In: Accounting
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,640,000 | $ | 2,300,000 | $ | 2,926,000 | |||
Estimated costs to complete as of year-end | 6,160,000 | 2,660,000 | 0 | ||||||
Billings during the year | 2,080,000 | 2,860,000 | 5,060,000 | ||||||
Cash collections during the year | 1,840,000 | 2,800,000 | 5,360,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
(Do not round intermediate calculations. Loss amounts
should be indicated with a minus sign.)
2-a. In the journal below, complete the
necessary journal entries for the year 2021 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2021 | 2022 | 2023 | |||||||
Costs incurred during the year | $ | 2,640,000 | $ | 3,840,000 | $ | 3,240,000 | |||
Estimated costs to complete as of year-end | 6,160,000 | 3,140,000 | 0 | ||||||
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2021 | 2022 | 2023 | |||||||
Costs incurred during the year | $ | 2,640,000 | $ | 3,840,000 | $ | 4,020,000 | |||
Estimated costs to complete as of year-end | 6,160,000 | 4,180,000 | 0 | ||||||
Particulars | Year 2021($) | Year 2022($) | Year 2023($) | Total($) |
Contract Revenue | 10,000,000 | |||
Cost incurred till date | 2,640,000 | 2,300,000 | 2,926,000 | 7,866,000 |
Estimated Cost to complete | 6,160,000 | 2,660,000 | 0 | 8,820,000 |
Total cost to complete estimate | 8,800,000 | 8,820,000 | 7,866,000 | |
(2,640,000+6 ,160,000) | (6,160,000+2,660,000) | (Actual Cost) | ||
Billing during the year | 2,080,000 | 2,860,000 | 5,060,000 | |
Cash collected during the year | 1,840,000 | 2,800,000 | 5,360,000 | |
Percentage of Completion | 30% | 56% | 100% | |
(Cost incurred till date/Total Estimated Cost)*100 | (2,640,000/8,800,000)*100 | (4,940,000/8,820,000)*100 | ||
Revenue to be recognized during the year | 3,000,000 | 2,600,000 | 4,400,000 | |
10,000,000*30% | (10,000,000*56%)-3,000,000 | 10,000,000-5,600,000 | ||
Cost Incurred till date | 2,640,000 | 2,300,000 |
2,926,000 |
|
Gross profit to be recognized during the year | 360,000 | 300,000 | 1,474,000 | |
Question 2 | ||||
(a) | Journal entries for the year 2021 | |||
1. | Construction In Progress a/c Dr | 2,640,000 | ||
To, Payabales A/c | 2,640,000 | |||
2. | Accounts Receivable A/c Dr | 2,080,000 | ||
To, Billing | 2,080,000 | |||
3. | Cash A/c Dr | 1,840,000 | ||
4. | Construction in Progress A/c Dr | 360,000 | ||
Construction Expenses A/c Dr | 2,640,000 | |||
To, Construction Revenue Account | 3,000,000 | |||