Question

In: Accounting

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts.

Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.

2-a.In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).

2-b.In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).

2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).

3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,800,000 $ 3,200,000 Estimated costs to complete as of year-end 5,600,000 3,100,000 0 5.

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,800,000 $ 3,900,000 Estimated costs to complete as of year-end 5,600,000 4,100,000 0

Solutions

Expert Solution

Dear student, we cannot able to post solution more than four sub parts of question as per our policy.

Answer 1

Revenue Recognize = Cost incurred plus Gross Profit Less Gross Loss (if any)

Gross profit Recognize under completed contract method when Company completed contract.

Gross Profit from Contract = 10000000-2400000-3600000-2200000

         1,800,000

Year

2018

2019

2020

Gross profit

                          0

                          0

         1,800,000

Revenue

         2,400,000

         3,600,000

         4,000,000

Answer 2

Date

General Journal

Debit

Credit

2018

Construction in progress

         2,400,000

Various accounts

         2,400,000

(To record cost incurred in Progress.)

2018

Accounts receivable

         2,000,000

Billings on construction contract

         2,000,000

(To record Billings to Customer.)

2018

Cash

         1,800,000

Accounts receivable

         1,800,000

(To record cash collected from customer.)

2018

Cost of construction

         2,400,000

Revenue from long-term contracts

         2,400,000

(To record recognize Revenue.)

2019

Construction in progress

         3,600,000

Various accounts

         3,600,000

(To record cost incurred in Progress.)

2019

Accounts receivable

         4,000,000

Billings on construction contract

         4,000,000

(To record Billings to Customer.)

2019

Cash

         3,600,000

Accounts receivable

         3,600,000

(To record cash collected from customer.)

2019

Cost of construction

         3,600,000

Revenue from long-term contracts

         3,600,000

(To record recognize Revenue.)

2020

Construction in progress

         2,200,000

Various accounts

         2,200,000

(To record cost incurred in Progress.)

2020

Accounts receivable

         4,000,000

Billings on construction contract

         4,000,000

(To record Billings to Customer.)

2020

Cash

         4,600,000

Accounts receivable

         4,600,000

(To record cash collected from customer.)

2020

Construction in progress

         1,800,000

Cost of construction

         2,200,000

Revenue from long-term contracts

         4,000,000

(To record recognize Revenue.)

Answer 3

Partial balance sheet

2018

2019

Current assets

Account receivable

             200,000

       600,000

Construction in progress

         2,400,000

         6,000,000

Less: Billings

         2,000,000

         6,000,000

Cost in excess of Billings

             400,000

                    0

Current liability

Answer 4

Revenue Recognize = Cost incurred plus Gross Profit Less Gross Loss (if any)

Gross profit Recognize under completed contract method when Company completed contract.

Gross Profit from Contract = 10000000-2400000-3800000-3200000

             600,000

Year

2018

2019

2020

Gross profit

                          0

                          0

             600,000

Revenue

        2,400,000

         3,800,000

         3,800,000


Related Solutions

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018. 2019 2020 Cost incurred during the year $2,624,000  $3,690,000  $2,074,600 Estimated costs to complete as of year-end 5,576,000   1,886,000 0 Billings during the year 2,200,000   4,114,000   3,686,000 Cash collections during the year 2,000,000   3,800,000   4,200,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,610,000 $ 3,162,000 $ 2,230,800 Estimated costs to complete as of year-end 6,390,000 2,028,000 0 Billings during the year 2,100,000 3,672,000 4,228,000 Cash collections during the year 1,850,000 3,000,000 5,150,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the year 1,840,000 2,800,000 5,360,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT