Question

In: Accounting

Question 11 In early February 2020, Indigo Corp. began construction of an addition to its head...

Question 11

In early February 2020, Indigo Corp. began construction of an addition to its head office building that is expected to take 18 months to complete. The following 2020 expenditures relate to the addition:

Feb. 1 Payment #1 to contractor $105,000
Mar. 1 Payment to architect 24,000
July 1 Payment #2 to contractor 63,000
Dec. 1 Payment #3 to contractor 186,000
Dec. 31 Asset carrying amount $378,000


On February 1, Indigo issued a $105,000, three-year note payable at a rate of 10% to finance most of the initial payment to the contractor. No other asset-specific debt was entered into. Details of other interest-bearing debt during the period are provided in the table below:

Other Debt Instruments Outstanding—2020 Principal amount
8%, 15-year bonds, issued May 1, 2005, matured May 1, 2020 $303,000
7%, 10-year bonds, issued June 15, 2014 $496,000
6%, 12-year bonds, issued May 1, 2020 $303,000


What amount of interest should be capitalized for the fiscal year ending December 31, 2020, according to IAS 23? (Do not round intermediate calculations. Round capitalization rate to 2 decimal places, e.g. 52.75% and final answer to 0 decimal places, e.g. 5,275.)

Amount of interest $

Solutions

Expert Solution

# Calculation of Weighted average Borrowing Cost

Debt Principal amount interest date of issue period outatnading for dec 31 2020 Weighted average principal amunt
8% debt $303000

=$303000*8%*4/12

=$8080

may 1 2002

mature on may 1, 2020

4 months

(january 2020 to december 2020)

=$303000*4/12

=$101000

7% bond $496000

=$496000*7%

=$34720

June 15, 2014 12months

=$496000*12/12

=$496000

6% Debt $303000

=$303000*6%*8/12

=$12120

may 1,2020 8 months

=$303000*8/12

=$202000

TOTAL $54920 $799000

Annualised weighted avereage generic borrowing rate =

=Total interest / Weighted avg.principal amount *100

=$54920/$799000 =6.87%

# Borrowing Cost Calculation-

Date Cost ($) Months upto 31 dec 2020 Specific borrowing used specific interest cost(A) generic borrowing used Generic borrowing cost(B) Total Borrowing cost(A+B)
Feb 1 $105000 11 months $105000

=$105000*10%*11/12

=$9625

------ ----- $9625
March 1 $24000 10 months ----- ----- $24000

=$24000*6.87%*10/12

=$1374

$1374
July 1 $63000 6 months ---- ------ $63000

=$63000*6.87%*6/12

=$2164

$2164
Dec 1 $186000 1 month ---- ------ $186000

=$186000*6.87%*1/12

=$1065

$1065
Total Borrowing Cost $14228

Hence $14228 of interest amount should be capitalised


Related Solutions

Based on Problem 10-6 Indigo Landscaping began construction of a new plant on December 1, 2020....
Based on Problem 10-6 Indigo Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $147,600 in cash. In addition, it paid $3,120 in surveying costs and $4,080 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was...
(Analysis of Percentage-of-Completion Financial Statements) In 2020, Steinrotter Construction Corp. began construction work under a 3-year...
(Analysis of Percentage-of-Completion Financial Statements) In 2020, Steinrotter Construction Corp. began construction work under a 3-year contract. The contract price was $1,000,000. Steinrotter uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2020, are shown below. Balance Sheet Accounts receivable $18,000 Construction in process $65,000 Less: Billings...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its office headquarters. The building is expected to be completed on December 31, 2020. Expenditures on this project during 2020 were as follows:                 January 1st          $ 160,000 March 1st               420,000 June 1st                  270,000 October 31st           165,000 On Jan. 1, 2020, the company obtained a $600,000 specific construction loan with a 7% interest rate. The loan was outstanding during the entire construction period. The company’s...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Cullumber Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.4 million and was expected to be completed in July 2024 at a total estimated cost of $82.1 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.8 million and was expected to be completed in July 2024 at a total estimated cost of $83.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred...
Tamarisk Construction Company began work on a $406,500 construction contract in 2020. During 2020, Tamarisk incurred costs of $292,500, billed its customer for $213,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $161,340. Prepare Tamarisk’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred...
Cullumber Construction Company began work on a $400,000 construction contract in 2020. During 2020, Cullumber incurred costs of $250,000, billed its customer for $200,000, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $178,890. Prepare Cullumber’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The...
n February 2020, Oriole Construction signed a contract and commenced construction on a parking garage. The total contract price was $91.0 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT