In: Accounting
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam for $1,730,000. The project was
begun in 2020 and completed in 2021. Cost and other data are
presented below:
2020 | 2021 | |||||
Costs incurred during the year | $ | 476,000 | $ | 1,030,000 | ||
Estimated costs to complete | 884,000 | 0 | ||||
Billings during the year | 470,000 | 1,260,000 | ||||
Cash collections during the year | 370,000 | 1,360,000 | ||||
Assume that Beavis recognizes revenue on this contract over time
according to percentage of completion.
Required:
Compute the amount of gross profit recognized during 2020 and
2021.
Beavis Construction Company was the low bidder on a construction
project to build an earthen dam for $1,730,000. The project was
begun in 2020 and completed in 2021. Cost and other data are
presented below:
2020 | 2021 | |||||
Costs incurred during the year | $ | 476,000 | $ | 1,030,000 | ||
Estimated costs to complete | 884,000 | 0 | ||||
Billings during the year | 470,000 | 1,260,000 | ||||
Cash collections during the year | 370,000 | 1,360,000 | ||||
Assume that Beavis recognizes revenue on this contract over time
according to percentage of completion.
Required:
Compute the amount of gross profit recognized during 2020 and
2021.
2020 |
2021 |
Total |
|
Cost incurred during the year |
$476,000 |
$1,030,000 |
$1,506,000 |
Costs incurred till date |
$476,000 |
$1,506,000 |
|
Estimated costs to complete |
$884,000 |
$1,506,000 |
|
Billings during the year |
$470,000 |
$1,260,000 |
|
Cash collections during the year |
$370,000 |
$1,360,000 |
|
Percentage complete |
54% |
100% |
|
Revenue during the year based on % of completion |
$931,538 |
$798,462 |
|
Expenses incurred |
$476,000 |
$1,030,000 |
|
Gross profit recognized |
$455,538 |
-$231,538 |
$224,000 |
From the case in question, the total revenue on the project is $1,730,000
From the table above we see costs $476,000 and $1,030,000 incurred during 2020 and 2021 respectively, so total cost of project = $476,000+$1,030,000 = $1,506,000.
Costs incurred till date tells us total project cost till date,so for 2021, it is cumulative of cost incurred in 2020 and 2021. This is required to calculate % of project completed.
Estimated total costs to complete the project are given as $884,000 in 2020, however, costs overran in 2021 to total cost of $1,506,000 for the project.
Billings during the year and cash collections are bills generated and cash collected out of total project price.
No, percentage of project complete = Cost incurred till date/Estimated costs to complete
So, for 2020, % complete = $476,000/$884,000 = 54%
However, in 2021,costs incurred till date became $1,506,000 and since it was project completion year, so estimated total costs to complete also changes to $1,506,000
% of project complete = $1,506,000 / %1,506,000 = 100%
Revenue recognized for 2020 = % of project complete*Total project price
=54%*$1,730,000 = $931,538
Further, expenses incurred in 2020 = $476,000
So, gross profit recognized in 2020 = $931,538 - $476,000 = $455,538
Revenue recognition for 2021 = (%of project complete*Total Project Price) – Revenue previously recognized
So, revenue for 2021 = $1,730,000*54% - $931,538
=$798,462
Expenses incurred in 2021 = $1,030,000
So, loss recognized during 2021 = $798,462 - $1,030,000 = $231,538