In: Civil Engineering
Construct a precedence diagram (AON) b) On the diagram, compute the four activity dates (ESD, EFD, LSD, and LFD) and the floats (TF and FF) for each activity. c) Identify critical event(s), critical activities, and critical path(s) Please calculate and show results on the diagram in the following form: Act Time Predecessors B 5 - M 4 B N 9 B P 8 B L 6 M F 5 M,N C 8 N,P K 6 P G 7 L,F,C A 3 F,C D 7 C,K E 13 K H 3 G,A J 2 D,E,H