Question

In: Statistics and Probability

A project has four activities (A, B, C, and D) that must be performed sequentially. The...

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:


Activity
Activity Time
(weeks)

Probability
A 5 0.32
6 0.39
7 0.27
8 0.02
B 4 0.18
6 0.51
8 0.31
C 7 0.10
9 0.29
11 0.43
13 0.15
15 0.03
D 10 0.61
12 0.39
  1. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
    Activity Base case Worst case Best case
    A weeks weeks weeks
    B weeks weeks weeks
    C weeks weeks weeks
    D weeks weeks weeks
    Total weeks weeks weeks
  2. Use the random numbers 0.3487, 0.4561, 0.3031 and 0.9067 to simulate the completion time of the project in weeks.
    Activity Random Number Completion Time
    A 0.3487 weeks
    B 0.4561 weeks
    C 0.3031 weeks
    D 0.9067 weeks
    Total weeks
  3. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less.

    Simulation provides a distribution of project completion times. The ___ of times weeks and under can be used to estimate the probability that the project will be completed within weeks.

Solutions

Expert Solution


Related Solutions

A project has five activities: A, B, C, and D, which must be carried out sequentially....
A project has five activities: A, B, C, and D, which must be carried out sequentially. The probability distributions of the number of weeks required to complete each of the activities A, B, and C are uniform in intervals [1,5], [2,3], and [3,6], respectively. The number of weeks required to complete activity D is a beta distribution with shape parameters a=2 and b=5, lower bound 2, and upper bound 10. Use simulation to forecast the total completion time of the...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 3 0.29 4 0.38 5 0.29 6 0.04 B 7 0.22 9 0.53 11 0.25 C 9 0.05 11 0.24 13 0.36 15 0.19 17 0.16 D 10 0.59 12 0.41 Provide the base-case, worst-case, and best-case calculations for the...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
You are following four traits (a, b, c, and d). The following crosses were performed. -...
You are following four traits (a, b, c, and d). The following crosses were performed. - Cross 1: a b female x c d male F1 progeny: all wild type - Cross 2: F1 female x F1 male F2 progeny:    1600 wild type (total 6400)     800 d 400 b d 800 a 400 a b 1200 c 400 dc 800 b A. Describe the inheritance pattern for each trait.   Be as complete as possible. B. Which, if any, genes are...
2) You are following four traits (a, b, c, and d). The following crosses were performed....
2) You are following four traits (a, b, c, and d). The following crosses were performed. Cross 1: a b female x c d male F1 progeny: all wild type Cross 2: F1 female x F1 male F2 progeny:     1600 wild type (total 6400)     800 d 400 b d 800 a 400 a b 1200 c 400 dc 800 b A. Describe the inheritance pattern for each trait.   Be as complete as possible. B. Which, if any, genes are linked?...
The following graph contains four lines (A, B, C and D), each of which has a...
The following graph contains four lines (A, B, C and D), each of which has a slope that is either positive, negative, zero, or infinite.For each of the following scenarios, indicate whether the relationship between the two variables is positive or negative, as well as which line on the previous graph has a slope that reflects this type of relationship. Hint: The X-axis and Y-axis on the graph are not labeled intentionally. You need to substitute the variables from each scenario...
The following graph contains four lines (A, B, C and D), each of which has a...
The following graph contains four lines (A, B, C and D), each of which has a slope that is either positive, negative, zero, or infinite.For each of the following scenarios, indicate whether the relationship between the two variables is positive or negative, as well as which line on the previous graph has a slope that reflects this type of relationship. Hint: The X-axis and Y-axis on the graph are not labeled intentionally. You need to substitute the variables from each scenario...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3...
Consider an experiment with four independent variables: A, B, C, and D. Factor A has 3 levels and is a between-subjects variable; Factor B has 2 levels and is a within-subjects variable; Factor C has 2 levels and is a between-subjects variable; Factor D has 3 levels and is a within-subjects variable. 1. How many “cells” or “conditions” or “groups” are there in this experiment? 2. If you want to test 10 participants per cell, how many TOTAL participants will...
A process has four stages (A, B, C, and D). The stages have output rates of...
A process has four stages (A, B, C, and D). The stages have output rates of 5 units/hr, 12 units/hr, 10 units/hr, and 7 units/hr, respectively. What is the output rate of this process? a. 12 units/hr b. 10 units/hr c. 7 units/hr d. 5 units/hr
A large company has the opportunity to select one of four projects: A, B, C, D,...
A large company has the opportunity to select one of four projects: A, B, C, D, or the null (Do nothing) alternative. Each project requires a single initial investment as shown in the table below. Information on each alternative was fed into a computer program that calculated the IRR for each project as well as the pertinent incremental IRR(s) as shown in the table below. Project Initial Investment Project IRR Incremental Rate of Return of “Row” – “Column” Null A...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT