Question

In: Accounting

1. Beavis Construction Company was the low bidder on a construction project to build an earthen...

1. Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:

                                                                          2017                           2018

Costs incurred during the year                    $ 450,000                  $1,100,000

Estimated costs to complete                       1,050,000                                  0

Billings during the year                                 400,000                    1,400,000

Cash collections during the year                    300,000                    1,500,000

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Required:

Prepare all journal entries to record costs, billings, collections, and profit recognition for 2017 and 2018.

2. Answer each of the following unrelated questions.

1) Bill wants to give Maria a $500,000 gift in seven years. If money is worth 6% compounded semiannually, what is Maria's gift worth today?

2) At the end of each quarter, Patti deposits $500 into an account that pays 12% interest compounded quarterly. How much will Patti have in the account in three years?

*In the following questions, the interest is compounded annually.

3) Spielberg Inc. signed a $200,000 noninterest-bearing note due in five years from a production company eager to do business. Comparable borrowings have carried an 11% interest rate. What is the value of this debt at its inception?

4) Mustard's Inc. sold the rights to use one of its patented processes that will result in cash receipts of $2,500 at the end of each of the next four years and a lump sum receipt of $4,000 at the end of the fifth year. The total present value of these payments if interest is at 9% is:

5) Claudine Corporation will deposit $5,000 into a money market sinking fund at the end of each year for the next five years. How much will accumulate by the end of the fifth and final payment if the sinking fund earns 9% interest?

6) Fenland Co. plans to retire $100 million in bonds in five years, so it wishes to fund a savings account at the beginning of each year during that period for which it expects to earn 8% annually. At the end of the five years, there will be enough money in the account to pay off the bonds. What amount does Fenland need to invest each year?

7) Polo Publishers purchased a multi-color offset press with terms of $50,000 to be paid at the date of purchase, and a noninterest-bearing note requiring payment of $20,000 at the end of each year for five years. The interest rate implicit in the purchase contract is 11%. Polo would record the asset at:

Solutions

Expert Solution


Related Solutions

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 420,000 $ 1,200,000 Estimated costs to complete 980,000 0 Billings during the year 450,000 1,450,000 Cash collections during the year 350,000 1,550,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016   Costs incurred during the year $ 399,000 $1,060,000      Estimated costs to complete 931,000 0      Billings during the year 485,000 1,330,000      Cash collections during the year 385,000 1,430,000    Required information Assume that Beavis recognizes revenue on this contract over time...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:                                                                                     2012                           2013 Costs incurred during the year                               $450,000                $ 1.100,000 Estimated costs to complete 1,050,000                      0 Billings during the year                                            400,000                    1,400,000 Cash collections during the year                             300,000                     1,500,000 Assume that Beavis uses the percentage- of- completion method for...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,720,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $ 411,000 $1,020,000 Estimated costs to complete 959,000 0 Billings during the year 465,000 1,310,000 Cash collections during the year 365,000 1,410,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required:...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT