In: Accounting
On January 2, 2019, TI enters into a contract with Drewry Corp. to build a new piece of equipment. The contract price is $3,200,000, and construction is expected to take 18 months. Drewry is billed and pays $1,600,000 of the contract price on January 2, 2019, and will pay the balance at completion.
TI estimates that the cost of construction will be $2,300,000.
Drewry includes two performance bonuses in the contact:
| • | U.S. Bonus: If the equipment design receives a U.S. patent by March 15, 2020, Drewry will pay a $200,000 bonus. | 
| • | International Bonus: If the equipment receives approval for international distribution by January 31, 2020, Drewry will pay a $1,000,000 bonus. | 
The bonuses are payable when a U.S. patent is approved and when international distribution is approved.
On the date the contract is signed, TI estimates that there is an 80% chance it will receive U.S. patent protection by March 15, 2020, but only a 30% chance that the equipment will be approved for international distribution.
TI received a U.S. patent on the equipment design on November 15, 2019, and immediately billed Drewry and received its bonus payment. On December 31, 2019, TI has incurred $1,840,000 of contract costs and is 80% complete. TI won approval for international distribution on January 15, 2020, and completed the equipment project on April 15, 2020, at a cost of $2,300,000.
Required:
| 1. | Identify the performance obligations in the contract. | 
| 2. | Provide the journal entries that TI should make to recognize revenue from the contract. | 
| 2. Prepare the journal entries to record | |
| 1. | the initial contract billing and receipt on January 2, 2019 | 
| 2. | the patent billing and receipt on November 15 | 
| 3. | contract costs incurred for the year on December 31 | 
| 4. | profit recognized for the year on December 31 | 
| 5. | the partial contract billing and receipt on January 15, 2020 | 
| 6. | costs incurred for the year to date on April 15 | 
| 7. | profit recognized for the year to date on April 15 | 
| 8. | the final entry to close the construction accounts on April 15, 2020 | 
General Journal Instructions
All transactions on this page must be entered (except for post ref(s)) before you will receive Check My Work feedback.
PAGE 2019PAGE 2020
GENERAL JOURNAL
Score: 7/363
| DATE | ACCOUNT TITLE | POST. REF. | DEBIT | CREDIT | |
|---|---|---|---|---|---|
| 
 1  | 
|||||
| 
 2  | 
|||||
| 
 3  | 
|||||
| 
 4  | 
|||||
| 
 5  | 
|||||
| 
 6  | 
|||||
| 
 7  | 
|||||
| 
 8  | 
|||||
| 
 9  | 
|||||
| 
 10  | 
|||||
| 
 11  | 
|||||
| 
 12  | 
|||||
| 
 13  | 
Points:
1.33 / 69
Feedback