Question

In: Finance

King Ltd enters into a fixed price contract for $18 000 000 to build a train...

King Ltd enters into a fixed price contract for $18 000 000 to build a train station for Hunter Ltd. It will take 3 years to build the station. The project is expected to be completed by the end of 2020. King Ltd’s estimate of contract costs is $16 000 000 at the commencement of construction. However, the expected costs to complete a construction project can change throughout the project. The following data relates to the project: 2018 2019 2020 Progress billing to date 4 000 000 12 000 000 18 000 000 Cash collection to date 3 500 000 11 500 000 18 000 000 Costs for the year 4 000 000 8 500 000 4 000 000 Costs incurred to date 4 000 000 12 500 000 16 500 000 Estimated costs to complete 12 000 000 4 000 000 — What is the gross profit to be recognised by King Ltd at the end of 2019? a. 500 000 b. 636 363 c. 1 136 363 d. 1 015 152

Solutions

Expert Solution

2018 2019 2020
Revenue for the year            4,500,000            9,136,364            4,363,636
Costs incurred during the year            4,000,000            8,500,000            4,000,000
Gross profit/ (loss)                500,000                636,364                363,636
Costs incurred during the year            4,000,000            8,500,000            4,000,000
Costs incurred in prior years                           -              4,000,000          12,500,000
A Total costs icurred            4,000,000          12,500,000          16,500,000
Total costs:
Costs incurred in prior years                           -              4,000,000          12,500,000
costs incurred during the year            4,000,000            8,500,000            4,000,000
estimated cost to complete          12,000,000            4,000,000                           -  
B Total contract costs          16,000,000          16,500,000          16,500,000
C=A/B *100 Percentage of completion 25.00% 75.76% 100.00%
D Contract amount          18,000,000          18,000,000          18,000,000
E=C*D Revenue earned            4,500,000          13,636,364          18,000,000
Less: revenue recognised in earlier years                           -              4,500,000          13,636,364
Revenue for the year            4,500,000            9,136,363.64            4,363,636

Revenut for 2019 = 9,136,363.64

Expenses for 2019 = $8,500,000

Gross profit = 9,136,363.64 - $8,500,000 = $636,363

Answer is b. 636 363

Please rate the answer.


Related Solutions

Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? a. $0 b. $1,050,000 c....
QUESTION 2 (IFRS 16) (12) Build Ltd enters into a contract with Bull Ltd for the...
QUESTION 2 (IFRS 16) (12) Build Ltd enters into a contract with Bull Ltd for the lease of heavy construction equipment. The duration of the lease is for one year. Bull Ltd undertakes to insure the equipment and to maintain it by having it serviced every month. The contract stipulates that the payments are $24 000 for the year, of which $4 000 relates to the annual insurance and $7 200 relates to the provision of monthly servicing, which would...
A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Cullumber commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5%...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on...
Cullumber Construction enters into a contract with a customer to build a warehouse for $1070000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Cullumber commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5%...
On January 2016, Profit Ltd enters the contract with City Ltd for the use of a...
On January 2016, Profit Ltd enters the contract with City Ltd for the use of a truck. The contract contained the following clauses: Lease term: four years with a $6,000 purchase option at the end of the lease. Lease payments: $200,048 per annum in advance, the first payment is made on 1 January 2016. Fair value of the truck : $720,000 Profit Ltd incurs $50,000 initial direct cost, including $15,000 legal fees and $35,000 commission to real estate agent At...
On January 2016, Profit Ltd enters the contract with City Ltd for the use of a...
On January 2016, Profit Ltd enters the contract with City Ltd for the use of a truck. The contract contained the following clauses: Lease term: four years with a $6,000 purchase option at the end of the lease. Lease payments: $200,048 per annum in advance, the first payment is made on 1 January 2016. Fair value of the truck : $720,000 Profit Ltd incurs $50,000 initial direct cost, including $15,000 legal fees and $35,000 commission to real estate agent At...
At the beginning of 2021 Carefree Contracting Corporation (CCC) enters into a contract to build a...
At the beginning of 2021 Carefree Contracting Corporation (CCC) enters into a contract to build a home for a customer that is expected to take three years to complete. The contract price is $4,000,000. Completion is scheduled for the end of 2023. CCC's year end is December 31. 2021 2022 2023 Actual costs incurred current year $750,000 $2,250,000 $775,000 actual costs incurred prior years -0- 750,000 3,000,000 Cumulative actual costs incurred to date 750,000 3,000,000 3,775,000 Estimated costs to complete...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT