Question

In: Accounting

The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

The following information applies to the questions displayed below.]

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400
Estimated costs to complete as of year-end 5,796,000 1,764,000 0
Billings during the year 2,040,000 4,596,000 3,364,000
Cash collections during the year 1,820,000 4,000,000 4,180,000


Westgate recognizes revenue over time according to percentage of completion.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2021. 2022. 2023

Revenue

Gross profit(loss)

Solutions

Expert Solution

  • Requirement 1

2021

2022

2023

Revenue

$       3,100,000.00

$       4,800,000.00

$          2,100,000.00

Gross Profits

$           496,000.00

$          768,000.00

$              159,600.00

Working

2021

2022

2023

A

Contract Price

$     10,000,000.00

$    10,000,000.00

$        10,000,000.00

B

Cost Incurred to Date

$       2,604,000.00

$       6,636,000.00

$          8,576,400.00

C

Estimated cost yet to be incurred to complete the contract

$       5,796,000.00

$       1,764,000.00

$                                -  

D = B+C

Total Cost

$       8,400,000.00

$       8,400,000.00

$          8,576,400.00

E = (B/D) x 100

% of Completion

31.00%

79.00%

100.00%

F = A x E

Revenue to date

$       3,100,000.00

$       7,900,000.00

$        10,000,000.00

G

Revenue of Previous year

$                            -  

$       3,100,000.00

$          7,900,000.00

H = F - G

Net Revenue this year

$       3,100,000.00

$       4,800,000.00

$          2,100,000.00

I (=B)

Cost to date

$       2,604,000.00

$       6,636,000.00

$          8,576,400.00

J

Cost to date of previous year

$                            -  

$       2,604,000.00

$          6,636,000.00

K = I - J

Net Cost for the year

$       2,604,000.00

$       4,032,000.00

$          1,940,400.00

L = H - K

Gross Profits

$           496,000.00

$          768,000.00

$              159,600.00


Related Solutions

[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year 2,016,000 2,808,000 2,613,600 Estimated costs to complete as of year end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000...
The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered...
The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,510,000 $ 2,316,600 Estimated costs to complete as of year-end 5,616,000 2,106,000 0 Billings during the year 2,120,000 3,574,000 4,306,000 Cash collections during the year 1,860,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the...
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company...
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT