requirements.

c) To identify the activities in which delay occurred, an “as built” schedule is prepared showing the durations of each of the activities as actually performed or “as built.” The as planned schedule must also be analyzed to correct any errors. An “as planned to as built” analysis will compare the as built schedule to the adjusted as planned schedule to identify activities that took longer than planned or how sequencing of activities changed. A “collapsed as built” analysis uses a reverse methodology that starts with an as built schedule and then deletes or removes delays. The as built schedule is then analyzed without each delay and concludes that the project could have been completed at an earlier date if the delays had not occurred.

d)

e) Following are the two added costs that might be incurred by the contractor as a result of a change issued by the owner:-

(1) Direct Cost - Direct costs are the easiest to identify and quantify because they’re tangible. They also often visibly impact project outcomes; therefore, they’re generally easier to justify in the event of changes or alterations. Typical direct costs include labor, materials, equipment, and expenses related to the change. However, there are additional direct labor, material, and equipment costs that are often overlooked and therefore impact profitability.

(2) Consequential Cost - The final piece in recovering your true costs is to understand and account for consequential costs. These are the costs incurred due to timing and scope changes, which may impact overall project costs or duration. It include Stacking of trades, Reassignment of manpower, Dilution of supervision, Site access interference, or Impact of seasonal and weather conditions.


Related Solutions

A construction project is carried out by a general contractor with the following descriptions: Project Duration:...
A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract Amount: 20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181 Budget Amount: 100,936+200,081+300,685 Contract Terms and Conditions Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after...
A contractor must choose between buying or renting a crane for the duration of a 5...
A contractor must choose between buying or renting a crane for the duration of a 5 year construction project. The contractor uses an MARR of 8%. At the end of the project, the crane can be sold for 26% of its initial cost. The cost to operate and maintain the crane is $210,000 per year. Renting the crane costs $330,000 per year including all operating and maintenance costs. Determine the maximum amount the contractor should pay to purchase the crane...
In order for companies to successfully sell products or services using a sales force, they must:...
In order for companies to successfully sell products or services using a sales force, they must: (Explain with a good marketing example.) 2. How would you describe the sales environment? 3. Define personal selling (PS). 4. When does PS become “more” important?
____ provide(s) protection against the failure of a contractor to fulfill contractual obligations. Fidelity bonds Key...
____ provide(s) protection against the failure of a contractor to fulfill contractual obligations. Fidelity bonds Key person insurance Surety bonds Business insurance
When creating a synthetic security, in order to successfully create the security, a number of assumptions or theories must be accepted or adhered to:
When creating a synthetic security, in order to successfully create the security, a number of assumptions or theories must be accepted or adhered to:a. One assumption is liquidity, that there is enough liquidity to insure stable pricing. Another is replication; the synthetic security is able to be replicated.b. There are many assumptions or theories. Two that must occur is the theory of pricing, or market-clearing, the second is denotation, the theory associated with a security’s notional value. c. One assumption is...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursed construction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursedconstruction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of financial...
What is postponement or delayed differentiation? Identify the order winning competitive factors for an automobile industry
What is postponement or delayed differentiation? Identify the order winning competitive factors for an automobile industry
You are a contractor on a $45 million project in down town Los Angeles. The project...
You are a contractor on a $45 million project in down town Los Angeles. The project is scheduled to be completed in 2 years. You are 6 months into the project so far and project performance reports indicate that the budget has been exceeded by 10% thus far. Your schedule has also been delayed by more than a month due to subcontractor issues and labor disagreements. As a result, the quality of the job is suffering. It is your job...
If the owner of the project experienced delayed financial funding from the bank, is he/she allowed...
If the owner of the project experienced delayed financial funding from the bank, is he/she allowed to delay the payment of the moneys due to the contractor? Explain. In regards to construction contracts.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT