Question

In: Statistics and Probability

A project has five activities: A, B, C, and D, which must be carried out sequentially....

A project has five activities: A, B, C, and D, which must be carried out sequentially. The probability distributions of the number of weeks required to complete each of the activities A, B, and C are uniform in intervals [1,5], [2,3], and [3,6], respectively. The number of weeks required to complete activity D is a beta distribution with shape parameters a=2 and b=5, lower bound 2, and upper bound 10. Use simulation to forecast the total completion time of the project.

a. What are the mean and standard deviation of the total completion time?

b. What are the upper and lower bounds of a 95% confidence interval for the completion time?

c. What is the probability that the project will be completed within

Solutions

Expert Solution

for A to C column

for beta distribution

I generated Unif(0,1) in G column

then use BETA.INV(p, α, β , lower bound ,upper bound) for each p in G column

last Sum is A+ B+ C +D

then mean ,sd is calculate for sum


Related Solutions

A project has four activities (A, B, C, and D) that must be performed sequentially. The...
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.32 6 0.39 7 0.27 8 0.02 B 4 0.18 6 0.51 8 0.31 C 7 0.10 9 0.29 11 0.43 13 0.15 15 0.03 D 10 0.61 12 0.39 Provide the base-case, worst-case, and best-case calculations for the time to complete...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be...
Problem 12-09 (Algorithmic) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 3 0.29 4 0.38 5 0.29 6 0.04 B 7 0.22 9 0.53 11 0.25 C 9 0.05 11 0.24 13 0.36 15 0.19 17 0.16 D 10 0.59 12 0.41 Provide the base-case, worst-case, and best-case calculations for the...
An elementary reaction A+B  C+D is to be carried out in a non-ideal CSTR which...
An elementary reaction A+B  C+D is to be carried out in a non-ideal CSTR which has both bypassing and a stagnant region in this reactor. The measured reactor volume is 1.0 m3 and the flow rate to the reactor is 0.1 m3/min. The reaction rate constant is 0.28 m3/kmol.min. The feed is equimolar in A and B with an entering concentration of A equal to 2.0 kmol/m3 k. Calculate the conversion that can be expected in this reactor if...
Consider a project consisting of four activities A, B, C, and D. The following are constraints...
Consider a project consisting of four activities A, B, C, and D. The following are constraints within which the project has to be conducted • A and B, the first activities of the project, can be started simultaneously. • C can be started only after A is completed. • D can be started only after B is completed Suppose the activity times for the activities are A = 4 weeks, B = 3 weeks, C = 2 weeks, D =...
Let A = {a, b, c, d} and B = {b, d, e}. Write out all...
Let A = {a, b, c, d} and B = {b, d, e}. Write out all of the elements of the following sets. (a) B ∩ ∅ (b) A ∪ B (c) (A ∩ B) × B (d) P(A\B) (e) {X ∈ P(A) | |X| ≤ 3}
The elementary irreversible gas phase reaction A --> B + C is carried out in a...
The elementary irreversible gas phase reaction A --> B + C is carried out in a PFR packed with catalyst. Pure A enters the reactor at a volumetric flowrate of 20 dm3 /s at a pressure of 10 atm and 450K. CpA=40 J/mol.K HfA=-70 kJ/mol   (TR=273 K) CpB=25 J/mol.K HfB=-50 kJ/mol CpC=15 J/mol.K HfC=-40 kJ/mol k = 0.133 exp ( E/R*[ 1/450 ? 1/T ] ) dm3 kg cat. s with E = 31.4 kJ/mol a) Plot the conversion and...
The elementary irreversible gas phase reaction A --> B + C is carried out in a...
The elementary irreversible gas phase reaction A --> B + C is carried out in a PFR packed with catalyst. Pure A enters the reactor at a volumetric flowrate of 20 dm3 /s at a pressure of 10 atm and 450K. Consider that the heat is removed by a heat exchanger jacketing the reactor. The flowrate of coolant through the jacket is sufficiently high so that the ambient exchanger temperature is constant at 50oC. CpA=40 J/mol.K HfA=-70 kJ/mol CpB=25 J/mol.K...
The elementary irreversible gas phase reaction A --> B + C is carried out in a...
The elementary irreversible gas phase reaction A --> B + C is carried out in a PFR packed with catalyst. Pure A enters the reactor at a volumetric flowrate of 20 dm3 /s at a pressure of 10 atm and 450K. Consider that the heat is removed by a heat exchanger jacketing the reactor. The flowrate of coolant through the jacket is sufficiently high so that the ambient exchanger temperature is constant at 50oC. CpA=40 J/mol.K HfA=-70 kJ/mol CpB=25 J/mol.K...
A factory has in it five machines, A, B, C, D, and E that produce Smart...
A factory has in it five machines, A, B, C, D, and E that produce Smart Pencils. Machine A produces 5 % of the factory's output with a 2 % defective rate. Machine B produces 10 % of the factory's output with a 3 % defective rate. Machine C produces 25 % of the factory's output with a 4 % defective rate. Machine D produces 3 0% of the factory's output with a 5 % defective rate. Machine E produces...
In the diagram, which point is at the lowest potential? (a) A (b) B (c) C (d) D
In the diagram, which point is at the lowest potential?(a) A(b) B(c) C(d) D
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT