Question

In: Operations Management

Complete a qualitative risk assessment and response planning of each of the risk identified in Project...

Complete a qualitative risk assessment and response planning of each of the risk identified in Project 1: Risk Identification (at least 10 risks). Use at least 1 of each of the threat risk response strategies for your response planning.

THE 10 RISKS:

Risk Statement/Description
Project prupose and need is not well defined.
Scope creep
Project schedule is not clearly defined or understood
Lack of communication, causing lack of clarity and confusion
No control over staff proprities
Consultant or contractor delays
Unresoulved project conflicts not escalated in a timely manner
Delay in earlier project phases jeopardizes ability to meet fixed date.                                                           For example delivery of just in time materials, for conference or launch date.
Added workload or time requirements because of new direction, policy, or statute
Stakeholder action delays project

Rubric

Task Point Value (out of 100)
Proper APA format, spelling, grammar, citation, and organization of writing 10 points
Risk Assessment 20 points
Risk Response Planning 50 points
Clear Format and Easy to View/ Report 20 points

Solutions

Expert Solution

A) Task and reason not all around characterized.

This is a hazard on the task which impacts the execution. Without appropriating reason characterized, the assets, and techniques for the task may not be utilized successfully. The reaction procedure to use here is Risk Mitigation, It is an investment to decrease the hazard on the venture.

Now, the undertaking supervisor can require a group gathering with the top administration and comprehend the destinations and reason. He can enlist a specialist to survey the present extend and characterize the key strides to prioritize. When the object is characterized, clear correspondence is required to be set up with the goal that all partner know about the reason.

B) Extension Creep.

Uncontrolled changes to extent of a task prompts Scope Creep. Handling extension creep includes controlling the adjustments in scope utilizing a change control process. This includes:

  • Ceaseless checking of the status and extent of the venture
  • Contrast the genuine presentation measures and the pattern scope
  • Comprehend the level of degree change and the reason for the change
  • Settling on the activity. Has it to be restorative or preventive?
  • Deal with all the change necessities using a legitimate procedure set up.


The reaction system is Risk Acceptance and Sharing. Its significant that all partners know about this adjustment in scope. The group should know about the change and set themselves up for reconsidering expectations. Considerably higher administration should be prepared to put resources into the gradual cost required for the extension change.

C) zA task plan isn't plainly characterized or comprehended.

Significant group and assets need to set up to gadget a legitimate calendar. Higher administration should be included to pass on the comprehension to the colleagues. This goals' system is Risk Mitigation.

D) Absence of correspondence causing absence of lucidity and disarray.

The explanation behind this hazard can be a ton. It could be social if multicolor groups are a piece of the undertaking. There are no enough bury group gatherings to comprehend colleagues/partner issues, and so forth. Right now, need to initially distinguish the wellspring of the issue and fix it. Little changes should be granted on to the group like a make up for losing time meeting, week after week meetings and so forth to impart and see appropriately. The goals' procedure is Risk Mitigation.

E) No power over staff needs.

In the event that staff doesn't know about the needs, venture calendars will get influenced. The alleviation methodology to use here is Risk Communication. In momentary all participants in the undertaking should know about the hazard and can organize in tackling this. In the long haul, association can archive best practices on how these dangers be redressed.

F) Postponement in prior undertaking stages risks capacity to meet fixed date.

Reaction system is Risk Acceptance. The postponement occurred because of unavoidable conditions. The task supervisor ought to acknowledge that be prepared to expect delays in the undertaking finish date. He can assess the hazard and plan for possibility to beat the lost time. Legitimate opportune correspondence should be done to significant specialists about the normal postponement and hazard.

G) Uncertain undertaking clashes not raised in an auspicious way

Tolerating hazard is the reaction procedure. The undertaking chief should know and see how far the substance can run tolerating such a hazard. The procedure of reaction includes investigation and assessment of hazard, utilizing acknowledged standards, correlation with comparative reference frameworks.

H) Contractual worker delays.

Such a hazard happens when the contractual worker determination process was not followed appropriately. Not looking at the temporary worker foundation likewise prompts such issues. The hazard reaction technique ought to be Risk Avoidance. This hazard must be stayed away from at the primary spot by picking a contractual worker who has a demonstrated reputation instead of investigating new ones. Other method for reaction technique of a current temporary worker postponement could be Escalation or Risk Transfer to higher specialists/contractual worker.

I) Included remaining task at hand or time necessities due to new course or arrangement.

The reaction procedure is Risk Acceptance and Sharing. The partners should know about this new course, so appropriate correspondence technique should be set up. The new venture plan additionally should be imparted and groups ought to line up with the new strategy.

J) Partner activity postpones venture.

Hazard Transfer reaction procedure should be utilized. The hazard must be moved to the partner for their activities dependent on the agreement made with the association. The issue must be raised and important hazard move to be started.


Related Solutions

Make a Project of Management Risk Assessment: 1. Make a Qualitative Risk assessment 2. Make Quantitative...
Make a Project of Management Risk Assessment: 1. Make a Qualitative Risk assessment 2. Make Quantitative Risk Assessment and Mitigation
Project Risk Response Risk responses and action steps are defined during the risk response planning phase....
Project Risk Response Risk responses and action steps are defined during the risk response planning phase. Here the project team must plan the actions that will be taken should any identified risk actually materialize. This is typically done for some subset of the total population of risk issues identified—most likely those that are of the highest probability and/or impact. Risks can be both negative (threats) and positive (opportunities). The possible strategies for responding to negative risks include the following: avoid,...
Project Risk Response Risk responses and action steps are defined during the risk response planning phase....
Project Risk Response Risk responses and action steps are defined during the risk response planning phase. Here the project team must plan the actions that will be taken should any identified risk actually materialize. This is typically done for some subset of the total population of risk issues identified—most likely those that are of the highest probability and/or impact. Risks can be both negative (threats) and positive (opportunities). The possible strategies for responding to negative risks include the following: avoid,...
What are the strengths and weaknesses of Qualitative risk assessment?
What are the strengths and weaknesses of Qualitative risk assessment?
Risk Assessment Homework In this assignment, you will perform a qualitative risk assessment, using a template...
Risk Assessment Homework In this assignment, you will perform a qualitative risk assessment, using a template that has been provided below.    A listing of threats has been prepopulated for you. These threats have been categorized by type as shown below:                                                    Threat Origination Category Type Identifier Threats launched purposefully P Threats created by unintentional human or machine errors U Threats caused by environmental agents or disruptions E Purposeful threats are launched by threat actors for a variety of reasons...
pros and cons of risk probability and impact assessment, in Qualitative risk analysis?
pros and cons of risk probability and impact assessment, in Qualitative risk analysis?
Quantitative and Qualitative Risk Assessments What’s the recommendation by the risk assessment team? What are the...
Quantitative and Qualitative Risk Assessments What’s the recommendation by the risk assessment team? What are the final decisions made by HGA management? Justify their decisions based on cost benefit analysis. PLEASE MAKE COPY PASTE AVAILABLE MUST BE 250 WORDS
BALEY CORPORATION PLANNING RISK ASSESSMENT You are in the process of planning for the audit of...
BALEY CORPORATION PLANNING RISK ASSESSMENT You are in the process of planning for the audit of a newly obtained client Baley Corporation, for the year ended December 31, 2017. Baley is regulated by the state utility commission and because it is a publicly traded company the audited financial statements must be filed with the Securities and Exchange Commission (SEC). During the risk assessment you have learned the following: Baley is considerably more profitable than many of its competitors, largely due...
Create a project risk management document for a hair product company using the following headings: planning,identification,qualitative...
Create a project risk management document for a hair product company using the following headings: planning,identification,qualitative analysis,quantitative analysis.response planning,response implementation and monitoring.
what are the tools in Plan Risk response inputs( Risk response tools & techniques )in project...
what are the tools in Plan Risk response inputs( Risk response tools & techniques )in project management that can be used to handle the risk involved in software development Systems on 500 medical records for an orthopedic health clinic?