Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:

Immediate Time (weeks)
Activity Description Predecessor(s) Optimistic Most Probable Pesssimistic
A Plan topic 2 2 2
B Obtain speakers A 1.5 2 2.5
C List meeting locations 1 2.5 10
D Select location C 1 1.5 2
E Finalize speaker travel plans B, D 0.5 1 1.5
F Make final check with speakers E 1.5 2 2.5
G Prepare and mail brochure B, D 4 4.5 8
H Take reservations G 2 4 6
I Handle last-minute details F, H 2 3 4
  1. Which project network is correct?
    (i) (ii)
    (iii) (iv)

    Network (iii)  
  2. Prepare an activity schedule.

    If required, round your answers to two decimal places. If your answer is zero, enter “0”.
    Activity Expected Time Variance
    A fill in the blank 2 fill in the blank 3
    B fill in the blank 4 fill in the blank 5
    C fill in the blank 6 fill in the blank 7
    D fill in the blank 8 fill in the blank 9
    E fill in the blank 10 fill in the blank 11
    F fill in the blank 12 fill in the blank 13
    G fill in the blank 14 fill in the blank 15
    H fill in the blank 16 fill in the blank 17
    I fill in the blank 18 fill in the blank 19
    Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity
    A fill in the blank 20 fill in the blank 21 fill in the blank 22 fill in the blank 23 fill in the blank 24 No
    B fill in the blank 26 fill in the blank 27 fill in the blank 28 fill in the blank 29 fill in the blank 30 No
    C fill in the blank 32 fill in the blank 33 fill in the blank 34 fill in the blank 35 fill in the blank 36
    D fill in the blank 38 fill in the blank 39 fill in the blank 40 fill in the blank 41 fill in the blank 42
    E fill in the blank 44 fill in the blank 45 fill in the blank 46 fill in the blank 47 fill in the blank 48
    F fill in the blank 50 fill in the blank 51 fill in the blank 52 fill in the blank 53 fill in the blank 54
    G fill in the blank 56 fill in the blank 57 fill in the blank 58 fill in the blank 59 fill in the blank 60 Yes
    H fill in the blank 62 fill in the blank 63 fill in the blank 64 fill in the blank 65 fill in the blank 66 Yes
    I fill in the blank 68 fill in the blank 69 fill in the blank 70 fill in the blank 71 fill in the blank 72 Yes
  3. What are the critical activities and what is the expected project completion time?

    A-B-G-H-I  

    If required, round your answer to one decimal place.

    Expected project completion time = fill in the blank 75 weeks.
  4. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project? Base your calculation solely on the critical path. Note: Use Appendix B to identify the standard score.

    If required, round your answer to one decimal place.

    T = fill in the blank 76 weeks.

Solutions

Expert Solution

Solution:-


Related Solutions

Budgeting is a tool used by management for performing the functions of planning, coordinating, and controlling...
Budgeting is a tool used by management for performing the functions of planning, coordinating, and controlling operations of a business. Our textbook, Managing Accounting Concepts, describes 2 main types of budgeting: static budgets and flexible budgets. Respond to the following in a minimum of 175 words: Differentiate between the 2 types of budgets. Provide an example of the type of business or company that would benefit from using a flexible budget. Provide support for your business selection and include the...
Budgeting is a tool used by management for performing the functions of planning, coordinating, and controlling...
Budgeting is a tool used by management for performing the functions of planning, coordinating, and controlling operations of a business. Our textbook, Managing Accounting Concepts, describes 2 main types of budgeting: static budgets and flexible budgets. Respond to the following in a minimum of 175 words: Differentiate between the 2 types of budgets. Provide an example of the type of business or company that would benefit from using a flexible budget. Provide support for your business selection and include the...
differences between planning and coordinating has applied in food and beverage operations management
differences between planning and coordinating has applied in food and beverage operations management
Green, Inc. is planning to invest $500,000 (before tax) in a personnel training program. The $500,000...
Green, Inc. is planning to invest $500,000 (before tax) in a personnel training program. The $500,000 outlay will be charged off as an expense by the firm this year (year 0). the returns from the program, in the form of greater productivity and a reduction in employee turnover, are estimated as follows (on an after-tax basis): Years 1-10: $30,000 per year Years 11-20: $60,000 per year Potato Inc. has estimated its cost of capital to be 10 percent. Assume that...
Koshy Company is planning a cash budget for the next three months. Estimated sales revenue is:...
Koshy Company is planning a cash budget for the next three months. Estimated sales revenue is: Month Revenue Month Revenue January $175,000 March $125,000 February 150,000 April 100,000 Month Sales Revenue Month Sales Revenue All sales are on credit; 60 percent is collected during the month of sale, and 40 percent is collected during the next month. Cost of goods sold is 80 percent of sales. Payments for merchandise sold are made in the month following the month of sale....
Upon reviewing the following video, “The Corporate Management Training Program at The Kraft Heinz Company”,share an...
Upon reviewing the following video, “The Corporate Management Training Program at The Kraft Heinz Company”,share an example of an effective or ineffective training program or experience. In your opinion what factors made the training program effective or ineffective? State your reasons why you responded as you did.
Consider this scenario, a company management is considering developing its next work planning using the triple...
Consider this scenario, a company management is considering developing its next work planning using the triple bottom line principles as its framework. 1/. Describe what triple bottom principles is? 2/. Describe/Explain in step by step process as how management can develop its next work planning framework using Triple Based Line Principles? (Within Australian Accounting Environment) (Please type up your answer)
Upon graduating from college in 2017, Karen Peterson entered the financial management-training program of a large...
Upon graduating from college in 2017, Karen Peterson entered the financial management-training program of a large financial consulting firm. The training program consisted of a one-year assignment in three different departments. In the Investment and Financial Analysis department, Peterson was asked to answer the questions related to the Company. Using the financial statement and data below answer the following questions: Financial Statement Data and Stock Price Data for Jays (All data as of fiscal year end; $ in millions) Income...
Garden Sales, Inc., sells garden supplies. Management is planning its cash needs for the second quarter.
Garden Sales, Inc., sells garden supplies. Management is planning its cash needs for the second quarter. The company usually has to borrow money during this quarter to support peak sales of lawn care equip­ment, which occur during May. The following information has been assembled to assist in preparing a cash budget for the quarter: a. Budgeted monthly absorption costing income statements for April-July are:   April May June July Sales ... $600,000 $900,000 $500,000 $400,000 Cost of goods sold ... 420,000...
Garden Sales, Inc., sells garden supplies. Management is planning its cash needs for the second quarter....
Garden Sales, Inc., sells garden supplies. Management is planning its cash needs for the second quarter. The company usually has to borrow money during this quarter to support peak sales of lawn care equipment, which occur during May. The following information has been assembled to assist in preparing a cash budget for the quarter: Budgeted monthly absorption costing income statements for April–July are: April May June July Sales $ 730,000 $ 1,190,000 $ 650,000 $ 560,000 Cost of goods sold...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT