In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,204,000 | $ | 3,192,000 | $ | 2,424,400 | |||
Estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 | ||||||
Billings during the year | 2,140,000 | 3,256,000 | 4,604,000 | ||||||
Cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
(Do not round intermediate calculations. Loss amounts
should be indicated with a minus sign.)