Question

In: Mechanical Engineering

Considering quantitative risk assessment, what is one of the most significant disadvantages to project crashing? reference...

Considering quantitative risk assessment, what is one of the most significant disadvantages to project crashing?

reference to source question https://www.chegg.com/homework-help/questions-and-answers/question-4-production-manager-electronic-toys-company-et-co-begin-project-design-productio-q29681067

This is not an incomplete question it is asking in genereal what is the disadvantages of project crashing. where disadvantages are that it is expensive and can cause failure to activities and effect the whole project. the part i do not understand is answering the question with reference to quantitative risk assessment.

Solutions

Expert Solution

Quantitative risk analysis numerically evaluates the effect of potential project risks on project targets. It is focused on creating realistic time and cost targets, and calculating the probability of achieving project objectives. For example, it will quantify the impact of failing to obtain a roadwork permit before the start of the project as causing a week delay and costing $50,000.

Quantitative risk analysis is objective and requires a list of prioritized potential project risks, usually created during the qualitative risk analysis.

Quantitative risk assessment evaluates probability of achieving project targets, providing risk ratings (based on risk to not achieving cost and time targets). Also risk ratings are calculated considering resources and deadlines. Crashing of an activity may require additional resources, which may increase risk on other activities leading to change in risk ratings. So this requires skil, effort and time to determine activities to be crashed and to the optimum level. Thus, considering quantitative risk assessment in project crashing may complicate the process and have it's own probability of failure.


Related Solutions

Make a Project of Management Risk Assessment: 1. Make a Qualitative Risk assessment 2. Make Quantitative...
Make a Project of Management Risk Assessment: 1. Make a Qualitative Risk assessment 2. Make Quantitative Risk Assessment and Mitigation
24. What is project crashing ? What are the 4 steps involved in the project crashing?...
24. What is project crashing ? What are the 4 steps involved in the project crashing? Explain. What is the LP formulation of the project crashing problem? What are the decision variables, constraints and the objective function of the LP formulation of crashing problem? Please answer question fully for a rating
Quantitative and Qualitative Risk Assessments What’s the recommendation by the risk assessment team? What are the...
Quantitative and Qualitative Risk Assessments What’s the recommendation by the risk assessment team? What are the final decisions made by HGA management? Justify their decisions based on cost benefit analysis. PLEASE MAKE COPY PASTE AVAILABLE MUST BE 250 WORDS
4. One of the most significant disadvantages of a monopoly is: a. oligarch capitalization b. no...
4. One of the most significant disadvantages of a monopoly is: a. oligarch capitalization b. no competition from international markets c. price wars d. high prices charged 5. D Ram prices in the U.S. were _____ in Dec-01 a. close to $1 b. better than those in potato sales c. not comparable to those of Vietnamese markets d. fixed 6. Pressure, rationalization, and opportunity help indicate issues that lead to: a. NYPD law investigation b. forensic dissecting of butterflies c....
Describe and explain what you feel is the most significant risk of information systems.
Describe and explain what you feel is the most significant risk of information systems.
Project Risk = Probability of event * Consequences of event Let’s investigate the quantitative risk identified...
Project Risk = Probability of event * Consequences of event Let’s investigate the quantitative risk identified for a company, last year. Probability of Failure Category Probability of Failure Consequences of Failure Category Process Maturity 30% Performance = 55% Technical Complexity 25% Schedule = 75% Vendor Dependency 30% Cost = $55 Workforce Availability 10% Reliability = 20% Use the table above to answer the following questions: Please calculate the total risk factor for this project. Would you assess this level of...
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? $______________ Activity                        Normal Time (days) Crash Time (days) Normal Cost      Total Cost with Crashing Immediate Predecessor(s) A 6 5 $800 $1,100 - B 8 6 $300 $400 - C 6 5 $600 $650 - D 6 3 $750 $1,500 A E 5 3 $1,200 $1,650 C a. $ 3550 b. $ 1550 c. $ 3800 d. $ 2500
REGARDING RISK ASSESSMENT What’s the recommendation by the risk assessment team? What are the final decisions...
REGARDING RISK ASSESSMENT What’s the recommendation by the risk assessment team? What are the final decisions made by HGA management? Justify their decisions based on cost benefit analysis. PLEASE MAKE COPY PASTE AVAILABLE MUST BE 250 WORDS
REGARDING RISK ASSESSMENT What’s the recommendation by the risk assessment team? What are the final decisions...
REGARDING RISK ASSESSMENT What’s the recommendation by the risk assessment team? What are the final decisions made by HGA management? Justify their decisions based on cost benefit analysis. PLEASE MAKE COPY PASTE AVAILABLE MUST BE 250 WORDS
REGARDING RISK ASSESSMENT What’s the recommendation by the risk assessment team?  What are the final decisions made...
REGARDING RISK ASSESSMENT What’s the recommendation by the risk assessment team?  What are the final decisions made by HGA management? Justify their decisions based on cost benefit analysis. PLEASE MAKE COPY PASTE AVAILABLE MUST BE 250 WORDS
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT