Question

In: Accounting

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:

2020 2021
Costs incurred during the year $ 476,000 $ 1,030,000
Estimated costs to complete 884,000 0
Billings during the year 470,000 1,260,000
Cash collections during the year 370,000 1,360,000


Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Required:
Compute the amount of gross profit recognized during 2020 and 2021.

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:

2020 2021
Costs incurred during the year $ 476,000 $ 1,030,000
Estimated costs to complete 884,000 0
Billings during the year 470,000 1,260,000
Cash collections during the year 370,000 1,360,000


Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Required:
Compute the amount of gross profit recognized during 2020 and 2021.

Solutions

Expert Solution

2020

2021

Total

Cost incurred during the year

$476,000

$1,030,000

$1,506,000

Costs incurred till date

$476,000

$1,506,000

Estimated costs to complete

$884,000

$1,506,000

Billings during the year

$470,000

$1,260,000

Cash collections during the year

$370,000

$1,360,000

Percentage complete

54%

100%

Revenue during the year based on % of completion

$931,538

$798,462

Expenses incurred

$476,000

$1,030,000

Gross profit recognized

$455,538

-$231,538

$224,000

From the case in question, the total revenue on the project is $1,730,000

From the table above we see costs $476,000 and $1,030,000 incurred during 2020 and 2021 respectively, so total cost of project = $476,000+$1,030,000 = $1,506,000.

Costs incurred till date tells us total project cost till date,so for 2021, it is cumulative of cost incurred in 2020 and 2021. This is required to calculate % of project completed.

Estimated total costs to complete the project are given as $884,000 in 2020, however, costs overran in 2021 to total cost of $1,506,000 for the project.

Billings during the year and cash collections are bills generated and cash collected out of total project price.

No, percentage of project complete = Cost incurred till date/Estimated costs to complete

So, for 2020, % complete = $476,000/$884,000 = 54%

However, in 2021,costs incurred till date became $1,506,000 and since it was project completion year, so estimated total costs to complete also changes to $1,506,000

% of project complete = $1,506,000 / %1,506,000 = 100%

Revenue recognized for 2020 = % of project complete*Total project price

=54%*$1,730,000 = $931,538

Further, expenses incurred in 2020 = $476,000

So, gross profit recognized in 2020 = $931,538 - $476,000 = $455,538

Revenue recognition for 2021 = (%of project complete*Total Project Price) – Revenue previously recognized

So, revenue for 2021 = $1,730,000*54% - $931,538

=$798,462

Expenses incurred in 2021 = $1,030,000

So, loss recognized during 2021 = $798,462 - $1,030,000 = $231,538


Related Solutions

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 420,000 $ 1,200,000 Estimated costs to complete 980,000 0 Billings during the year 450,000 1,450,000 Cash collections during the year 350,000 1,550,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016   Costs incurred during the year $ 399,000 $1,060,000      Estimated costs to complete 931,000 0      Billings during the year 485,000 1,330,000      Cash collections during the year 385,000 1,430,000    Required information Assume that Beavis recognizes revenue on this contract over time...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:                                                                                     2012                           2013 Costs incurred during the year                               $450,000                $ 1.100,000 Estimated costs to complete 1,050,000                      0 Billings during the year                                            400,000                    1,400,000 Cash collections during the year                             300,000                     1,500,000 Assume that Beavis uses the percentage- of- completion method for...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,720,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $ 411,000 $1,020,000 Estimated costs to complete 959,000 0 Billings during the year 465,000 1,310,000 Cash collections during the year 365,000 1,410,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required:...
1. Beavis Construction Company was the low bidder on a construction project to build an earthen...
1. Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                           2017                           2018 Costs incurred during the year                    $ 450,000                  $1,100,000 Estimated costs to complete                       1,050,000                                  0 Billings during the year                                 400,000                    1,400,000 Cash collections during the year                    300,000                    1,500,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT