In: Finance
| 
 Project  | 
 Year 0  | 
 Year 1  | 
 Year 2  | 
 Year 3  | 
 Year 4  | 
| 
 A  | 
 -$103  | 
 28  | 
 34  | 
 44  | 
 53  | 
| 
 B  | 
 -$103  | 
 53  | 
 44  | 
 34  | 
 24  | 
What is the IRR of each project? Which project should you
choose?
Select one:
a. IRR of Project A = 17.7%, IRR of Project B = 21.7%. Choose project A.
b. IRR of Project A = 17.7%, IRR of Project B = 21.7%. Choose project B.
c. IRR cannot be used to compare these projects. Choose project A because it has a higher NPV.
d. IRR of Project A = 11.9%, IRR of Project B = 17.7%. Choose project B.
*Please calculate manually and show step by step, I need a major refresher on IRR and NPV
Answer : (b) IRR of Project A = 17.7%, IRR of Project B = 21.7%. Choose project B.
Excel sheet used to solve the question :

Formula sheet :