In: Accounting
Questions:
1. In a company that uses job order costing, the entry to transfer the costs from WIP to Finished Goods would include a debit to Finished Goods equal to the
A. total cost of all units worked on during the period.
B. total cost of all units in batches completed and sold during the period.
C. total cost of all units in batches completed during the period.
D. current period costs related to units in batches completed during the period.
2. An engineering company that uses job order (project) costing should not include which of the following in determining the total estimated overhead?
A. Receptionist salary
B. Engineer salaries
C. Office rent
D. Depreciation of office equipment
3. Marley Mar Company uses job order costing. Their predetermined MOH rate is $15 per direct labor hour.
They started Job 875 in September. As of September 30, the total cost in WIP for Job 875 was $3,650.
They finished the job in October (50 units produced.) Direct materials added to the job in October cost $1,895. Direct labor cost in October was $400 (40 hours). What was the cost per unit for Job 875?
4. Under the FIFO method of process costing , the calculation of cost per equivalent unit of production considers:
A. current period costs only
B. current period costs plus the cost of beginning work in process inventory
C. current period costs plus the cost of ending work in process inventory
D. current period costs less the cost of beginning work in process inventory
5. In a company using process costing (FIFO), there were 600 units in beginning inventory (60% complete with respect to materials costs). What's the units that should be included in the calculation of equivalent units of production for materials?(No decimals.)
6. There were two departments in a company using process costing (FIFO) - Assembly and Finishing. In the Finishing department, there were 5,000 units in ending inventory. The units were 80% complete with respect to Finishing material costs and 75% complete with respect to Finishing Conversion costs. What's the units that should be included in the calculation of equivalent units of production in the Finishing Department for Transferred in (Assembly) costs? (Use commas. No decimals.)
1. ENTRY FOR TRANSFERING COST FROM WIP TO FINISHED GOODS UNDER JOB ORDER COSTING WOULD BE:
C. TOTAL COST OF ALL UNITS IN BATCHES COMPLETED DURING THE PERIOD.
2.FOLLOWING COST WOULD NOT BE CONSIDERED BY AN ENGINEERING CO. THAT USES JOB ORDER COSTING:
D. DEPRECIATION OF OFFICE EQUIPMENT.
3. TOTAL COST WOULD BE:
WIP OF SEPTEMBER- 3650
ADD: RAW MATERIAL ADDED IN OCT 1895
ADD: DIRECT LABOUR HOUR IN OCT 400
ADD: OVERHEAD (15*40) 600
TOTAL COST FOR JOB-875 6545
4. UNDER FIFO METHOD OF PROCESS COSTING, THE EQUIVALENT COST OF PRODUCTION WILL COVER:
A. CURRENT PERIOD COST.
5. OPENING 600 UNITS COMPLETED 60 %, SO 40% WOULD BE COMPLETED THIS MONTH. HENCE EQUIVALENT UNITS WILL BE 600*40% i.e. 240 UNITS
6. EQUIVALENT UNITS TRANSFERRED TO ASSEMBLE DEPT
IN RESPECT OF MATERIAL IN RESPECT OF CONVERSION COST
CLOSING WIP 5000 UNITS 5000 UNITS
% COMPLETION 80% 75%
EQUIVALENT UINTS 4000 UNITS(5000*80%) 3750 UNITS(5000*75%)