Question

In: Civil Engineering

Oliver Owner wishes to build an office building. Oliver hired Original Architect, Inc. to create the...

Oliver Owner wishes to build an office building. Oliver hired Original Architect, Inc. to create the design. Over several months, Original Architect, Inc. gave Oliver several drafts of increasing detail. Uninspired by what he saw, Oliver terminated its contract with Original Architect, Inc. and hired Replacement Architect, Inc. in its place. Oliver gave Replacement Architect, Inc. the last drawing Oliver had received from Original Architect, Inc. Replacement Architect, Inc. used this last drawing to create its own final design. Oliver then hired Prime Builder, Inc. to be the prime contractor on the job. The contract price was for a fixed amount, with work to be completed in one year. The project did not go smoothly. Oliver failed to obtain a zoning change on time, and work had to begin one month late. Meanwhile, Prime Builder, Inc. found the design literally impossible to implement; for example, all of the specified conduits would not fit into the space allotted, forcing Replacement Architect, Inc. to redesign. This took Replacement Architect, Inc. two weeks to do. Meanwhile, Replacement Architect, Inc. was unhappy with the quality of the contractor’s work. Within a week after the foundation was poured, it began to crack. Replacement Architect, Inc. determined the soil preparation work was not properly done. It ordered Prime Builder, Inc. to remove the foundation and redo the soil preparation, which the contractor did. The project was finished three months late. As a result, several commercial tenants who had promised to move into the new building found rentals elsewhere. Overwhelmed with all the problems on the construction project, Oliver did not even try to find replacement tenants until two months after the building was completed. Eventually, Oliver fully rented the building.


What will likely happen? What are the likely outcomes? Why? Calculate the damages.

Solutions

Expert Solution

1. Original Architect, Inc. sued Oliver Owner for (a) nonpayment of the design work the architect had done and (b) emotional distress for not being chosen as the project architect.

2. Oliver sued Replacement Architect, Inc. and Prime Builder, Inc. for late completion.

3. Prime Builder, Inc. sued both Oliver and Replacement Architect, Inc. for (a) higher performance costs than anticipated, (b) home office overhead expenses, and (c) lost profits on the new contracts Prime Builder, Inc. would have signed had it not been still working on Oliver's project after the original, one-year completion date.


Related Solutions

A building owner is evaluating the following alternatives for leasing space in an office building for...
A building owner is evaluating the following alternatives for leasing space in an office building for the next five years: Net lease with steps. Rent will be $15 per square foot the first year and will increase by $1.50 per square foot each year until the end of the lease. All operating expenses will be paid by the tenant. Net lease with CPI adjustments. The rent will be $16 per square foot the first year. After the first year, the...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Skysong estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Headland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022: At At At 12/31/2020 12/31/2021 12/31/2022 Contract...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp
Construction Contract Accounting as per Percentage-of-Completion Method & Completed Contract Method.  Problem Four: Long-Term Contract  On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp. for a total contract price of S2,000,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated...
You are the owner of a 50,000 square foot office building in a market that is...
You are the owner of a 50,000 square foot office building in a market that is currently 17% vacant. The overall market currently totals 2.6 million square feet, but a new building with 75,000 square feet is expected to come on line in one year, replacing two smaller buildings which had totaled 35,000 square feet. The market is relatively strong, with net annual absorption totaling 85,000 square feet per year. A large tenant has just moved out of your building...
You are the owner of a 65,000 square foot office building. You purchased the building five...
You are the owner of a 65,000 square foot office building. You purchased the building five years ago for $11,500,000. During that entire time the building was triple net leased to a tenant who was also responsible for all maitenance and capital upkeep. The net rent the tenant paid was flat at $12.50 per square foot per year. You have just negotiated a lease extension which will raise the rent to $14.00 per square foot for the next 10 years....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT