Question

In: Economics

Options are under consideration to meet a 12-period need are shown below. Options have different lives...

Options are under consideration to meet a 12-period need are shown below. Options have different lives so an adjustment for equivalence is required to perform a valid analysis using engineering economic methods. The interest rate for use is 8.0%.

Options A B C D
Purchase Cost 65,000 41,000 29,000 19,000
First Year Operating Cost 4,800 6,400 7,500 8,100
Operating Cost Increase Per Period 500 700 900 1,400
Life/Salvage 6/4,000 4/2,000 3/1,500 2/800

a. What is the PW of Option A?    

b. What is the PW of Option B?

c. What is the PW of Option C?

d.What is the PW of Option D?

Solutions

Expert Solution

ANSWER:

A) PW of option a:

i = 8% and n = 12 years

pw = purchase cost + first year operating cost(p/a,i,n) + operating cost per period(p/g,i,n) + salvage value(p/f,i,n) + purchase cost in year 6(p/f,i,n) + salvage value in year 12(p/f,i,n)

pw = -65,000 - 4,800(p/a,8%,12) - 500(p/g,8%,12) + 4,000(p/f,8%,6) - 65,000(p/f,8%,6) + 4,000(p/f,8%,12)

pw = -65,000 - 4,800 * 7.536 - 500 * 34.634 + 4,000 * 0.6302 - 65,000 * 0.6302 + 4,000 * 0.3971

pw = -65,000 - 36,172.8 - 17,317 + 2,520.8 - 40,963 + 1,588.4

pw = -157,864

B) Pw of option b:

i = 8% and n = 4 years

pw = purchase cost + first year operating cost(p/a,i,n) + operating cost per period(p/g,i,n) + salvage value(p/f,i,n) + purchase cost in year 4(p/f,i,n) + salvage value in year 8(p/f,i,n) + purchase cost in year 8(p/f,i,n) + salvage value in year 12(p/f,i,n)

pw = -41,000 - 6,400(p/a,8%,12) - 700(p/g,8%,12) + 2,000(p/f,8%,4) - 41,000(p/f,8%,4) + 2,000(p/f,8%,8) - 41,000(p/f,8%,8) + 2,000(p/f,8%,12)

pw = -41,000 - 6,400 * 7.536 - 700 * 34.634 + 2,000 * 0.735 - 41,000 * 0.735 + 2,000 * 0.5403 - 41,000 * 0.5403 + 2,000 * 0.3971

pw = -41,000 - 48,230.4 - 24,243.8 + 1,470 - 30,135 + 1,080.6 - 22,152.3 + 794.2

pw = -163,887

C) Pw of option c:

i = 8% and n = 3 years

pw = purchase cost + first year operating cost(p/a,i,n) + operating cost per period(p/g,i,n) + salvage value(p/f,i,n) + purchase cost in year 3(p/f,i,n) + salvage value in year 6(p/f,i,n) + purchase cost in year 6(p/f,i,n) + salvage value in year 9(p/f,i,n) + purchase cost in year 9(p/f,i,n) + salvage value in year 12(p/f,i,n)

pw = -29,000 - 7,500(p/a,8%,12) - 900(p/g,8%,12) + 1,500(p/f,8%,3) - 29,000(p/f,8%,3) + 1,500(p/f,8%,6) - 29,000(p/f,8%,6) + 1,500(p/f,8%,9) - 29,000(p/f,8%,9) + 1,500(p/f,8%,12)

pw = -29,000 - 7,500 * 7.536 - 900 * 34.634 + 1,500 * 0.7938 - 29,000 * 0.7938 + 1,500 * 0.6302 - 29,000 * .6302 + 1,500 * 0.5002 - 29,000 * 0.5002 + 1,500 * 0.3971

pw = -29,000 - 56,520 - 31,170.6 + 1,190.7 - 23,020.2 + 945.3 - 18,275.8 + 750.3 - 14,505.8 + 595.65

pw = -170,201

D) Pw of option d:

i = 8% and n = 2 years

pw = purchase cost + first year operating cost(p/a,i,n) + operating cost per period(p/g,i,n) + salvage value(p/f,i,n) + purchase cost in year 2(p/f,i,n) + salvage value in year 4(p/f,i,n) + purchase cost in year 4(p/f,i,n) + salvage value in year 6(p/f,i,n) + purchase cost in year 6(p/f,i,n) + salvage value in year 8(p/f,i,n) + purchase cost in year 8(p/f,i,n) + salvage value in year 10(p/f,i,n) + purchase cost in year 10(p/f,i,n) + salvage value in year 12(p/f,i,n)

pw = -19,000 - 8,100(p/a,8%,12) - 1,400(p/g,8%,12) + 800(p/f,8%,2) - 19,000(p/f,8%,2) + 800(p/f,8%,4) - 19,000(p/f,8%,4) + 800(p/f,8%,6) - 19,000(p/f,8%,6) + 800(p/f,8%,8) - 19,000(p/f,8%,8) + 800(p/f,8%,10) - 19,000(p/f,8%,10) + 800(p/f,8%,12)

pw = -19,000 - 8,100 * 7.536 - 1,400 * 34.634 + 800 * 0.8573 -19,000 * 0.8573 + 800 * 0.735 - 19,000 * 0.735 + 800 * 0.6302 - 19,000 * 0.6302 + 800 * 0.5403 - 19,000 * 0.5403 + 800 * 0.4632 - 19,000 * 0.4632 + 800 * 0.3971

pw = -19,000 - 61,041.6 - 48,487.6 + 685.84 - 16,288.7 + 588 - 13,965 + 504.16 - 11,973.8 + 432.24 - 10,265.7 + 370.56 - 8,880.8 + 317.68

pw = - 187,611


Related Solutions

Options are under consideration to meet a 12 period need are shown below. Options have different...
Options are under consideration to meet a 12 period need are shown below. Options have different lives so an adjustment for equivalence is required to perform a valid analysis using engineering economic methods. The interest rate for use is 8.0%. Option A B C D Purchase Cost 65,000 41,000 29,000 19,000 First Year Operating Cost 4,800 6,400 7,500 8,100 Operating Cost Increase per Period 500 700 900 1,400 Life/Salvage 6/4,000 4/2,000 3/1,500 2/800 a. What is the PW of Option...
The machines shown below are under consideration for an improvement to an automated candy bar wrapping...
The machines shown below are under consideration for an improvement to an automated candy bar wrapping process. Machine C Machine D First cost, $ –50,000 –65,000 Annual cost, $/year –10,000 –15,000 Salvage value, $ 12,000   25,000 Life, years 4 7 1.) Based on the data provided and using an interest rate of 8% per year, the Capital Recovery “CR” of Machine C is closest to: (All the alternatives presented below were calculated using compound interest factor tables including all decimal...
1) The machines shown below are under consideration for an improvement to an automated candy bar...
1) The machines shown below are under consideration for an improvement to an automated candy bar wrapping process. Determine which machine should be selected on the basis of an Annual Worth Analysis using an interest rate of 10% per year. (50 points) (Remember to include complete calculations for AWmachine C, AWmachine D, and selection) Machine C Machine D First cost, $ –40,000 –75,000 Annual cost, $/year –15,000 –10,000 Salvage value, $ 12,000 25,000 Life, years 3 6 Chapter 7_Rate of...
The machines shown below are under consideration for an improvement to an automated candy bar wrapping...
The machines shown below are under consideration for an improvement to an automated candy bar wrapping process. Determine which machine should be selected on the basis of an Annual Worth Analysis using an interest rate of 8% per year. (50 points) Machine C Machine D First cost, $ –40,000 –65,000 Annual cost, $/year –10,000 –12,000 Salvage value, $ 12,000 25,000 Life, years 3 6
The machines shown below are under consideration for an improvement to an automated candy bar wrapping...
The machines shown below are under consideration for an improvement to an automated candy bar wrapping process. Machine C Machine D First cost, $ –40,000 –75,000 Annual cost, $/year –15,000 –10,000 Salvage value, $ 12,000 25,000 Life, years 3 6 (Source: Blank and Tarquin) Question 1 (10 points) Based on the data provided and using an interest rate of 5% per year, the correct equation to calculate the Capital Recovery “CR” of Machine C is: CRC = –40,000(P/A, 5%, 3)...
Five mutually exclusive cost alternatives that have infinite lives are under consideration for decreasing the fruit-bruising...
Five mutually exclusive cost alternatives that have infinite lives are under consideration for decreasing the fruit-bruising rates of a thin skin-fruit grading and packing operation (peaches, pears, apricots, etc.). The initial costs and cash flows of each alternative are available. If the MARR is 15% per year, the one alternative to select is: Alternative A B C D E Initial cost, $ −15,000 −12,000 −9,000 −14,000 −11,000 Cash flow, $ per year −300 −900 −1400 −700 −1000 A B D...
Below you have a payoff table for a set of decisions that are under consideration.                             &nb
Below you have a payoff table for a set of decisions that are under consideration.                                                States of Nature Alternative                  Low          High Option A                     10              15 Option B                     12              13 Option C                     13               10 Choose the correspondence equation line for option A, B, and C: Y= -5x+15x Y=3x+10 Y=-X+13
The estimates shown are for a bridge under consideration. Use the B/C ration method at an...
The estimates shown are for a bridge under consideration. Use the B/C ration method at an interest rate of 6% per year to determine which bridge, if either , should be built. East Location West Location Initial Cost, $ 11,000,000 27,000,000 Annual M&O, $/year 100,000 90,000 Benefits $/year 990,000 2,400,000 Disbenefits $/year 120,000 100,000 Life, years infinity infinity
The two ME alternatives shown are under consideration for facility improvements in a company in Abu...
The two ME alternatives shown are under consideration for facility improvements in a company in Abu Dhabi. Determine which one should be selected based on a B/C analysis. Assume an interest rate of 10% per year and a 5-year study period.                                                                                                            Alternative X Alternative Y First costs, AED 40,000 90,000 Annual M&O costs, AED per year 50,000 20,000 Benefits, AED per year 120,000 150,000 Disbenefits, AED per year 30,000 10,000 Match the closest correct answers for the below questions:...
Three different plans for financing an $7,200,000 corporation are under consideration by its organizers. Under each...
Three different plans for financing an $7,200,000 corporation are under consideration by its organizers. Under each of the following plans, the securities will be issued at their par or face amount, and the income tax rate is estimated at 40% of income: Plan 1 Plan 2 Plan 3 10% Bonds _ _ $3,600,000 Preferred 10% stock, $40 par _ $3,600,000 1,800,000 Common stock, $7.2 par $7,200,000 3,600,000 1,800,000 Total $ 7,200,000 $ 7,200,000 $ 7,200,000 Required: 1. Determine the earnings...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT