Problem 9-15 (Algorithmic)
Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:
Immediate | Time (weeks) | ||||
Activity | Description | Predecessor(s) | Optimistic | Most Probable | Pesssimistic |
A | Plan topic | — | 2 | 2 | 2 |
B | Obtain speakers | A | 1.5 | 2 | 2.5 |
C | List meeting locations | — | 2 | 2.5 | 9 |
D | Select location | C | 1.5 | 1.5 | 1.5 |
E | Finalize speaker travel plans | B, D | 2 | 4 | 6 |
F | Make final check with speakers | E | 4 | 4.5 | 8 |
G | Prepare and mail brochure | B, D | 1.5 | 2 | 2.5 |
H | Take reservations | G | 0.5 | 1 | 1.5 |
I | Handle last-minute details | F, H | 3 | 3.5 | 4 |
(i) | (ii) | ||
(iii) | (iv) |
Activity | Expected Time | Variance | ||
A | ||||
B | ||||
C | ||||
D | ||||
E | ||||
F | ||||
G | ||||
H | ||||
I |
Earliest | Latest | Earliest | Latest | Critical | ||||||||
Activity | Start | Start | Finish | Finish | Slack | Activity | ||||||
A | ||||||||||||
B | ||||||||||||
C | ||||||||||||
D | ||||||||||||
E | ||||||||||||
F | ||||||||||||
G | ||||||||||||
H | ||||||||||||
I |
(Please like the answer it will encourage me. Do comment if any correction required before disliking.)