In: Accounting
Material and Labor Variances
The following actual and standard cost data for direct material and
direct labor relate to the production of 2,000 units of a
product:
Actual Costs | Standard Costs | |||||||
---|---|---|---|---|---|---|---|---|
Direct material | 4,200 | lbs. @ | $4.90 | 4,000 | lbs. @ | $5.20 | ||
Direct labor | 5,700 | hrs. @ | $9.30 | 6,000 | hrs. @ | $9.50 |
Determine the following variances:
Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable.
Materials Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
a. Materials price | Answer | AnswerFU |
b. Materials efficiency | Answer | AnswerFU |
Labor Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
c. Labor rate | Answer | AnswerFU |
d. Labor efficieny | Answer | AnswerFU |
Material Variances
Actual Cost = Actual quantity × Actual Rate
= 4200lbs × $4.90
= $ 20,580
Standard Cost = Standard quantity × Standard Rate
= 4000lbs × $5.20
= $ 20,800
Split Cost = Standard Cost - Actual Cost
= $ 20,800 - $ 20,580
= $ 220 F
a. Material Price Variance =
= Actual Quantity × ( Standard Price - Actual Price)
= 4200 (5.20 - 4.90)
= 4200 × 0.3
= $ 1260 F
b. Material Efficiency Variance
= Standard Rate × ( Actual Quantity - Standard Quantity)
= 5.20 (4200-4000)
= 5.20 × 200
=$ 1040 F
Labour Variances
Actual Cost = Actual hours × Axtual Rate
= 5700hrs × $ 9.30
= $53,010
Standard Cost = Standard Hours × Standard Rate
= 6000hrs × $ 9.50
= $57,000
Split Cost = Standard Cost - Actual Cost
= 57,000 - 53,010
= $ 3990 F
c. Labour Rate Variance
= Actual hours worked × (Actual Rate - Standard Rate)
= 5700 ( 9.30 - 9.50 )
= 5700 × (-0.20)
= $ 1,140 U
d. Labour Efficiency Variance
= (Actual Hours × Standard Rate) - (Standard Hours × Standard
Rate)
= (5700×9.50) - (6000×9.50)
= 54,150 - 57,000
= $ 2,850 U