In: Statistics and Probability
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
Activity |
Activity Time (weeks) |
Probability |
||
| A | 5 | 0.32 | ||
| 6 | 0.39 | |||
| 7 | 0.27 | |||
| 8 | 0.02 | |||
| B | 4 | 0.18 | ||
| 6 | 0.51 | |||
| 8 | 0.31 | |||
| C | 7 | 0.10 | ||
| 9 | 0.29 | |||
| 11 | 0.43 | |||
| 13 | 0.15 | |||
| 15 | 0.03 | |||
| D | 10 | 0.61 | ||
| 12 | 0.39 | |||
| Activity | Base case | Worst case | Best case |
|---|---|---|---|
| A | weeks | weeks | weeks |
| B | weeks | weeks | weeks |
| C | weeks | weeks | weeks |
| D | weeks | weeks | weeks |
| Total | weeks | weeks | weeks |
| Activity | Random Number | Completion Time |
|---|---|---|
| A | 0.3487 | weeks |
| B | 0.4561 | weeks |
| C | 0.3031 | weeks |
| D | 0.9067 | weeks |
| Total | weeks |