In: Finance
A. Cost of capital = 10%
NPV of Proj X = NPV(Rate, CF1,CF2) + CF0 = NPV(10%,400,400) -600 =
$94
NPV of Proj Y = NPV(10%,500,275) - 600 = $82
Based on NPV, Proj X is better due to higher NPV
B. Cost of capital = 25%
NPV of Proj X = NPV(Rate, CF1,CF2) + CF0 = NPV(25%,400,400) -600 =
($24)
NPV of Proj Y = NPV(25%,500,275) - 600 =($24)
Based on NPV, Both projects should be rejected.