In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts.
Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a.In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b.In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,800,000 $ 3,200,000 Estimated costs to complete as of year-end 5,600,000 3,100,000 0 5.
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,800,000 $ 3,900,000 Estimated costs to complete as of year-end 5,600,000 4,100,000 0
Dear student, we cannot able to post solution more than four sub parts of question as per our policy.
Answer 1 |
|||
Revenue Recognize = Cost incurred plus Gross Profit Less Gross Loss (if any) |
|||
Gross profit Recognize under completed contract method when Company completed contract. |
|||
Gross Profit from Contract = 10000000-2400000-3600000-2200000 |
1,800,000 |
||
Year |
2018 |
2019 |
2020 |
Gross profit |
0 |
0 |
1,800,000 |
Revenue |
2,400,000 |
3,600,000 |
4,000,000 |
Answer 2 |
|||
Date |
General Journal |
Debit |
Credit |
2018 |
Construction in progress |
2,400,000 |
|
Various accounts |
2,400,000 |
||
(To record cost incurred in Progress.) |
|||
2018 |
Accounts receivable |
2,000,000 |
|
Billings on construction contract |
2,000,000 |
||
(To record Billings to Customer.) |
|||
2018 |
Cash |
1,800,000 |
|
Accounts receivable |
1,800,000 |
||
(To record cash collected from customer.) |
|||
2018 |
Cost of construction |
2,400,000 |
|
Revenue from long-term contracts |
2,400,000 |
||
(To record recognize Revenue.) |
|||
2019 |
Construction in progress |
3,600,000 |
|
Various accounts |
3,600,000 |
||
(To record cost incurred in Progress.) |
|||
2019 |
Accounts receivable |
4,000,000 |
|
Billings on construction contract |
4,000,000 |
||
(To record Billings to Customer.) |
|||
2019 |
Cash |
3,600,000 |
|
Accounts receivable |
3,600,000 |
||
(To record cash collected from customer.) |
|||
2019 |
Cost of construction |
3,600,000 |
|
Revenue from long-term contracts |
3,600,000 |
||
(To record recognize Revenue.) |
|||
2020 |
Construction in progress |
2,200,000 |
|
Various accounts |
2,200,000 |
||
(To record cost incurred in Progress.) |
|||
2020 |
Accounts receivable |
4,000,000 |
|
Billings on construction contract |
4,000,000 |
||
(To record Billings to Customer.) |
|||
2020 |
Cash |
4,600,000 |
|
Accounts receivable |
4,600,000 |
||
(To record cash collected from customer.) |
|||
2020 |
Construction in progress |
1,800,000 |
|
Cost of construction |
2,200,000 |
||
Revenue from long-term contracts |
4,000,000 |
||
(To record recognize Revenue.) |
Answer 3 |
||||
Partial balance sheet |
||||
2018 |
2019 |
|||
Current assets |
||||
Account receivable |
200,000 |
600,000 |
||
Construction in progress |
2,400,000 |
6,000,000 |
||
Less: Billings |
2,000,000 |
6,000,000 |
||
Cost in excess of Billings |
400,000 |
0 |
||
Current liability |
||||
Answer 4 |
|||
Revenue Recognize = Cost incurred plus Gross Profit Less Gross Loss (if any) |
|||
Gross profit Recognize under completed contract method when Company completed contract. |
|||
Gross Profit from Contract = 10000000-2400000-3800000-3200000 |
600,000 |
||
Year |
2018 |
2019 |
2020 |
Gross profit |
0 |
0 |
600,000 |
Revenue |
2,400,000 |
3,800,000 |
3,800,000 |