In: Accounting
In 2018, the Westgate
Construction Company entered into a contract to construct a road
for Santa Clara County for $10,000,000. The road was completed in
2020. Information related to the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 3,150,000 | $ | 2,475,000 | |||
Estimated costs to complete as of year-end | 5,400,000 | 2,250,000 | 0 | ||||||
Billings during the year | 2,150,000 | 3,100,000 | 4,750,000 | ||||||
Cash collections during the year | 1,875,000 | 3,100,000 | 5,025,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 3,875,000 | $ | 3,275,000 | |||
Estimated costs to complete as of year-end | 5,400,000 | 3,175,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 3,875,000 | $ | 4,125,000 | |||
Estimated costs to complete as of year-end | 5,400,000 | 4,250,000 | 0 | ||||||
Please help, i am so confused.....
As per policy only first four questions will be answered
Part 1
2018 | 2019 | 2020 | |
Revenue recognized | 2800000 | 4200000 | 3000000 |
Gross profit (loss) | 700000 | 1050000 | 525000 |
Revenue recognized
2018 = costs incurred / total costs * contract price = 2100000/(2100000+5400000)*10000000 = 2800000
2019 = 3150000/(3150000+2250000)*(10000000 - 2800000) = 4200000
2020= 10000000-2800000 - 4200000 = 3000000
Gross profit = revenue - expenses
2018 = 2800000-2100000 = 700000
2019 = 4200000-3150000 = 1050000
2020 = 3000000-2475000 = 525000
Part 2A
Date | general journal | debit | credit |
2018 | construction in progress | 2100000 | |
Various accounts | 2100000 | ||
2018 | accounts receivable | 2150000 | |
Bills on construction contract | 2150000 | ||
2018 | cash | 1875000 | |
Accounts receivable | 1875000 | ||
2018 | construction in progress | 700000 | |
Cost of construction | 2100000 | ||
Revenue from long-term contracts | 2800000 |
Part 2 B
Date | general journal | debit | credit |
2019 | construction in progress | 3150000 | |
Various accounts | 3150000 | ||
2019 | accounts receivable | 3100000 | |
Bills on construction contract | 3100000 | ||
2019 | cash | 3100000 | |
Accounts receivable | 3100000 | ||
2019 | construction in progress | 1050000 | |
Cost of construction | 3150000 | ||
Revenue from long-term contract | 4200000 |
Part 2 C
Date | general journal | debit | credit |
2020 | construction in progress | 2475000 | |
Various accounts | 2475000 | ||
2020 | Accounts receivable |
4750000 |
|
Bills on construction contract | 4750000 | ||
2020 | Cash | 5025000 | |
Accounts receivable | 5025000 | ||
2020 | Construction in progress | 525000 | |
Cost of construction | 2475000 | ||
Revenue from long-term contract | 3000000 |