Question

In: Finance

Consider the following projects, X and Y where the firm can only choose one.


3

Consider the following projects, X and Y where the firm can only choose one. Project X costs $600 and has cash flows of $400 in each of the next 2 years. Project also costs $600 and generates cash flows of $500 for the next 2 years respectively. Which investment should the firm choose the cost of capital is 25 percent? 

Another since both the projects have negative NPV 

Another, since both the projects have positive NPV 

Project X sine X has a higher NPV than Y 

Project Y since Y has a higher NPV than X


4

Capital asset pricing model (CAPM) For the shown in the following table, use the capital asset pricing model to find the required return.

image.png

Solutions

Expert Solution

Answer to question 3

The correct answer is D. Project Y, since it has a higher NPV than Project X.

For mutually exclusive projects we need to select only one of them. When Net Present Value (NPV) of both the projects is positive then such project will be selected whose NPV is greater.

Generally while using NPV for decision making such project should be selected whose NPV is greater than zero. In case of negative NPV such project shall be rejected.

NPV = Present value of cash inflows - Initial Investment

Since the NPV of Project Y is greater, it should be selected over project X.

Note - How did we calculate discounting factors @25%

Year 1 - 1/1.25

= 0.8000

Year 2 - 0.8000 / 1.25

= 0.6400

Answer to question 4

As per Capital Asset Pricing Model (CAPM)

Re = Rf + (Rm-Rf) β

Where Re = Required rate of return

Rf = Risk free rate of return

Rm – Market Return or Expected Return on Market

β – Beta

Calculation of Required rate of return

Rm = 10 %

Rf = 4 %

β = 1.7

Using the formula Re = Rf + (Rm-Rf) β

Re = 4 + (10-4) 1.7

= 4 + 6 * 1.7

= 4 + 10.2

= 14.20 %

Therefore Required Rate of Return = 14.20%


Related Solutions

Consider the following projects, X and Y where the firm can only choose one. Project X...
Consider the following projects, X and Y where the firm can only choose one. Project X costs $1500 and has cash flows of $678, $652, $347, $111, $54, $16 in each of the next 6 years. Project Y also costs $1500, and generates cash flows of $738, $693, $405 for the next 3 years, respectively. WACC=9.5%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...
Consider the following projects X and Y where the firm can choose only once. Project X...
Consider the following projects X and Y where the firm can choose only once. Project X costs $600 and has cash flows of $400 in each of the next two years. Project B also costs $ 600 and generates cash flows $500 and $275 for the next two years, respectively. Sketch a net present value profile (graphs) for each of these projects. For graphs you may use approximation Which project should the firm choose if the cost of capital is...
"Consider the following cash flows for projects X and Y. Assume the firm can only select...
"Consider the following cash flows for projects X and Y. Assume the firm can only select one of the projects. What is the MARR such that the firm is indifferent between selecting Project X or Y? Enter your answer as a percent between 0 and 100, rounded to the nearest tenth of a percent. You might consider an incremental approach. Project X (for n = 0 through 4) $ : -11,100 8,400 4,574 1,340 610 IRR : 21.1% Project Y...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Consider the following premerger information about Firm X and Firm Y: Firm X Firm Y Total...
Consider the following premerger information about Firm X and Firm Y: Firm X Firm Y Total earnings $ 88,000 $ 18,500 Shares outstanding 45,000 20,000 Per-share values: Market $ 45 $ 16 Book $ 16 $ 7 Assume that Firm X acquires Firm Y by paying cash for all the shares outstanding at a merger premium of $5 per share, and that neither firm has any debt before or after the merger. Construct the postmerger balance sheet for Firm X...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Project X cash flows -$100 80 60 40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 2.0% 18.7% Regular Payback 2.23 years 1.77 years 5) Assuming the three projects X, Y & Z are...
ompany B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
ompany B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Project X cash flows -$100 80 60 40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 2.0% 18.7% Regular Payback 2.23 years 1.77 years 9) If IRR for Project X is 17.95%, and the...
Solve the following differential equation: y''+e^{-y}=0 where y is only a function of x.
Solve the following differential equation: y''+e^{-y}=0 where y is only a function of x.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT