Question

In: Accounting

The Young Company enters into a long-term project to build a new office building. The Contract...

The Young Company enters into a long-term project to build a new office building. The Contract price is $9,000,000 and Young expects to complete the project in three years. Young gives you the following information for the first two years regarding the project:

2017

2018

Actual costs incurred during year

2,400,000

3,800,000

Estimated costs to complete at as of

December 31:

5,100,000

3,000,000

Amounts billed to customer

2,800,000

4,100,000

Collections from customer

2,600,000

3,400,000

Required:

1.    Prepare the journal entries to record the above information for both 2017 and 2018 under the percentage of-completion method.

2.    What items would be disclosed on the Company’s December 31, 2018 balance sheet?

12 1 Debit Credit
2017
2018
2
2018

Solutions

Expert Solution

2017 2018
Total Cost $7,500,000 $9,200,000
Cost incurred $2,400,000 $6,200,000
% complete 32% 67%
Total Estimated Revenue $9,000,000 $9,000,000
Total Revenue Recognised to date $2,880,000 $6,000,000
Revenue to be recognised in current year $2,880,000 $3,120,000
Income/(Loss) to date $480,000 ($200,000)
Income/(Loss) recognised current year $480,000 ($680,000)
2017 Account Heading Debit Credit
Construction in Progress $2,400,000
   Accounts Payable $2,400,000
Accounts receivable $2,800,000
Billings on construction contract $2,800,000
Cash $2,600,000
   Accounts receivable $2,600,000
Construction in Progress $480,000
Construction expense $2,400,000
   Construction revenue $2,880,000
2018
Construction in Progress $3,800,000
   Accounts Payable $3,800,000
Accounts receivable $4,100,000
Billings on construction contract $4,100,000
Cash $3,400,000
   Accounts receivable $3,400,000
Construction in Progress $680,000
Construction expense $3,800,000
   Construction revenue $3,120,000

Related Solutions

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? a. $0 b. $1,050,000 c....
Waterway Corp. enters into a contract with a customer to build an apartment building for $1,069,900....
Waterway Corp. enters into a contract with a customer to build an apartment building for $1,069,900. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $153,300 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $51,100 each week that completion is delayed. Waterway commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Cheyenne Corp. enters into a contract with a customer to build an apartment building for $995,600....
Cheyenne Corp. enters into a contract with a customer to build an apartment building for $995,600. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $145,500 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $48,500 each week that completion is delayed. Cheyenne commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Indigo Corp. enters into a contract with a customer to build an apartment building for $1,061,800....
Indigo Corp. enters into a contract with a customer to build an apartment building for $1,061,800. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $139,200 to be paid if the building is ready for rental beginning August 1, 2021. The bonus is reduced by $46,400 each week that completion is delayed. Indigo commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $40,000,000. The scheduled construction costs follow. Year Cost 2016 $9,000,000 2017 15,000,000 2018 6,000,000 Total $30,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue Answer Answer Answer Expense Answer Answer Answer Gross Profit Answer Answer Answer...
A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
Problem 5 Sage Corp. enters into a contract with a customer to build an apartment building...
Problem 5 Sage Corp. enters into a contract with a customer to build an apartment building for $1,069,900. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $153,300 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $51,100 each week that completion is delayed. Sage commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT