In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.