Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs)

Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down by cost type (materials, labor, overhead) and further by cost variances within cost types and usage or efficiency variances within cost types:

Direct Materials Cost Variance Direct Materials Price Variance
Direct Materials Quantity Variance
Total Manufacturing Cost Variance Direct Labor Cost Variance Direct Labor Rate Variance
Direct Labor Time Variance
Factory Overhead Cost Variance Variable Factory Overhead Controllable Variance
Fixed Factory Overhead Volume Variance

Manufacturing cost variances are determined using a standard costing system. Standard costs are predetermined  costs that should be incurred under efficient operating conditions. Standard costing is most suited to manufacturing  organizations, where activities consist of common or repetitive operations and the direct costs required to produce each item are defined.

In a standard costing system, it is important to understand that costs are compared to budget based on a flexible budget rather than a fixed budget. Flexible budgets use standard  costs and actual  production volume. This means that the actual costs in the period are compared to the number of units produced in the period at the standard cost.

Feedback

Standards are set up as part of the budgeting process and are used when per unit costs can be estimated under efficient operating conditions. Remember that flexible budgets account for changes in volume.

If actual costs are greater than standard costs, the variance is unfavorable , alternatively, if actual costs are less than standard costs, the variance is favorable .

Direct Materials Cost Variance

Calculating Direct Materials Cost Variance, you can see that the actual costs are higher  than standard and the actual quantity purchased and used is less  than standard. The two variances are combined for a total favorable  direct material cost variance of $.

Direct Labor Cost Variance

Calculating Direct Labor Cost Variance, you can see that the actual costs are higher  than standard and the actual hours are higher  than standard. The two variances are combined for a total favorable  direct labor cost variance of $.

Feedback

The illustrations provide the information to complete the problem.

The standard cost sheet for a product is shown.


Manufacturing Costs

Standard price

Standard Quantity
Standard Cost
per unit
Direct materials $4.70 per pound 5.60 pounds $ 26.32
Direct labor $12.28 per hour 2.30 hours $ 28.24
Overhead $2.20 per hour 2.30 hours $ 5.06
$ 59.62

The company produced 3,000 units that required:

• 17,300 pounds of material purchased at $4.55 per pound

• 6,810 hours of labor at an hourly rate of $12.68 per hour

• Actual overhead in the period was $15,580

Fill in the Budget Performance Report for the period. Some amounts are provided. Round your answers to the nearest dollar. However, do not round your intermediate calculations.

Budget Performance Report

Manufacturing Costs:
3,000 units

Actual
Costs

Standard
Costs
Variance
(Favorable)/
Unfavorable
Direct materials $78,715 $ $
Direct labor 84,732
Overhead 15,580
$ $ $1,774

Split the direct materials cost variance into the materials price varaince and the Direct materials quantity variance. Remember that you want to isolate the price variance from the quantity variance so be sure to use factors that do not overlap. Also remember that the two variances should equal the total direct material cost variance.

Direct materials price variance: Direct materials quantity variance:
(Actual price - Standard price) x actual quantity (Actual quantity - Standard quantity) x standard  price
$2,595 favorable $2,350 unfavorable

Split the direct labor cost variance into the direct labor rate variance and the direct labor time variance. Remember that you want to isolate the price variance from the efficiency variance so be sure to use factors that do not overlap. Also remember that the two variances should equal the total direct labor cost variance.

Direct labor rate variance: Direct labor time variance:
(Actual rate - Standard rate) x actual hours (Actual hours - Standard hours) x standard  labor rate
$2,724 unfavorable $1,105 favorable

Manufacturing variances are period costs that are rolled into cost of sales  and reported on the income statement  . A favorable variance is recorded as a credit  and an unfavorable variance is recorded as a debit .

Solutions

Expert Solution

Standard per unit
Direct Material 5.6 pound
Direct labor 2.3 hr
Variable Overhead 2.3 hr
Standard DATA for 3000 units
Quantity (SQ) Rate (SR) Standard Cost
[A] [B] [A x B]
Direct Material ( 5.6 pound x 3000 units)=16800 pound $          4.70 $       78,960.00
Direct labor ( 2.3hr x 3000 units)=6900hr $        12.28 $       84,732.00
Variable Overhead ( 2.3hr x 3000 units)=6900hr $          2.20 $       15,180.00
Actual DATA for 3000 units
Quantity (AQ) Rate (AR) Actual Cost
Direct Material 17300 $              4.550 $           78,715.00
Direct labor 6810 $              12.68 $           86,350.80
Variable Overhead 6810 $                2.29 $           15,580.00
Standard DATA for 3000 units
Quantity (SQ) Rate (SR) Standard Cost
Direct Material 16800 $                4.70 $           78,960.00
Direct labor 6900 $              12.28 $           84,732.00
Variable Overhead 6900 $                2.20 $           15,180.00
Budget Performance Report
Variance
Manufacturing Costs: Actual Standard (Favorable)/
3,000 units Costs Costs Unfavorable
Direct materials $78,715 78960 ($245)
Direct labor 86350.8 84,732 $1,619
Overhead 15,580 15180 $400
$180,646 $178,872 $1,774
Material Price Variance
( Standard Rate - Actual Rate ) x Actual Quantity
( $                        4.70 - $                       4.55 ) x 17300
2595
Variance $              2,595.00 Favourable-F
Material Quantity Variance
( Standard Quantity - Actual Quantity ) x Standard Rate
( 16800 - 17300 ) x $                           4.70
-2350
Variance $              2,350.00 Unfavourable-U
Labor Rate Variance
( Standard Rate - Actual Rate ) x Actual Labor Hours
( $                     12.28 - $                    12.68 ) x 6810
-2724
Variance $              2,724.00 Unfavourable-U
Labour Efficiency Variance
( Standard Hours - Actual Hours ) x Standard Rate
( 6900 - 6810 ) x $                        12.28
1105.2
Variance $              1,105.20 Favourable-F
Note no. Explanation
1 Standard data is calculated by considering budgeted data and using actual data.
2 Variance refers to the difference between Standard cost and Actual cost.
3 If Actual cost is MORE than Standard Cost, the Variance is said to be UNFAVOURABLE.
4 If Actual cost is LESS than Standard Cost, the Variance is said to be FAVOURABLE.

Related Solutions

Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A × $2.00 per unit 1 unit of material B × $3.00 per unit Direct labor 3 hours × $8.00 per hour Activity for September Materials purchased Material A 2,600 units × $2.05 per unit Material B 700 units × $3.10 per unit Materials used Material A 2,250 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 3 units of material A x $8.00 per unit 2 units of material B x $4.00 per unit Direct labor 2 hours x $15.00 per hour Activity for September Materials purchased Material A 7,000 units x $7.80 per unit Material B 4,800 units x $4.50 per unit Materials used Material A 6,430 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Repine Company for September: Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit Direct labor 3 hours x $ 18.00 per hour Activity for September Materials purchased Material A 6,750 units x $ 6.20 per unit Material B 1,650 units x $ 8.50 per unit Materials...
Manufacturing Cost Variances. a) Make up your own Standard and Actual data for a production run...
Manufacturing Cost Variances. a) Make up your own Standard and Actual data for a production run of 20,000 units of a product. Make sure your actual data is different than your standard data. Use the following formats for 20,000 units:               Cost Type                   Standard Price/Rate   x    Standard Quantity = Standard Cost Direct Materials (DM)         $?.??                   x                     ???          =            ???                          Direct Labor (DL)                 $?.??                   x                     ???          =            ???                           Factory Overhead (FO)        $?.??                   x                     ???            =           ???                                                               Total Standard Product...
Mastery Problem: Evaluating Variances from Standard Costs Sole Purpose Shoe Company Sole Purpose Shoe Company is...
Mastery Problem: Evaluating Variances from Standard Costs Sole Purpose Shoe Company Sole Purpose Shoe Company is owned and operated by Sarah Charles. The company manufactures casual shoes, with manufacturing facilities in your state. Sarah began the business this year, and while she has a great deal of experience in manufacturing popular and comfortable shoes, she needs some help in evaluating her results for the year, and asks for your help. Starting Questions Sarah’s first questions for you have to do...
Mastery Problem: Evaluating Variances from Standard Costs Sole Purpose Shoe Company Sole Purpose Shoe Company is...
Mastery Problem: Evaluating Variances from Standard Costs Sole Purpose Shoe Company Sole Purpose Shoe Company is owned and operated by Sarah Charles. The company manufactures casual shoes, with manufacturing facilities in your state. Sarah began the business this year, and while she has a great deal of experience in manufacturing popular and comfortable shoes, she needs some help in evaluating her results for the year, and asks for your help. Starting Questions Sarah’s first questions for you have to do...
Mastery Problem: Evaluating Variances from Standard Costs Sole Purpose Shoe Company Sole Purpose Shoe Company is...
Mastery Problem: Evaluating Variances from Standard Costs Sole Purpose Shoe Company Sole Purpose Shoe Company is owned and operated by Sarah Charles. The company manufactures casual shoes, with manufacturing facilities in your state. Sarah began the business this year, and while she has a great deal of experience in manufacturing popular and comfortable shoes, she needs some help in evaluating her results for the year, and asks for your help. Direct Materials Under normal conditions, Sarah spends $8.40 per unit...
A recent review of actual operating results compared to budget indicates an unfavorable cost variance on...
A recent review of actual operating results compared to budget indicates an unfavorable cost variance on both direct materials and direct labor (that is, we are spending more on materials and labor than we expected to). Which departments may be responsible for additional costs? For example, can we blame Human Resources for hiring inexperienced factory workers who have been making many mistakes causing us to waste materials?
A recent review of actual operating results compared to budget indicates an unfavorable cost variance on...
A recent review of actual operating results compared to budget indicates an unfavorable cost variance on both direct materials and direct labor. (that is, we are spending more on materials and labor than we expected to). Which departments may be responsible for additional costs? For example, can be blame Human Resources for hiring inexperienced factory workers who have been making many mistakes causing us to waste materials?
A recent review of actual operating results compared to budget indicates an unfavorable cost variance on...
A recent review of actual operating results compared to budget indicates an unfavorable cost variance on both direct materials and direct labor. (that is, we are spending more on materials and labor than we expected to). Which departments may be responsible for additional costs? For example, can be blame Human Resources for hiring inexperienced factory workers who have been making many mistakes causing us to waste materials?