In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800
Estimated costs to complete as of year-end 6,020,000 1,978,000 0
Billings during the year 2,060,000 4,562,000 3,378,000
Cash collections during the year 1,830,000 4,200,000 3,970,000


Westgate recognizes revenue over time according to percentage of completion.

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,580,000 $ 3,830,000 $ 3,230,000
Estimated costs to complete as of year-end 6,020,000 3,130,000 0

Solutions

Expert Solution

Calculation of Percentage of Completion for the Year ending 2021,2022 and 2023

2021 2022 2023

Cost incurred up to the end of the year (A)

$ 2580000

$ 6410000

($ 2580000 + $ 3830000)

$ 9640000

($ 2580000 + $ 3830000 + $ 3230000)

Estimated costs to complete as of year-end $ 6020000 $ 3130000 $ 0
Total Cost end of the year (B) $ 8600000 $ 9540000 $ 9640000
Percentage of Completion (A / B) 30 % 67.20 % 100 %

Calculation of the amount of revenue and gross profit (loss) to be recognized in each of the three years

2021 2022 2023

Contract Amount

$ 10000000

$ 10000000

$ 10000000

Percentage of Completion 30 % 67.20 % 100 %
Revenue upto end of the year $ 3000000 $ 6720000 $ 10000000
Less: Revenue already recognized in Previous years $ 0 ($ 3000000) ($ 6720000)
Revenue recognized during the year $ 3000000 $ 3720000 $ 3280000
Less: Cost incurred during the year ($ 2580000) ($ 3830000) ($ 3230000)
Gross Profit / (loss) $ 420000 ($ 110000) $ 50000

Related Solutions

Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT