Question

In: Finance

"Consider the following cash flows for projects X and Y. Assume the firm can only select...

"Consider the following cash flows for projects X and Y. Assume the firm can only select one of the projects. What is the MARR such that the firm is indifferent between selecting Project X or Y? Enter your answer as a percent between 0 and 100, rounded to the nearest tenth of a percent. You might consider an incremental approach.
Project X (for n = 0 through 4) $ :
-11,100
8,400
4,574
1,340
610
IRR : 21.1%
Project Y (for n = 0 through 4) $ :
-5,703
4,653
2,287
1,340
610
IRR : 30.8%"

Solutions

Expert Solution

here incremental approach should be used

It is assumed tha project X is choosen over Project Y

Hence Incremental cash out flow = -11100 - (-5703) = -5397 $

Incremental cash inflow for year 1 = 8400 - 4653 = $ 3747

Incremental cash inflow for year 2 = 4574 - 2287 = $ 2287

Incremental cash inflow for year 3 and Incremental cash inflow for year 4 = 0

Now, one shall find IRR . IRR is rate at which NPV is 0

Assume r = 8%, then NPV

Year Incremental cash flow PVIF @ 8% PV
0 -5397 1.0000 -5397.00
1 3747 0.9259 3469.44
2 2287 0.8573 1960.73
Total = NPV 33.18

Assume r = 9% ,then NPV

Year Incremental cash flow PVIF @ 9% PV
0 -5397 1.0000 -5397.00
1 3747 0.9174 3437.61
2 2287 0.8417 1924.92
Total = NPV -34.46

Using interpolation method one can find r

R NPV
8% 33.18
9% -34.46
1% 67.64
? 33.18

=33.18/67.64

=0.49

Thus IRR = 8%+0.49% = 8.49%

Thus at MARR of 8.49% , firm will be indifferent between selecting Project X or Y


Related Solutions

Consider the following projects, X and Y where the firm can only choose one.
3Consider the following projects, X and Y where the firm can only choose one. Project X costs $600 and has cash flows of $400 in each of the next 2 years. Project also costs $600 and generates cash flows of $500 for the next 2 years respectively. Which investment should the firm choose the cost of capital is 25 percent? Another since both the projects have negative NPV Another, since both the projects have positive NPV Project X sine X has a higher...
Consider the following projects X and Y where the firm can choose only once. Project X...
Consider the following projects X and Y where the firm can choose only once. Project X costs $600 and has cash flows of $400 in each of the next two years. Project B also costs $ 600 and generates cash flows $500 and $275 for the next two years, respectively. Sketch a net present value profile (graphs) for each of these projects. For graphs you may use approximation Which project should the firm choose if the cost of capital is...
Consider the following projects, X and Y where the firm can only choose one. Project X...
Consider the following projects, X and Y where the firm can only choose one. Project X costs $1500 and has cash flows of $678, $652, $347, $111, $54, $16 in each of the next 6 years. Project Y also costs $1500, and generates cash flows of $738, $693, $405 for the next 3 years, respectively. WACC=9.5%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $300 $400 $700 Project Y -$1,000 $900 $100 $55 $45 The projects are equally risky, and their WACC is 10%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $100 $300 $400 $650 Project Y -$1,000 $1,000 $110 $45 $55 The projects are equally risky, and their WACC is 10%. What is the MIRR of the project that maximizes shareholder value? Do not round intermediate calculations. Round your answer to two decimal places.   %_____
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $280 $400 $700 Project Y -$1,000 $1,100 $110 $45 $50 The projects are equally risky, and their WACC is 11%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $320 $400 $750 Project Y -$1,000 $1,000 $90 $45 $50 The projects are equally risky, and their WACC is 11%. What is the MIRR of the project that maximizes shareholder value? Do not round intermediate calculations. Round your answer to two decimal places
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $90 $300 $370 $650 Project Y -$1,000 $900 $100 $50 $45 The projects are equally risky, and their WACC is 10%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. ____%
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $110 $280 $370 $650 Project Y -$1,000 $1,100 $100 $55 $45 The projects are equally risky, and their WACC is 8%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. %
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...
A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: Project X: CF0= -$1,000, CF1= $110, CF2= $300, CF3= $370, CF4= $750 Project Y: CF0= -$1,000, CF1= $900, CF2= $110, CF3= $50, CF4= $50 The projects are equally risky, and their WACC is 13%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT