Question

In: Civil Engineering

You are field manager for the general contractor on a multi-story office building under construction. The...

You are field manager for the general contractor on a multi-story office building under construction. The project has risen all 15 floors above the foundation. The roof is on and the exterior façade of the structure, consisting of alternating blue glass ribbon windows and red granite panels, has “dried in” the project many weeks ago. On the third, seventh and fifteenth floors, the executive offices located on the corners of the building have blue glass doors that lead outside to small balconies. Interior work (walls, electricity, hvac, water, sewer, sprinker, suspended ceiling, millwork, carpet, etc.) is well under way on several of the lower floors. After carefully checking the blueprints, shop drawings and bulletin drawings completed and approved by Architects & Engineers, the superintendent for the plumbing contractor stops by your office to mention that the design doesn’t seem to provide for floor drains on the exterior balconies. A quick conversation with the architect reveals that a serious design error has occurred. Floor drains and the necessary piping will need to be retrofitted that tie-in to the vertical pipe for the roof drain, located near the center of the building. There is vertical air space (plenum) available (approx. 2 feet) on each floor between the bottom of the concrete floor slab above and the top of the ceiling grid that can be used to route the connecting pipes to each balcony drain. However, many specialty contractors have already installed their work on several floors in the plenum space. Another problem is the length of connecting piping needed for each balcony drain. Following the minimum slope for the drain pipe allowed by building code, the distance is so great from each balcony to the vertical roof drain in the center of the building that the connecting pipe would be visible below the ceiling grid, which is not acceptable to the project owner. So, the piping for each balcony drain will have to be routed at the minimum slope above the ceiling grid partway to an interior column, where a vertical pipe and floor penetration will be needed. Each balcony drain pipe will continue in the plenum space on the floor below in order to reach the roof drain. The vertical piping next to certain interior columns can be hidden with studs and drywall. In this manner, each of the retrofitted balcony drains can connect to the vertical roof drain pipe without being visible in the interior office space on each floor.

List Five things/actions that you as a Manager could do to keep the project going and solve the problem as well as what parts and how could your Schedule be affected:

Another Problem would be Who Pays: Who and Why?

Solutions

Expert Solution

The five actions I need to do as a manager are:-

1. Stop all the interior work (walls, electricity, hvac, water, sewer, sprinker, suspended ceiling, millwork, carpet, etc) so that the plumbing work could be done first.

2. Make space for plumbing pipe in vertical plumen by adjusting other works in plumen

3. Have a meeting with the owners and the architect about the extra cost and who is going to pay that cost

4. Ask architect to design interior again so that the plumbing pipe can be hidden in the ceiling grid.

5. Go though the design again, so that , if that is any other problem in the building design or structure which you have not attended earlier can be attended and rectified

Secondly,

The amounts shall be partially paid by the contractor and the architect because it is a mistake of the architect so the extra cost occuring due to it has to be beared by the architect and the original cost as planned has to be paid by the contractor.


Related Solutions

A governmental entity is the recipient of a bequest of a multi-story office building that the...
A governmental entity is the recipient of a bequest of a multi-story office building that the government intends to use as a new city hall. The building has a historical cost of $850,000; a book value in the hands of the benefactor of $700,000; and a fair value of $1,050,000. The city should recognize on its governmental fund financial statements, donations revenue of a) $-0-. b) $700,000. c) $850,000. d) $1,050,000 Explanation to why answer is d A governmental entity...
A government is the recipient of a bequest of a multi-story office building that the government...
A government is the recipient of a bequest of a multi-story office building that the government intends to use as a new city hall. The building has a historical cost of $850,000; a book value in the hands of the benefactor of $700,000; and a fair value of $1,050,000. The city should recognize on its governmental fund financial statements donations revenue of $-0-. $700,000. $850,000. $1,050,000 Explanation to the answer please
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction...
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction work commenced on April 1, 2020, and it is expected to continue through July 31, 2022, the estimated completion date. Reed made progress payments to the contractor in 2020 as follows: Date Amount April 1 $ 48,000 June 1 195,000 September 1 322,000 November 1 67,000 $632,000 As stated in A5 above, Reed took a 1-year, 9%, $225,000 construction loan to help fund the...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
You are the new CM for a 2 story OFFICE building that is lagging behind by...
You are the new CM for a 2 story OFFICE building that is lagging behind by the following: Wall framing in upper floor is incomplete and needs 2 more days to complete. Doors for installation first floor have not been delivered. Painting contractor crew cannot start painting since floor is not clear of debris ect. Foreman has left due to family emergency. Electrical contractor is 3 days behind. Give your interpretation of how you will approach this situation and provide...
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
Advise when a contractor will not be in breach of a construction contract as defined under...
Advise when a contractor will not be in breach of a construction contract as defined under the Housing Grants Construction and Regeneration Act 1996, if he wants to stop work on a project due to non-payment.
a building design was complete and is under construction. You had selected a window with a...
a building design was complete and is under construction. You had selected a window with a U-value of 1.6 and a solar heat gain coefficient (SHGC) of 0.25. The window manufacturer informs you that they no longer carry that window model, but that they can give you a window with a U-value of 1.6 and SHGC of 0.4. How would this new window impact your building's modeled heating and cooling energy consumption?
a building design was complete and is under construction. You had selected a window with a...
a building design was complete and is under construction. You had selected a window with a U-value of 1.6 and a solar heat gain coefficient (SHGC) of 0.25. The window manufacturer informs you that they no longer carry that window model, but that they can give you a window with a U-value of 1.6 and SHGC of 0.4. How would this new window impact your building's modeled heating and cooling energy consumption?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT