Question

In: Accounting

On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...

On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $53,600 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $26,800 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $26,800 to Green. Revis estimates an 80% chance that cost savings will reach the target and calculates the contract price based on the expected value of future payments to be received.

Required:
Prepare the following journal entries for Revis:

1. to 3. Prepare the journal entry on January 31 to record the collection of cash and recognition of the first month’s revenue. Also record the entry on June 30 for receipt of the bonus assuming total cost savings exceed target. And record the entry on June 30 for payment of the penalty assuming total cost savings fall short of target. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

  • Record the collection of cash and recognition of the first month's revenue.
Date General Journal Debit Credit
January 31
  • Record the receipt of the bonus assuming total cost savings exceed target.
Date General Journal Debit Credit
June 30   
  • Record the payment of penalty assuming that total cost savings fall short of target.
Date General Journal Debit Credit
June 30   

Solutions

Expert Solution


Related Solutions

On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $41,600 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $20,800 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $20,800 to Green. Revis estimates an 80% chance that cost savings will reach the...
1. On January 1, Revis Consulting entered into a contract to complete a cost reduction program...
1. On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $68,000 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $34,000 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $34,000 to Green. Revis estimates an 80% chance that cost savings will reach...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium for consideration of $ 200 million. The contract was expected to take 2 years to complete. At 31 December 2019 Areej had incurred costs of $ 55 million, Costs to complete are estimated at $ 50 million. In addition to these costs, Amir purchased plant to be used on the contract at a cost of $ 30 million. This plant was purchased on 1...
On 1 January 2017 Kuntan Ltd entered into an operating lease contract for premises in the...
On 1 January 2017 Kuntan Ltd entered into an operating lease contract for premises in the Windhoek Weinhill Mall. The lease is to run for a period of 4 years (contract expires on 31 December 2020). As a result of several factors , the board of directors decided on 31 December 2018 to move the entity to Merua Mall with effect from 2 January 2019. However the lease contract determines the following: Operating lease payments per year (no escalation) N$10...
1. On January 1, 2020, Ginseng Inc. entered into a forward contract to purchase U.S. $6,000...
1. On January 1, 2020, Ginseng Inc. entered into a forward contract to purchase U.S. $6,000 for $6,336 Canadian in 30 days. On January 15, the fair value of the contract was $40 (reflecting the present value of the future cash flows under the contract). Assume that the company would like to update its records on January 15. (a) Prepare only the necessary journal entries on January 1 and 15, 2020. 2. (Derivative Transaction) On April 1, 2020, Petey Ltd....
On January 1, 2018, Harlon Consulting entered into a three-year lease for new office space agreeing...
On January 1, 2018, Harlon Consulting entered into a three-year lease for new office space agreeing to lease payments of: $5,000 in 2018, $6,000 in 2019 and $7,000 in 2020. Payments are due on December 31 of each year with the first payment being made on December 31, 2018. Harlon is aware that the lessor used a 5% interest rate when calculating lease payments. Required: 1. Prepare the appropriate entries for Harlon Consulting on January 1, 2018 to record the...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Teal Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $597,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $908,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $286,560 $453,720 $609,000 Estimated costs to complete 310,440 143,280 –0– Progress billings to date 273,000 548,000 908,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking...
Sheffield Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $595,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $279,650 $487,900 $606,000 Estimated costs to complete 315,350 107,100 –0– Progress billings to date 272,000 545,000 903,000 Cash collected to date...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT