Question

In: Accounting

Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory Salazar Company is a job-order costing firm that uses...

Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory Salazar Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Salazar identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Setting up design $168,000 Setups 1,200 Purchasing 186,000 Number of parts 15,000 Other overhead 415,000 Direct labor hours 50,000 Salazar worked on five jobs in March. Data are as follows: Job 15 Job 16 Job 17 Job 18 Job 19 Balance, March 1 $34,600 $39,890 $24,090 $0 $0 Direct materials $28,000 $37,900 $25,350 $11,000 $13,550 Direct labor $10,000 $8,500 $23,000 $12,700 $8,000 Setups 20 14 35 8 15 Number of parts 150 180 200 500 300 Direct labor hours 650 580 1,600 870 520 By March 31, Jobs 15, 16, and 17 were completed and sold. The remaining jobs were in process. Required: 1. Calculate the activity rates for each of the three overhead activities. If required, round your answers to the nearest cent. Setup rate $ 140 per set up Purchasing rate $ 12.4 per part Other overhead rate $ 8.3 per direct labor hour Feedback 1. Remember OH rate = estimated annual OH ÷ by the related driver. 2. Prepare job-order cost sheets for each job showing all costs through March 31. What is the cost of each job by the end of March?. If an amount is zero, enter "0". Salazar Company Job-Order Cost Sheets Job 15 Job 16 Job 17 Job 18 Job 19 Balance, March 1 $ 34,600 $ 39,890 $ 24,090 $ 0 $ 0 Direct materials 28,000 37,900 25,350 11,000 13,550 Direct labor 10,000 8,500 23,000 12,700 8,000 Applied overhead: Setups Purchasing Other overhead Total cost $ $ $ $ $ Feedback 2. The job-order cost sheet must include a unique number or name for this particular job, all direct costs, and all overhead costs associated with the job. 3. Calculate the balance in Work in Process on March 31. $ 4. Calculate the cost of goods sold for March. $

Solutions

Expert Solution

ANSWER

1)

Activity rates should be calculated as follows:

Above figures have been calculated in the following manner:

2)

Above figures have been calculated in the following manner:

Above figures are calculated in the following manner:

3.

Jobs 15, 16, and 17 have been completed and sold in March. Therefore, work in process on March 31 will contain only Jobs 18 and 19.

Work in process on March 31 = Job 18 + Job 19 = $38,241 + $31,686= $69,927

4.

Cost of goods sold for March = Job 15 + Job 16 + Job 17 = $82,655 + $95,296 + $93,100 = $271,051

===========================================

DEAR STUDENT,

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating

*****************THANK YOU**************


Related Solutions

Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory, Journal Entries Feldspar Company uses an ABC system to...
Activity-Based Costing, Unit Cost, Ending Work-in-Process Inventory, Journal Entries Feldspar Company uses an ABC system to apply overhead. There are three activity rates: Setting up $20 per setup Machining $5.20 per machine hour Other overhead 80% of direct labor cost During September, Feldspar worked on three jobs. Data relating to these jobs follow: Job 13-280 Job 13-281 Job 13-282 Units in each order 200 510 100 Units sold 200 — 100 Materials requisitioned $4,750 $3,800 $5,600 Direct labor cost $2,000...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $108,000 Number of moves 4,500 Engineering 165,000 Number of change orders 10,000 Other overhead 263,200 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs....
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $81,900 Number of moves 3,500 Engineering 135,150 Number of change orders 8,500 Other overhead 240,000 Direct labor hours 48,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs....
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost    Driver Amount of Driver Materials handling $ 72,000      Number of moves 3,000   Engineering 165,000      Number of change orders 10,000   Other overhead 280,000      Direct labor hours 50,000   Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year. ? Activity Cost Driver Amount of driver setups $240,000 number of setups 6,000 purchasing 160,000 number of parts 20,000 other overhead 300,000 direct labor hours 80,000 ? The following information about the jobs was given for April. ? ? Job 101 Job 102 Job 103 Job 104 Balance 4/1 $64,900 $40,770 $30,500 0 direct...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year. Activity Cost Driver Amount of driver Setups $240,000 Number of setups 6,000 Purchasing 160,000 Number of parts 20,000 Other overhead 300,000 Direct labor hours 80,000 The following information about the jobs was given for April. Job 101 Job 102 Job 103 Job 104 Balance 4/1 $64,900 $40,770 $30,500 0 Direct materials 54,000 37,900 25,000...
Explain overhead for the different methods, for process costing, activity-based costing, job order costing.
Explain overhead for the different methods, for process costing, activity-based costing, job order costing.
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,370 $6,280 $0 Direct materials $10,510 $12,350 $16,190 Direct labor $16,040 $12,240 $24,030 Machine hours 500 290 980 Overhead is applied to jobs at the rate of $17 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT