1. A contractor needs water at a remote construction site for a five year project. A...

1. A contractor needs water at a remote construction site for a five year project. A pipeline from a river,six miles away, will supply the water. The cost of the pipeline and the cost of pumping the water will vary with pipe size. See table below. The contractor uses a MARR of 7%. The contractor plans to work 2000 hours per year, and that is the time the pump will run each year. At the end of five years the salvage value of the pipeline will equal the cost of its demolition.
Part A. (20 points) Which pipe diameter should she select? [Copy pertinent values before you start Part B.
Part B. (5 points) The contractor may work overtime, so the work year has more than 2000 hours. How many hours must they work so that the costs of the 3 inch and 4 inch options are equal?
Pipe Diameter
2 inch 3 inch 4 inch 6 inch
Cost of pipeline and pump $22,000.00 $23,000.00 $25,000.00 $30,000.00
Cost per hour for pumping ($/hr) $1.20 $0.65 $0.50 $0.40

Solutions

Expert Solution

PART A

Annuity factor of 7% for 5 Years = [1-(1+r)^-n] / r = (1-(1+0.07)^-5) / 0.07 = 4.100197436

Calculation of PV of Cash outflow for all Pipe diameter

Annuity factor/Muliplier 2 inch 3 inch 4 inch 6 inch
Cost of pipeline and pump 1 22000 23000 25000 30000
Cost per hour for pumping ($/hr) 4.100197436 9840.473846 5330.256667 4100.197436 3280.157949
(1.2*2000*4.100197436) (0.65*2000*4.100197436) (0.5*2000*4.100197436) (0.4*2000*4.100197436)
Total 31840.47385 28330.25667 29100.19744 33280.15795

As per the above table since PV of 3 inch diameter is the least of all the pipes therefore 3 inch pipe diameter should be selected

Part B

Difference in Fixed Cost of 3 inch and 4 inch pipe = 25000 - 23000 = $2000

Difference in cost per hour for pumping = $0.65 - $0.50 = $0.15

Total per hour cost for pumping for 5 years at PV = 0.15 * 4.10019744 = $0.615029615

Therefore Total hours per year required = DIff in fixed cost/Total per hour cost for pumping for 5 years at PV = 2000/0.615029615 = 3251.875926 hours per year

Therefore the contractor must work for 3251.875926 hours per year so that the cost of 3 inch & 4 inch pipe are equal


Related Solutions

A construction contractor needs to choose between two suppliers of dump trucks. Supplier 1 has an...
A construction contractor needs to choose between two suppliers of dump trucks. Supplier 1 has an initial cost of $125,000 and annual operating cost of $25, 000 per year. Supplier 2 has initial cost $160,000 and has annual operating cost of 20,000 per year. The truck fleet has the same 10-year life forecast Based on incremental rate of return (IROR) and a MARR of 8%, and which supplier of trucks should the contractor choose? Please do not use excel.
A construction project is carried out by a general contractor with the following descriptions: Project Duration:...
A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract Amount: 20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181 Budget Amount: 100,936+200,081+300,685 Contract Terms and Conditions Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
On January 1, Year 1, Company ABC hired a general contractor to begin construction of a...
On January 1, Year 1, Company ABC hired a general contractor to begin construction of a new office building. ABC negotiated a $900,000, five-year, 10% loan on January 1, Year 1, to finance construction. Payments made to the general contractor for the building during Year 1 amount to $1,000,000. Payments were made evenly throughout the year. Construction is completed at the end of Year 1, and ABC moves in and begins using the building on January 1, Year 2. The...
You are a construction engineer working for a large utility contractor. The project you are working...
You are a construction engineer working for a large utility contractor. The project you are working on is in New York City (Manhattan). You are installing approximately 1,000 L.F. of 48” dia. RCP for storm drains. Invert elevation ranges from 9’ to 14’ below grade. Pay lines for the trench are indicated in the attached specification. Soil characteristics range from SM to SC, based on the Unified Soil Classification. What considerations would you make with regards to a trenching &...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Part 2 – Construction Cost A sub-contractor needs to decide which companies they should hire for...
Part 2 – Construction Cost A sub-contractor needs to decide which companies they should hire for each type of building they want to construct. Below is the estimated time it should take (in hours) for each of the different types of buildings they work on. Building Excavating Framing Electrical Plumbing Finishing Office Space 45 100 88 132 312 School 56 250 147 28 290 Apartments 84 480 75 125 244 Grocery Store 95 160 26 78 236 Below are the...
You're a contractor who needs to lease space for a field office during the five years...
You're a contractor who needs to lease space for a field office during the five years of a construction project. The owner of the building where you want to rent space offers you three lease options. Each option assumes payment at the beginning of each year, and i=4% per year. which option would you chose? A) First year annual rent of $12,000, with an increase of $2,500 per year for each of the next four years B) First year annual...
Contaminated water: In a sample of 42 water specimens taken from a construction site, 26 contained...
Contaminated water: In a sample of 42 water specimens taken from a construction site, 26 contained detectable levels of lead. Part 1 of 3 Your Answer is correct (a) Construct a 90% confidence interval for the proportion of water specimens that contain detectable levels of lead. Round the answer to at least three decimal places. A 90% confidence interval for the proportion of water specimens that contain detectable levels of lead is 0.497<<p0.743 . Part: 1 / 3 1 of...
During the construction phase of a health-care project, delays not attributed to the contractor were experienced,...
During the construction phase of a health-care project, delays not attributed to the contractor were experienced, but the contractor was delayed in submitting all delay information required by the contract until 7 days before the contractual completion date, can the architect issue an extension of time prior to the completion date? Explain.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT