Question

In: Accounting

The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered...

The following information applies to the questions displayed below.]

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,184,000 $ 3,510,000 $ 2,316,600
Estimated costs to complete as of year-end 5,616,000 2,106,000 0
Billings during the year 2,120,000 3,574,000 4,306,000
Cash collections during the year 1,860,000 3,400,000 4,740,000


Westgate recognizes revenue over time according to percentage of completion.


rev: 09_15_2017_QC_CS-99734

2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).

Solutions

Expert Solution

Working notes for calculation of Revenue below:

2018 2019 2020
Actual cost          2,184,000        3,510,000        2,316,600        8,010,600
Estimated cost          5,616,000        2,106,000                        -          7,722,000
Percentage of Completion 28% 74% 100%
Contract To Date Revenue          2,828,283        7,373,737      10,000,000
Yearly Revenue          2,828,283        4,545,455        2,626,263      10,000,000
Billings during the year          2,120,000        3,574,000        4,306,000      10,000,000
Cash collections          1,860,000        3,400,000        4,740,000      10,000,000

Note 1: Percentage of Completion = Cost to date / Total Estimated cost

Note 2: Contract to date Revenue Recognition = Total Estimated Revenue (Billings) * Percentage of Completion

Journal for the above transactions below:

Date Dr/Cr Particulars LF Debit Credit
2-a Dr Cost incurred A/c     2,184,000
Cr To Bank 2,184,000
(Cost incured for the year)
Dr Santa Clara County A/c     2,120,000
Cr To Sales 2,120,000
(Billings for the year)
Dr Bank A/c     1,860,000
Cr Santa Clara County A/c 1,860,000
(Cash received)
Dr Accrued billings A/c        708,283
Cr To Sales      708,283
(Accrued Revenue on POC method)
2-b Dr Sales A/c        708,283
Dr To Accrued Billings A/c      708,283
(Accrual of the previous year reversed)
Dr Cost incurred A/c     3,510,000
Cr To Bank 3,510,000
(Cost incured for the year)
Dr Santa Clara County A/c     3,574,000
Cr To Sales 3,574,000
(Billings for the year)
Dr Bank A/c     3,400,000
Dr Santa Clara County A/c 3,400,000
(Cash received)
Dr Accrued billings A/c     1,679,737
Dr To Sales 1,679,737
(Accrued Revenue on POC method)
2-c Dr Sales A/c     1,679,737
Dr To Accrued Billings A/c 1,679,737
(Accrual of the previous year reversed)
Dr Cost incurred A/c     2,316,600
Dr To Bank 2,316,600
(Cost incured for the year)
Dr Santa Clara County A/c     4,306,000
Dr To Sales 4,306,000
(Billings for the year)
Dr Bank A/c     4,740,000
Dr Santa Clara County A/c 4,740,000
(Cash received)

Related Solutions

[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company...
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year 2,016,000 2,808,000 2,613,600 Estimated costs to complete as of year end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT