Question

In: Accounting

Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit

1 unit of material B x $ 8.00 per unit

Direct labor 3 hours x $ 18.00 per hour

Activity for September

Materials purchased

Material A 6,750 units x $ 6.20 per unit

Material B 1,650 units x $ 8.50 per unit

Materials used

Material A 6,225 units

Material B 1,508 units

Direct labor used 4,425 hours x $ 18.80 per hour

Production output 1,500 units

There were no beginning direct materials inventories.

(a) Determine the materials price and quantity variances.

Material A Material B

Materials price variance $Answer Answer F U $Answer Answer F U

Materials quantity variance Answer Answer F U Answer Answer F U

(b) Determine the labor rate and efficiency variances.

Labor rate variance $Answer Answer F U

Labor efficiency variance $Answer Answer F U

Solutions

Expert Solution

Computation of Material Price Variance
Standarrd costof Raw material/Unit $32
Material A:   $6/Unit
Material B : $8/Unit
Actual Cost of Raw Material/Unit
Material A : $6.20/Unit
Material B: $8.50/Unit
Actual Material Consumed
Material A : 6225 Unit
Material B: 1508 Units
Material Price Variance
( Standard Price- Actual Price)* Actual Quantity
Material A: ( $6-$6.20 )* 6225 Unit ($1,245) Unfavourable
Material B : ( $ 8- $8.50)* 1508 Unit ($754) Unfavourable
Total Material Price Variance ($1,999) Unfavourable
Computation of Material Quantity Variance
Standard Quantity of Raw Material
Material A: (4 Unit* 1500 Unit) 6000 Unit
Material B : ( 1 Unit*1500 Unit) 1500 Unit
Actual material Consumed
Material A: ( 6225) 6225 Unit
Material B : ( 1508) 1508 Unit
Material Quanitity Variance
( Standard Quanity - Actual Quantity) Standard Price
Material A: (6000 Unit-6225 Unit) * $6 -$1,350.00 Unfavourable
Material B: ( 1500 Unit-1508 Unit) * $8 -$64.00 Unfavourable
Total Material Quantity Variance -$1,414.00 Unfavourable
Computation of Labour Rate Variance
Standarrd Rate of Direc Labour $18.0
Actual Rate of Direc Labour $18.80
Actual Labour Hour used 4425 Hour
Labour Rate Variance
( Standard Rate - Actual Rate)* Actual Labour Hour Used
( $18-$18.80) * 4425 Hour ($3,540) Unfavourable
Computation of Labour Efficiency Variance
Standard Labout Hour Required for 1500 Unit Produced ( 3 Hour* 1500 Unit) 4500 Hour
Actual Labour Hour Used 4425 Hour
Standard Rate of Direc Labour $18/ Hour
Labour Efficiency Variance
( Standard l Hours - Actual Hour) Standard Price $1,350.00 Favourable
(4500-4425 Hour) * $18/Hour

Related Solutions

Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A × $2.00 per unit 1 unit of material B × $3.00 per unit Direct labor 3 hours × $8.00 per hour Activity for September Materials purchased Material A 2,600 units × $2.05 per unit Material B 700 units × $3.10 per unit Materials used Material A 2,250 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 3 units of material A x $8.00 per unit 2 units of material B x $4.00 per unit Direct labor 2 hours x $15.00 per hour Activity for September Materials purchased Material A 7,000 units x $7.80 per unit Material B 4,800 units x $4.50 per unit Materials used Material A 6,430 units...
The following information pertains to the standard costs and actual activity for Repine Company for September:...
The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit: Direct materials. . . .. 4 units of material A x $6.00 per unit, 1 unit of material B x $8.00 per unit Direct labor. . . . . . . 3 hours x $18.00 per hour Activity for September Materials purchased: Material A . . . . . . . . . 6,750 units x $6.20 per unit Material...
The following information is for the standard and actual costs for the Happy Corporation Standard Costs:...
The following information is for the standard and actual costs for the Happy Corporation Standard Costs: Budgeted units of production - 16,000 (80% of capacity) Standard labor hours per unit - 4 Standard labor rate - $28 per hour Standard material per unit - 9 lbs Standard material cost - $ 14 per pound Standard variable overhead rate - $18 per labor hour Budgeted fixed overhead - $650,000 Fixed overhead rate is based on budgeted labor hours at 80% capacity....
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...
The following information is for the standard and actual costs for Happy Corporation: Standard Costs: Budgeted...
The following information is for the standard and actual costs for Happy Corporation: Standard Costs: Budgeted units of production 16,000 [80% (or normal) capacity] Standard labor hours per unit 4 Standard labor rate $26 per hour Standard material per unit 8 lbs. Standard material cost $12 per pound Standard variable overhead rate $15 per labor hour Budgeted fixed overhead $640,000 Fixed overhead rate is based on budgeted labor hours at 80% (or normal) capacity. Actual Costs: Actual production 16,500 units...
Material and Labor Variances The following actual and standard cost data for direct material and direct...
Material and Labor Variances The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 4,200 lbs. @ $4.90 4,000 lbs. @ $5.20 Direct labor 5,700 hrs. @ $9.30 6,000 hrs. @ $9.50 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable. Materials...
Question 2 – Chap. 10 Material and Labor Variances The following actual and standard cost data...
Question 2 – Chap. 10 Material and Labor Variances The following actual and standard cost data for direct material and direct labor relate to the production of 2,000 units of a product: Actual Costs Standard Costs Direct material 17,550 lbs. @ $5.30 18000 lbs. @ $5.10 Direct labor 27,900 hrs. @ $8.40 27,000 hrs. @ $8.70 Determine the following variances: Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable...
The following information pertains to each of the company’s first two years of operations: Variable costs...
The following information pertains to each of the company’s first two years of operations: Variable costs per unit: Manufacturing: Direct materials $ 25 Direct labor $ 12 Variable manufacturing overhead $ 4 Variable selling and administrative $ 3 Fixed costs per year: Fixed manufacturing overhead $ 320,000 Fixed selling and administrative expenses $ 60,000 During its first year of operations, Walsh produced 50,000 units and sold 40,000 units. During its second year of operations, it produced 40,000 units and sold...
Q 22 The following data relates to actual output, actual costs and variances for the four-weekly...
Q 22 The following data relates to actual output, actual costs and variances for the four-weekly accounting period number 4 of a company from Bole which makes only one product. The value of work in progress at the end of period 4 was the same as the value of work -in - progress at the beginning of the month Actual production of product XY 18,000 units Actual costs incurred GHS'000 Direct materials purchased and used (150,000 kg) 210 Direct labour...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT